In re: Darren Ralph Mann and Phylicia Merrie Mann

United States Bankruptcy Appellate Panel for the Ninth Circuit·Decided June 4, 2020·No. SC-19-1323-BLG·Unpublished

Opinion

FILED

JUN 4 2020

NOT FOR PUBLICATION

SUSAN M. SPRAUL, CLERK

U.S. BKCY. APP. PANEL

OF THE NINTH CIRCUIT

UNITED STATES BANKRUPTCY APPELLATE PANEL OF THE NINTH CIRCUIT

In re: BAP No. SC-19-1323-BLG

DARREN RALPH MANN and PHYLICIA Bk. No. 18-02163-LT MERRIE MANN, Adv. No. 18-90078-CL

Debtors.

DARREN RALPH MANN, Appellant,

v. MEMORANDUM* INTERGULF-JMR (PARC ONE) LLC, Appellee.

Argued and Submitted on May 21, 2020 Filed – June 4, 2020

Appeal from the United States Bankruptcy Court for the Southern District of California

*

This disposition is not appropriate for publication. Although it may be cited for whatever persuasive value it may have, see Fed. R. App. P. 32.1, it has no precedential value, see 9th Cir. BAP Rule 8024-1.

Honorable Christopher B. Latham, Bankruptcy Judge, Presiding

Appearances: Andrew J. Miller of Engel & Miller argued for appellant Darren Ralph Mann; Joseph Louis Oliva of Joseph Oliva & Associates PC argued for appellee Intergulf-JMR (Parc One)

LLC.

Before: BRAND, LAFFERTY, and GAN, Bankruptcy Judges.

INTRODUCTION

Appellant Darren Mann appeals an order granting the motion for summary judgment filed by appellee, Intergulf-JMR (Parc One) LLC ("Intergulf"). Prior to Mann's bankruptcy filing, Intergulf obtained a default judgment against him in the California state court for common law fraud. Intergulf sought to except the debt from Mann's discharge on several theories under § 523(a),1 and later moved for partial summary judgment on its § 523(a)(2)(A) claim based on issue preclusion. Finding that the elements of issue preclusion were met, the bankruptcy court granted the motion. Thereafter, the court entered a final judgment determining that the debt was excepted from Mann's discharge and dismissing Intergulf's remaining claims. We AFFIRM.

1 Unless specified otherwise, all chapter and section references are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, all "Rule" references are to the Federal Rules of Bankruptcy Procedure, and all "Civil Rule" references are to the Federal Rules of Civil Procedure.

I. FACTUAL BACKGROUND AND PROCEDURAL HISTORY A. Prepetition events 1. Background of the parties Mann owned and operated West America Corporation ("West"), a general contractor. In late 2013, Intergulf entered into a contract with West to construct a 172-unit apartment complex. West hired various subcontractors for the project. Intergulf agreed to pay to West, and West agreed to forward to the subcontractors, progress payments based on applications received from West. The intent of these earmarked progress payments was to compensate the subcontractors for work completed in the payment period. During construction, West sent Intergulf applications for progress payments, which Intergulf timely paid to West.

In October 2014, Intergulf discovered that some subcontractors had not been paid by West for work performed on the project, despite Intergulf having made the progress payments to West. West refused to provide Intergulf with an accounting or explanation as to how the progress payments were applied. To the contrary, West and Mann told Intergulf that the subcontractors had in fact been paid. The evidence showed that Intergulf's checks had been cashed by West and Mann, but nothing reflected that any payments had been forwarded to the subcontractors. Mann later told Intergulf's project manager, Brian Buchanan, that he was using Intergulf's funds to pay overhead unrelated to the project.

Soon thereafter, Intergulf terminated the contract with West. Intergulf discovered that West and Mann had misappropriated $1,068,793.24. Intergulf also learned that West and Mann had conspired with certain subcontractors to overcharge Intergulf. For example, to repay some of his outstanding loans to one subcontractor, Mann fabricated work orders to include fictitious charges that were not related to any additional work or materials for the Intergulf project.

