In re: Darren Ralph Mann and Phylicia Merrie Mann

CourtUnited States Bankruptcy Appellate Panel for the Ninth Circuit
DecidedJune 4, 2020
DocketSC-19-1323-BLG
StatusUnpublished

This text of In re: Darren Ralph Mann and Phylicia Merrie Mann (In re: Darren Ralph Mann and Phylicia Merrie Mann) is published on Counsel Stack Legal Research, covering United States Bankruptcy Appellate Panel for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Darren Ralph Mann and Phylicia Merrie Mann, (bap9 2020).

Opinion

FILED JUN 4 2020 NOT FOR PUBLICATION SUSAN M. SPRAUL, CLERK U.S. BKCY. APP. PANEL OF THE NINTH CIRCUIT

UNITED STATES BANKRUPTCY APPELLATE PANEL OF THE NINTH CIRCUIT

In re: BAP No. SC-19-1323-BLG

DARREN RALPH MANN and PHYLICIA Bk. No. 18-02163-LT MERRIE MANN, Adv. No. 18-90078-CL Debtors.

DARREN RALPH MANN,

Appellant,

v. MEMORANDUM*

INTERGULF-JMR (PARC ONE) LLC,

Appellee.

Argued and Submitted on May 21, 2020

Filed – June 4, 2020

Appeal from the United States Bankruptcy Court for the Southern District of California

* This disposition is not appropriate for publication. Although it may be cited for whatever persuasive value it may have, see Fed. R. App. P. 32.1, it has no precedential value, see 9th Cir. BAP Rule 8024-1. Honorable Christopher B. Latham, Bankruptcy Judge, Presiding

Appearances: Andrew J. Miller of Engel & Miller argued for appellant Darren Ralph Mann; Joseph Louis Oliva of Joseph Oliva & Associates PC argued for appellee Intergulf-JMR (Parc One) LLC.

Before: BRAND, LAFFERTY, and GAN, Bankruptcy Judges.

INTRODUCTION

Appellant Darren Mann appeals an order granting the motion for

summary judgment filed by appellee, Intergulf-JMR (Parc One) LLC

("Intergulf"). Prior to Mann's bankruptcy filing, Intergulf obtained a default

judgment against him in the California state court for common law fraud.

Intergulf sought to except the debt from Mann's discharge on several theories

under § 523(a),1 and later moved for partial summary judgment on its

§ 523(a)(2)(A) claim based on issue preclusion. Finding that the elements of

issue preclusion were met, the bankruptcy court granted the motion.

Thereafter, the court entered a final judgment determining that the debt was

excepted from Mann's discharge and dismissing Intergulf's remaining claims.

We AFFIRM.

1 Unless specified otherwise, all chapter and section references are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, all "Rule" references are to the Federal Rules of Bankruptcy Procedure, and all "Civil Rule" references are to the Federal Rules of Civil Procedure.

2 I. FACTUAL BACKGROUND AND PROCEDURAL HISTORY

A. Prepetition events

1. Background of the parties

Mann owned and operated West America Corporation ("West"), a

general contractor. In late 2013, Intergulf entered into a contract with West to

construct a 172-unit apartment complex. West hired various subcontractors

for the project. Intergulf agreed to pay to West, and West agreed to forward

to the subcontractors, progress payments based on applications received from

West. The intent of these earmarked progress payments was to compensate

the subcontractors for work completed in the payment period. During

construction, West sent Intergulf applications for progress payments, which

Intergulf timely paid to West.

In October 2014, Intergulf discovered that some subcontractors had not

been paid by West for work performed on the project, despite Intergulf

having made the progress payments to West. West refused to provide

Intergulf with an accounting or explanation as to how the progress payments

were applied. To the contrary, West and Mann told Intergulf that the

subcontractors had in fact been paid. The evidence showed that Intergulf's

checks had been cashed by West and Mann, but nothing reflected that any

payments had been forwarded to the subcontractors. Mann later told

Intergulf's project manager, Brian Buchanan, that he was using Intergulf's

funds to pay overhead unrelated to the project.

