Brown Commercial Construction Co. v. Corbin Park, L.P. (In Re Corbin Park, L.P.)

470 B.R. 573, 2012 WL 1574359
CourtBankruptcy Appellate Panel of the Tenth Circuit
DecidedMay 7, 2012
DocketBAP KS-10-084, KS-10-085, KS-10-086, KS-10-088, KS-11-001, KS-11-004; Bankruptcy 10-20014
StatusPublished
Cited by1 cases

This text of 470 B.R. 573 (Brown Commercial Construction Co. v. Corbin Park, L.P. (In Re Corbin Park, L.P.)) is published on Counsel Stack Legal Research, covering Bankruptcy Appellate Panel of the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brown Commercial Construction Co. v. Corbin Park, L.P. (In Re Corbin Park, L.P.), 470 B.R. 573, 2012 WL 1574359 (bap10 2012).

Opinion

CORNISH, Chief Judge.

Two general contractors and four subcontractors appeal the bankruptcy court’s order determining that, under Kansas law, the interest of a construction lender/mortgagee in a retail shopping center development has priority over their mechanic’s lien claims. Having thoroughly reviewed the record and applicable law, we conclude that the bankruptcy court committed no *577 reversible error in determining the priority of interests between these claimants. Therefore, we must affirm the bankruptcy court’s order.

I. BACKGROUND FACTS 1

Debtor Corbin Park, L.P. (“Debtor”) owns a large portion of a partially developed 97-acre shopping center known as “Corbin Park” (the “Property”), 2 which is located at the intersection of Metcalf Avenue and West 135th Street in Overland Park, Kansas. Debtor acquired the Property from previous owners and developers State Line, LLC and 135 Metcalf, LLC (collectively “Metcalf’). Metcalf began developing the Property in 2004 through a related entity called Cormac Company (“Cormac”), 3 and hired appellant Slaggie Architects, Inc. (“Slaggie”) to provide the design. In 2007, Metcalf hired appellant Brown Commercial Construction Co. (“Brown”) as its general contractor to ready the Corbin Park site for vertical construction. Pursuant to the verbal and written agreements between Metcalf and Brown, appellants O’Donnell & Sons Construction Co., Inc. (“O’Donnell”) 4 and McCorkendale Construction, Inc. (“McCorkendale”) were hired as subcontractors for grading, underground utilities, and road work on the Property. 5 Construction and improvements were plainly visible at the Corbin Park site beginning in 2007.

In February 2008, Metcalf advised Slag-gie and Brown that it was no longer able to fund the construction, and that new private investment and/or a construction loan would be necessary in order to continue the project. In March 2008, Metcalf held meetings and made presentations to attract investors in which both Slaggie and Brown participated. In April 2008, Met-calf stopped paying its contractors. About the same time, appellee Bank of America (“BOA”) and Invesco Ltd. (“Invesco”) emerged as potential new funding sources for the project. In August 2008, anticipating the sale of Corbin Park, Metcalf informed its contractors that it would be closing its contracts with them, and that they would be required to enter into new contracts with the purchaser. Slaggie and Brown then began contract negotiations with Invesco.

Invesco did not invest funds in Metcalf directly. Instead, on September 8, 2008, *578 Invesco and Metcalfs in-house agent Cor-mac formed Debtor, a new limited partnership, for the purpose of purchasing the Property. 6 After formation of Debtor, but prior to closing of the sale of the Property, Brown and Slaggie entered into new written agreements with Debtor. Slaggie entered into a new contract with Debtor having an effective date of September 29, 2008. Brown required its subcontractors to rebid their work so it could offer Debtor a guaranteed maximum price covering the buildings and remaining site work. Debt- or and Brown then executed two written contracts, one a construction contract and the other a site administration contract. The contracts were signed by Brown on September 23, 2008, and by Debtor on September 30, 2008, but had an effective date of September 16, 2008. Notwithstanding the effective date of the contracts, the construction commencement date was dependent upon a written notice to proceed from Debtor. Additionally, Brown could not accommodate the entire scope of work on the Corbin Park project because of its bonding capacity limitations. Therefore, Debtor entered into two, new written contracts with a second general contractor, Taylor Kelly. 7

The sale closed on October 8, 2008, and Metcalf conveyed the Property to Debtor. Other pieces of Corbin Park were conveyed to J.C. Penney Properties, Inc., Von Maur, Inc., and Overland Park Loft Hotels, LLC. 8 On the same day, Debtor and BOA executed a construction loan agreement, together with all agreements necessary to secure the financing for continuation of the Corbin Park project. The next day, Debtor sent written notice to proceed with construction under the contracts to Brown and Taylor Kelly. BOA recorded its mortgage on October 10, 2008. Funds from the BOA loan proceeds and Invesco’s capital investment were used to pay off an existing mortgage on the Property and most of Metcalfs costs for the pre-existing improvements, which included the invoices submitted by Brown and its subcontractors for work performed up to August 24, 2008, under the contracts with Metcalf. None of the contractors filed a mechanic’s lien of record against the Property with respect to work performed under contract with Metcalf.

Construction on the Property continued into late summer of 2009 until Debtor failed to make payments. Brown issued a stop work notice to its subcontractors on August 6, 2009. 9 Brown and its subcontractors filed mechanic’s liens against the Property in September and October 2009. 10 Several contractors filed mechanic’s lien enforcement actions in Kansas state court. 11 Debtor then filed its present Chapter 11 petition on January 5, 2010.

BOA quickly filed a motion for emergency relief from stay, or in the alternative to winterize Debtor’s property and receive a priority claim and lien. 12 The contractors objected, and on February 9, 2010, Debtor filed a motion to establish procedures for the resolution of the mechanic’s lien claims *579 and other interests against property of the estate. 13 On March 8, 2010, the bankruptcy court entered an order establishing procedures for resolving the mechanic’s lien claims against the Property. 14

After discovery and briefing, the bankruptcy court began a five-day evidentiary trial on November 1, 2010, during which it admitted 30 exhibit notebooks containing thousands of pages. The mechanic’s hen claimants argued they began work under their September 2008 contracts with Debt- or prior to the filing of BOA’s mortgage. They also argued that the change in ownership of the Property was inconsequential, and thus they were first on site working under one, continuous contract, giving them first priority. BOA argued that all parties knew of and shared a common intent for the mechanic’s lien claimants to be paid in full for work performed under contract with prior owner Metcalf, and that BOA would loan Debtor ongoing construction funds only in exchange for fresh start and a first priority lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
470 B.R. 573, 2012 WL 1574359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brown-commercial-construction-co-v-corbin-park-lp-in-re-corbin-park-bap10-2012.