2. The state court litigation Intergulf filed suit against West, Mann and others in the California state court asserting multiple causes of action including breach of contract, negligence, and common law fraud ("State Court Action"). Intergulf later filed a second amended complaint, the operative complaint in the case, to include alter ego claims against Mann. In addition to damages caused by West's and Mann's alleged misappropriation, Intergulf also sought damages for their alleged negligence and breach of contract. Intergulf alleged that, during the course of construction and in breach of the contract, West had left installed drywall exposed to the elements for a prolonged period of time, which caused damage to the drywall and to the building's interior. Neither West nor Mann filed an answer to the operative complaint.

Prior to filing the second amended complaint, Intergulf had served West and Mann, through their counsel, with requests for admission ("RFAs"). When they failed to respond, Intergulf moved for and obtained an order

deeming the RFAs admitted on the following: • West was the alter ego of Mann;

• West used funds paid by Intergulf for work performed on the project for purposes unrelated to the project, without Intergulf's knowledge or consent;

• Mann told Intergulf that West diverted Intergulf's funds for purposes unrelated to the project;

• West did not pay subcontractors for work performed on the project after receiving payment from Intergulf for the work, and told Intergulf that the subcontractors were paid all of the money they were owed under West's approved payment applications;

• West conspired with certain subcontractors to create secret profit shelters by using increased bid amounts; the purpose of the profit shelters was to overcharge Intergulf for costs of construction; and West promised to split any profits obtained by the profit shelters with the participating subcontractors;

• West left portions of the project open and exposed to weather, including installed drywall.

One year into the State Court Action, Mann informed Intergulf's counsel that he had been unable to reach his attorney for at least six months, and that he was in the process of retaining new counsel. Intergulf agreed to postpone Mann's deposition so that he could find new counsel. Mann never secured new counsel, refused to sit for deposition, and failed to participate in his own defense.

Approximately 18 months into the State Court Action, Intergulf requested and received an entry of default against West and Mann. Neither West nor Mann sought to have the defaults set aside.

Intergulf then sought a default judgment against West and Mann, supported by 970 pages of documents including a sworn declaration from Buchanan, Intergulf's project manager. With respect to Intergulf's alleged negligence and breach of contract damages, Buchanan stated that, in addition to the damages caused by West's failure to properly install the drywall and protect it from weather, Intergulf was damaged by West's failure to clean up the construction site. Also, due to West's failure to properly schedule and coordinate certain work performed by subcontractors, Intergulf incurred additional expenses having to dig up installed underground electrical lines and re-waterproof decks due to damage caused by scaffolding. In total, Buchanan stated that the damages related to West's negligence and breach of contract were $732,567.03. Adding this amount to the claimed fraud damages of $1,068,793.24, Intergulf's total damages were $1,801,360.27.

Free access — add to your briefcase to read the full text and ask questions with AI

In re: Darren Ralph Mann and Phylicia Merrie Mann, (bap9 2020).

In re: Darren Ralph Mann and Phylicia Merrie Mann (In re: Darren Ralph Mann and Phylicia Merrie Mann) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Federated Department Stores, Inc. v. Moitie
452 U.S. 394 (Supreme Court, 1981)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Grogan v. Garner
498 U.S. 279 (Supreme Court, 1991)
TrafficSchool.com, Inc. v. Edriver Inc.
653 F.3d 820 (Ninth Circuit, 2011)
Lazar v. Superior Court
909 P.2d 981 (California Supreme Court, 1996)
Khaligh v. Hadaegh (In Re Khaligh)
338 B.R. 817 (Ninth Circuit, 2006)
Roussos v. Michaelides (In Re Roussos)
251 B.R. 86 (Ninth Circuit, 2000)
Green v. Kennedy (In Re Green)
198 B.R. 564 (Ninth Circuit, 1996)
Younie v. Gonya (In Re Younie)
211 B.R. 367 (Ninth Circuit, 1997)
Kelly v. Okoye (In Re Kelly)
182 B.R. 255 (Ninth Circuit, 1995)
Gottlieb v. Kest
46 Cal. Rptr. 3d 7 (California Court of Appeal, 2006)
Lucido v. Superior Court
795 P.2d 1223 (California Supreme Court, 1990)
Roussos v. Michaelides
33 F. App'x 365 (Ninth Circuit, 2002)