In Re Corbin Park, L.P.

441 B.R. 370, 2010 Bankr. LEXIS 4940, 2010 WL 5573683
CourtUnited States Bankruptcy Court, D. Kansas
DecidedDecember 16, 2010
Docket19-20242
StatusPublished
Cited by1 cases

This text of 441 B.R. 370 (In Re Corbin Park, L.P.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Corbin Park, L.P., 441 B.R. 370, 2010 Bankr. LEXIS 4940, 2010 WL 5573683 (Kan. 2010).

Opinion

*373 ORDER SETTING PRIORITY BETWEEN MECHANIC’S LIEN CLAIMANTS AND MORTGAGEE

ROBERT D. BERGER, Bankruptcy-Judge.

The sole issue on trial is the determination of priority between the mechanic’s lien claimants and the mortgagee led by Bank of America, N.A. as administrative agent for Bank of America, N.A., U.S. Bank N.A., TierOne Bank, Regions Bank, and Compass Bank (“BOA”). The Court has jurisdiction to hear this matter. 1 Based upon the facts and arguments presented as well as pertinent legal authority, the Court finds BOA has priority over the mechanic’s lien claimants and hereby enters the following findings of fact and conclusions of law pursuant to Fed. R. Bank. P. 7052.

Findings of Fact 2

A. The Parties

Debtor acquired part of a 97-acre, partially developed, shopping center known as Corbin Park on October 8, 2008. 3 Slaggie Architects, Inc., provided Debtor with design services. Brown Commercial Construction Company was a general contractor. O’Donnell & Sons Construction Co., Inc., and McCorkendale Construction, Inc., were two of Brown’s subcontractors. Ball Kelly, LLC, d/b/a Taylor Kelly, LLC, was a second general contractor. BOA was Debtor’s lender.

Corbin Park is comprised of multiple tracts now owned by different entities: Debtor, J.C. Penney Properties, Inc., Von Maur, Inc., and Overland Park Loft Hotels, LLC (“NYLO”). 4 Debtor did not take title to the Von Maur site, the J.C. Penney site, or the NYLO Hotel site. 5 The mechanic’s lien claimants assert their liens attach to the J.C. Penney tract as well as Debtor’s.

B. Contracts and Construction Prior to October 8, 2008

The prior owners of Corbin Park were 135 Metcalf, LLC, and State Line, LLC 6 (collectively, “135 Metcalf’). 135 Metcalf began developing the property in 2004 through a related entity called Cormac Company. Cormac was essentially 135 Metcalfs in-house developer and agent. Cormac had also hired Slaggie, Brown, O’Donnell and McCorkendale under separate contracts, either verbal or written, to perform services at Corbin Park between *374 2004 and 2008. Construction at Corbin Park has been plainly visible since at least 2007.

Slaggie’s involvement began in 2004 with its predecessor, Jantsch, Slaggie & Slag-gie. When Slaggie started its own firm, it entered into a verbal contract with 135 Metcalf and later entered into a written agreement.

Brown’s employment began in 2007 pursuant to an oral agreement and on a “must do,” not “would like to do,” basis. 7 The scope of Brown’s employment was to ready the land for vertical construction, with the primary goal to prepare the Von Maur and J.C. Penney pad sites. 8 Brown, in turn, hired O’Donnell and McCorkendale for grading, underground utilities, and road work. Brown’s and 135 Metcalfs contractual relationship consisted of a series of job orders. 9 Brown invoiced 135 Metcalf monthly. Brown’s invoices stated a contract total of $19,543,008; however, Brown presented no evidence 135 Metcalf ever contracted with Brown beyond its immediate need for preliminary site preparation work on a cash-only basis. A representative of 135 Metcalf referred to the $19,543,008 as a master budget, not a contract price with Brown. 10 By September 2008, Brown’s and its subcontractors’ work was winding down. An owner representative described Brown’s work as “specific to sitework completed on the Von Maur parcel [and] a very small amount of work completed on the J.C. Penney’s parcel.” 11 As for the rest of the site in September 2008, no construction work was being performed elsewhere. 12 O’Donnell invoices dated September 2008 are marked as ‘Von Maur Sitework.” McCorkendale invoices are marked as repair jobs and work at the J.C. Penney site. During this time, Brown only invoiced for site supervision, and a Brown employee testified he was performing erosion control and safety fencing. A verified land survey dated September 25, 2008, notes the only work ongoing at that time was on the Von Maur and J.C. Penney sites.

C. The Ownership Change

By February 2008, 135 Metcalf and Cor-mac could no longer fund the construction and advised Slaggie and Brown they would need private money or a construction loan to continue. In March 2008, Slaggie and Brown participated in meetings and presentations hosted by 135 Metcalf to attract investors and lenders. In April 2008, 135 Metcalf stopped paying the contractors.

In April 2008, Invesco Ltd. (“Invesco”) 13 and BOA emerged as the new sources of funds for Corbin Park. Invesco would eventually invest at least $38 million, and BOA would agree to advance up to $107 million. However, Invesco did not make a capital contribution to 135 Metcalf. Instead, together with Cormac, it formed the Debtor on September 8, 2008. In August 2008, 135 Metcalf notified its contractors it would be closing its contracts with them, and the contractors would be required to enter into new contracts with Debtor.

*375 The evidence establishes the contractors had actual knowledge of the ownership change prior to Debtor’s formation and the BOA closing. In August 2008, 135 Metcalf advised Slaggie that Invesco and BOA required design work going forward on “BOA’s collateral” to be under a new, separate contract with Debtor, and the existing contract with 135 Metcalf would “close out.” 14 Likewise, 135 Metcalf advised Brown it was required to enter into new contracts with Debtor. In April 2008, Brown, at Invesco’s request, had already sent BOA financial information about Brown, and Brown named BOA as a loss-payee on its insurance for Corbin Park. Slaggie and Brown began contract negotiations with Invesco in the summer of 2008.

By September 2008, 135 Metcalf began winding down its involvement with Corbin Park. Contractors and subcontractors were slowing or stopping work because of non-payment and were calling 135 Metcalf often demanding payment. 135 Metcalf advised ah contractors they would be paid at closing and requested their bills for work performed so they could be paid. As the closing date was delayed, Slaggie and Brown continued to provide bills. 15 Both Slaggie and Brown witnesses testified they understood the bills were requested so all outstanding work could be paid out of closing proceeds.

D. The Closing

On October 8, 2008, 135 Metcalf conveyed the real property to Debtor and J.C. Penney.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
441 B.R. 370, 2010 Bankr. LEXIS 4940, 2010 WL 5573683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-corbin-park-lp-ksb-2010.