In Re Cranston

387 B.R. 480, 2008 Bankr. LEXIS 557, 2008 WL 619185
CourtUnited States Bankruptcy Court, D. Maryland
DecidedMarch 3, 2008
Docket19-11283
StatusPublished
Cited by3 cases

This text of 387 B.R. 480 (In Re Cranston) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Cranston, 387 B.R. 480, 2008 Bankr. LEXIS 557, 2008 WL 619185 (Md. 2008).

Opinion

MEMORANDUM DECISION IN SUPPORT OF ORDER OVERRULING, IN PART, OBJECTION TO THE CLAIM OF ROBERT F. LEAGAN, MARY LEAGAN AND JEANNE C. KLINE [CLAIM NO. 16]

WENDELIN I. LIPP, Bankruptcy Judge.

The Court has before it the Debtor’s Objection to Claim filed by Robert F. Leagan, Mary Leagan and Jeanne C. Kline (collectively, the “Claimants”) [62] and the amended Response thereto filed by the Claimants [70]. This matter was first heard by this Court on March 9, 2007. At the conclusion of the March 9, 2007 hearing, the Court asked the parties to file briefs detailing the costs of completion of the project to support the damages claimed by the Claimants and the Debtor’s response to each item (hereinafter, referred to as the “Parties’ Damages Calculations”). The Parties’ Damages Calculations were filed and a continued trial was set for June 8, 2007, at which time this matter was assigned to the Bankruptcy Dispute Resolution Program, with the consent of the parties. A dispute resolution conference was held on October 10, 2007; however, the parties were unable to reach an agreement regarding the amount of damages to be awarded to the Claimants. Accordingly, the trial was rescheduled and the final hearing was held on October 19, 2007.

The Court has reviewed the pleadings submitted by the parties, listened to the testimony presented at the hearings and examined the Parties’ Damages Calculations 1 and the exhibits admitted into evidence. For the reasons set forth below, the Claimants’ Claim shall be allowed as an unsecured claim in the amount of $79,210.48.

I. Background

The Claimants filed a proof of claim in the Debtor’s bankruptcy cáse asserting a secured claim in the amount of $300,000.00 for breach of contract (the “Claim”). The contract forming the basis of the Claim was a New Home Agreement of Sale dated May 2, 2002, under which the Claimants retained CCServices, Inc. (“CCServices”) to construct a new home for the Claimants in Chesapeake Beach, Maryland (the “Contract”). The Debtor is the president and sole shareholder of CCServices. There is no dispute that CCServices breached the Contract, resulting in the Claimants filing a Complaint for Damages and Injunctive Relief (the “State Court Complaint”) against CCServices and the Debtor, individually, in the Circuit Court for Calvert County, Maryland (the “Circuit Court”) on January 22, 2004.

On November 22, 2004, while the Circuit Court litigation was pending, the Debtor filed a petition for bankruptcy relief under Chapter 13 of the United States Bankrupt *484 cy Code. 2 The Claimants timely filed the Claim on January 17, 2005. Attached to the Claim as supporting documentation was a one-page Order entered by the Circuit Court on October 30, 2004, granting a default judgment in favor of the Claimants and against the Debtor and CCServices. Thereafter, on October 27, 2005, the Circuit Court issued an Opinion and Order entering judgment against the Debtor, individually, and CCServices, jointly and severally, and in favor of the Claimants, in the amount of $122,008.52, and in favor of Timothy P. Leahy, Esq., counsel to the Claimants, in the amount of $14,452.50 for attorneys fees. The total amount awarded was $136,461.02 (the “Circuit Court Judgment”). 3 At the time the Claimants filed the Claim, the Circuit Court Judgment had not been liquidated. Although the Claimants have never filed an amended proof of claim, at trial, the Claimants initially limited the Claim to the amount of the Circuit Court Judgment and ultimately reduced the Claim to $112,389.02. The Debtor concedes that he breached the Contract, but asserts that the Claim should be established at $16,149.57, including $1,137 for a home warranty, plus reasonable attorney’s fees.

II. Discussion

A proof of claim is prima facie evidence of the validity and amount of the claim. Fed. R. Bankr. P. 3001(f); see In re Lewis, 363 B.R. 477, 481-82 (Bankr.D.S.C.2007). If an objection to a proof of claim is raised, the objecting party bears the burden of going forward to produce evidence sufficient to negate the prima facie validity of the filed claim. See id. (citing In re Allegheny Intern., Inc., 954 F.2d 167, 173 (3d Cir.1992)). Once the objecting party produces evidence sufficient to negate the validity of the claim, “[t]he ultimate burden of persuasion remains on the claimant to demonstrate by a preponderance of evidence that the claim deserves to share in the distribution of the Debtor’s assets.” Id.

The dispute in this case concerns the amount of damages to be awarded to the Claimants for CCServices’ breach of the Contract. 4 The Claimants filed the Claim alleging damages in the amount of $300,000.00. The Debtor filed an objection to the Claim and has produced evidence sufficient to negate the prima facie validity of the Claim. Furthermore, the Claimants have since conceded that the Claim is for a lesser amount. The burden is on the Claimants to prove by a preponderance of evidence the validity of the Claim.

“The amount of damages recoverable for breach of contract is that which will place the injured party in the mone *485 tary position he would have occupied if the contract had been properly performed.” Hall v. Lovell Regency Homes Ltd. P’ship, et al., 121 Md.App. 1, 708 A.2d 344, 349 (1998). In a breach of contract action stemming from a real estate construction contract, “[t]he primary measure of damages is the cost of repairing or remedying the defect.” Id. Accordingly, the major component of the damages recoverable by the Claimants is the cost they incurred in completing the construction of their new home as contemplated by the Contract and any agreed upon amendments thereto.

A. Completion Costs

The Contract price for the construction of the Claimants’ home was $204,000.00. The construction project was funded through a construction loan obtained from 1st Mariner Bank. Disbursements under the construction loan were made pursuant to a Construction Loan Draw Schedule that provided for six draws to be made after inspection by an officer of 1st Mariner Bank. The parties agree that CCServices completed the work necessary for the release of the first three draws totaling $112,000.00. It is also undisputed that CCServices performed additional work not contemplated by the Contract. This supplemental work entitled CCSer-vices to an additional payment of $11,072.00, which increased the total Contract price to $215,072.00. The total amount paid directly to CCServices for work performed on the construction project was $118,272.00.

The Claimants presented evidence that the cost of completion of the project after the breach by CCServices was $146,479.24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
387 B.R. 480, 2008 Bankr. LEXIS 557, 2008 WL 619185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-cranston-mdb-2008.