3 Soon thereafter, Intergulf terminated the contract with West. Intergulf

discovered that West and Mann had misappropriated $1,068,793.24. Intergulf

also learned that West and Mann had conspired with certain subcontractors

to overcharge Intergulf. For example, to repay some of his outstanding loans

to one subcontractor, Mann fabricated work orders to include fictitious

charges that were not related to any additional work or materials for the

Intergulf project.

2. The state court litigation

Intergulf filed suit against West, Mann and others in the California state

court asserting multiple causes of action including breach of contract,

negligence, and common law fraud ("State Court Action"). Intergulf later filed

a second amended complaint, the operative complaint in the case, to include

alter ego claims against Mann. In addition to damages caused by West's and

Mann's alleged misappropriation, Intergulf also sought damages for their

alleged negligence and breach of contract. Intergulf alleged that, during the

course of construction and in breach of the contract, West had left installed

drywall exposed to the elements for a prolonged period of time, which

caused damage to the drywall and to the building's interior. Neither West nor

Mann filed an answer to the operative complaint.

Prior to filing the second amended complaint, Intergulf had served

West and Mann, through their counsel, with requests for admission ("RFAs").

When they failed to respond, Intergulf moved for and obtained an order

4 deeming the RFAs admitted on the following:

• West was the alter ego of Mann;

• West used funds paid by Intergulf for work performed on the project for purposes unrelated to the project, without Intergulf's knowledge or consent;

• Mann told Intergulf that West diverted Intergulf's funds for purposes unrelated to the project;

• West did not pay subcontractors for work performed on the project after receiving payment from Intergulf for the work, and told Intergulf that the subcontractors were paid all of the money they were owed under West's approved payment applications;

• West conspired with certain subcontractors to create secret profit shelters by using increased bid amounts; the purpose of the profit shelters was to overcharge Intergulf for costs of construction; and West promised to split any profits obtained by the profit shelters with the participating subcontractors;

• West left portions of the project open and exposed to weather, including installed drywall.

One year into the State Court Action, Mann informed Intergulf's

counsel that he had been unable to reach his attorney for at least six months,

and that he was in the process of retaining new counsel. Intergulf agreed to

postpone Mann's deposition so that he could find new counsel. Mann never

secured new counsel, refused to sit for deposition, and failed to participate in

his own defense.

5 Approximately 18 months into the State Court Action, Intergulf

requested and received an entry of default against West and Mann. Neither

West nor Mann sought to have the defaults set aside.

Intergulf then sought a default judgment against West and Mann,

supported by 970 pages of documents including a sworn declaration from

Buchanan, Intergulf's project manager. With respect to Intergulf's alleged

negligence and breach of contract damages, Buchanan stated that, in addition

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federated Department Stores, Inc. v. Moitie
452 U.S. 394 (Supreme Court, 1981)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Grogan v. Garner
498 U.S. 279 (Supreme Court, 1991)
TrafficSchool.com, Inc. v. Edriver Inc.
653 F.3d 820 (Ninth Circuit, 2011)
Lazar v. Superior Court
909 P.2d 981 (California Supreme Court, 1996)
Khaligh v. Hadaegh (In Re Khaligh)
338 B.R. 817 (Ninth Circuit, 2006)
Roussos v. Michaelides (In Re Roussos)
251 B.R. 86 (Ninth Circuit, 2000)
Green v. Kennedy (In Re Green)
198 B.R. 564 (Ninth Circuit, 1996)
Younie v. Gonya (In Re Younie)
211 B.R. 367 (Ninth Circuit, 1997)
Kelly v. Okoye (In Re Kelly)
182 B.R. 255 (Ninth Circuit, 1995)
Gottlieb v. Kest
46 Cal. Rptr. 3d 7 (California Court of Appeal, 2006)
Lucido v. Superior Court
795 P.2d 1223 (California Supreme Court, 1990)
Roussos v. Michaelides
33 F. App'x 365 (Ninth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
In re: Darren Ralph Mann and Phylicia Merrie Mann, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-darren-ralph-mann-and-phylicia-merrie-mann-bap9-2020.