In Re Designer Doors, Inc.

389 B.R. 832, 2008 Bankr. LEXIS 1836, 2008 WL 2445090
CourtUnited States Bankruptcy Court, D. Arizona
DecidedJune 17, 2008
Docket2:07-BK-03226-RJH
StatusPublished
Cited by4 cases

This text of 389 B.R. 832 (In Re Designer Doors, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Designer Doors, Inc., 389 B.R. 832, 2008 Bankr. LEXIS 1836, 2008 WL 2445090 (Ark. 2008).

Opinion

RANDOLPH J. HAINES, Bankruptcy Judge.

This case raises the question of when an “obligation” to indemnify under a nonresidential lease “arises” for purposes of 11 U.S.C. § 365(d)(3).

*835 I. Facts

The material facts are undisputed. Designer Doors, Inc. (“the Debtor”) leased a property from Lester C. and Jimmy L. Smull Family Trust (“the Landlord”). The Debtor agreed in the lease to keep the property free of any liens 1 arising from “work performed, material furnished, or obligation incurred” by the Debtor on the property. The Debtor also agreed to indemnify 2 the Landlord in case any liens were recorded in connection with the Debtor’s use of the property.

The Debtor subsequently contracted with Palo Verde Dry Wall, Inc. (“Palo Verde”) to make some improvements to the property. The Debtor failed to pay Palo Verde for the work Palo Verde performed on the property. The Debtor then filed this chapter 11 case on July 9, 2007.

Five days after the Debtor filed its petition, Palo Verde recorded a mechanic’s lien against the property. 3 About three months later, but before the Debtor rejected the lease, Palo Verde filed suit against the Landlord seeking to foreclose on the mechanic’s lien, seeking payment of $12,800 plus attorneys’ fees. The Landlord spent $3,992 in attorneys’ fees defending that suit before the lease was rejected by order of this Court effective as of December 14, 2007.

The Landlord has filed an administrative expense claim seeking to have the Debtor pay for a bond to clear Palo Verde’s recorded lien, to pay for the attorney’s fees incurred to defend against the foreclosure suit, and for $15,640 in unpaid postpetition rent. Debtor has responded that the rent will be treated as an administrative claim and paid under the Debtor’s plan, but that the obligations to indemnify against the lien and pay for a bond and attorneys’ fees all arose prepetition and therefore should be treated as general unsecured claims.

II. Analysis of Law

Debtor had two or three separate obligations under this lease that are pertinent to the factual and legal context here: (1) a duty to keep the property free of liens; and (2) a duty to indemnify the Landlord if (a) the Landlord suffered any *836 loss on account of a lien or (b) the Landlord incurred attorneys’ fees defending against a lien. These indemnity obligations included both the costs of defense and the ultimate liability.

Bankruptcy Code 4 § 365(d)(3) provides that “the trustee shall timely perform all the obligations of the debtor ... arising from and after the order for relief under any unexpired lease of nonresidential real property, until such lease is assumed or rejected .... ” This language complicates questions such as the one presented here simply because the Bankruptcy Code does not define the term “obligation,” quite unlike its rather careful definition of “claim.” “The term ‘obligation’ is not defined in the Code, and it is thus apparently used in its commonly understood sense.” 5 Black’s Dictionary defines obligation as “anything that a person is bound to do or forbear from doing, whether the duty is imposed by law, contract, promise, social relations, courtesy, kindness, or morality.” BLACK’S LAW DICTIONARY 1104 (8th ed.2004). Here the Debtor’s duties to the Landlord would certainly be classified as obligations under any conceivable definition because they were duties under a valid contract.

The more difficult question here is when do these obligation arise. Section 365(d)(3) applies only to those obligations that arise between the time the petition is filed and the lease is assumed or rejected.

A. Duty to Keep the Property Free of Liens

Unlike most consensual liens, a mechanics’ and materialmen’s lien arises long before it is recorded. The lien arises from statute 6 and from the labor that is performed or the materials supplied. Here, because Palo Verde performed its labor and supplied its materials prepetition, the lien arose prepetition, even though not perfected until postpetition. 7 Therefore technically the debtor breached its obligation to keep the property free of liens pre-petition. This obligation, and the debtor’s liability to the Landlord for breaching this obligation, certainly continued postpetition, but cannot be said to have arisen only postpetition. It is not unlike prepetition rent that remains in default postpetition — the obligation did not arise postpetition and therefore is not within the scope of § 365(d)(3).

The situation is also analogous to claims arising from debtor/tenant’s damage to the leased property. In National Refracto ries, 8 the question was whether an administrative expense arose under § 365(d)(3) for the cost of repairing damage done to the property prepetition. The lease re *837 quired the debtor to maintain the property clean and in good repair. The court determined that “if the Debtor first brought the abandoned items, including the hazardous materials, onto the Leased Premises post-petition, pre-rejection, the Debtor’s failure to repair the damage and to remove the items of personal property would violate 11 U.S.C. § 365(d)(3).” 9 But because the hazardous materials were located on the premises prepetition, “the Debtors’ obligation to repair it became fixed” prepetition, and therefore was not subject to § 365(d)(3). 10 A similar analysis was adopted in Ames Department Stores, 11 only there the materials on the premises did not violate the lease until they were required to be removed upon termination, and because that was postrejection it also fell outside the scope of § 365(d)(3).

The repair/removal obligation in National Refractories is analogous to this debtor’s agreement to keep the property free of liens. Where the debtor’s breach of its obligation first arises prepetition, it is not an obligation that arises “from and after the order for relief’ so the Landlord is not entitled to administrative expense under § 365(d)(3).

B. Duty to Indemnify

The Debtor’s obligation to indemnify may not be as simple to analyze. First, however, it is useful to recognize that there are at least three different kinds of liabilities whose timing may be at issue in various contexts. The first is when does a cause of action

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Leather Factory Inc.
475 B.R. 710 (C.D. California, 2012)
Reyes v. STANDARD PARKING CORP.
461 B.R. 153 (D. Rhode Island, 2011)
In Re Bh S&B Holdings LLC
401 B.R. 96 (S.D. New York, 2009)
In Re Burival
392 B.R. 793 (D. Nebraska, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
389 B.R. 832, 2008 Bankr. LEXIS 1836, 2008 WL 2445090, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-designer-doors-inc-arb-2008.