This text of 384 B.R. 282 (In Re Cook) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Cook, 384 B.R. 282, 2008 Bankr. LEXIS 131, 2008 WL 141659 (Ala. 2008).

Opinion

MEMORANDUM OPINION AND ORDER

JAMES J. ROBINSON, Bankruptcy Judge.

This matter came before the Court on the Motion for Relief From Stay (the “Motion”) filed by Bobby Dale Welch Construction Company, L.L.C. (“Welch”). The Court has jurisdiction to hear this matter pursuant to 28 U.S.C. §§ 157 and 1334, and the General Order of Reference, as amended, entered by the United States District Court for the Northern District of Alabama. This is a core proceeding pursuant to 28 U.S.C. § 157(b)(2); therefore, the Court has authority to enter a final order. For the reasons stated below, the Court is denying the relief sought in the Motion. In compliance with Rule 7052(a) of the Federal Rules of Bankruptcy Procedure, 1 the following shall constitute the Court’s findings of fact and conclusions of law.

FINDINGS OF FACTS:

The facts are undisputed and for the most part can be taken from the Motion and the Exhibits thereto, and the pleadings and other records maintained in the Court’s file. On April 29, 2005, Dianna Phillis Cook (the “Debtor”) and Welch entered into a Contractor Agreement (Exhibit A to the Motion, and herein the “Agreement”), 2 under the terms of which Welch was to construct a home on the Debtor’s property located in Etowah County, Alabama (the “Property”). The Debtor allegedly failed to pay the sums due under the Agreement, and on December 12, 2005, Welch filed a Lien (Exhibit B to the Motion, and herein the “Verified Statement of Lien”) with the Office of the Judge of Probate of Etowah County, Alabama. In the Verified Statement of Lien, Welch claimed a mechanic’s lien on the Property *286 “to secure an indebtedness of $73,275.41 with interest from the 29th day of April, 2005, for materials supplied pursuant to the contract for construction of a new home .... ”

The Agreement contained an arbitration provision stating, “All disputes hereunder shall be resolved by binding arbitration in accordance with the rules of the American Arbitration Association.” Pursuant to this provision, on June 14, 2006, Welch made a Demand for Arbitration (Exhibit C to the Motion, and herein the “Arbitration Demand”) naming the Debtor as respondent. In the Arbitration Demand, Welch inserted $98,112.76 as the “DOLLAR AMOUNT OF CLAIM,” and described “OTHER RELIEF SOUGHT” as “Plus interest, attorneys’ fees & costs.” The Arbitration Demand described the dispute as involving “an agreement for the construction of a home,” and the Debtor’s refusal to pay the amounts due to Welch. There was no mention in the Arbitration Demand of any claim for a mechanic’s lien, although one of the 43 exhibits described on Welch’s Exhibit List in the arbitration proceedings was listed as a “Lien recorded with Probate Judge of Etowah County.”

An arbitration proceeding was conducted on May 2, 2007, and on May 11, 2007, the arbitrator handed down his Award of Arbitrator (Exhibit D to the Motion, and herein the “Arbitration Award”) in which he found Welch was entitled to recover $98,112.76 from the Debtor for sums due under the Agreement, plus interest at 12% from July 1, 2007; the arbitrator apportioned the fees and expenses of the arbitration between the parties. There was no mention of any mechanic’s lien securing the Arbitration Award, and the last sentence of the Arbitration Award read, “This award is in full settlement of all claims submitted to the arbitrator, and all other claims and counterclaims of the parties not expressly granted herein are denied.”

On May 22, 2007, Welch filed with the Circuit Court of Etowah County, Alabama an Application to Confirm Arbitration Award (Exhibit E to the Motion, and herein the “Circuit Court Application”). In the Circuit Court Application, Welch asked the circuit court to confirm the “Award as enforceable as a judgment upon which execution may issue.” There was no request in the Circuit Court Application for the enforcement of a mechanic’s lien or any mention of a lien securing the Arbitration Award. Apparently, the circuit court entered an order dated May 22, 2007 granting the relief sought by Welch in the Circuit Court Application; however, this Court was not furnished with a copy of the May 22, 2007 Order.

The Debtor filed her chapter 7 bankruptcy petition on May 31, 2007. On September 24, 2007, Welch filed a Motion to Amend Petition and Order Confirming Arbitration Award (Exhibit F to the Motion, and herein the “Amended Petition”). In the Amended Petition, Welch recognized that neither the Circuit Court Application nor the circuit court’s order granting such Application made any mention of the Arbitration Award being secured by a mechanic’s lien, and asked the circuit court to amend its order of May 22, 2007 “to reduce to judgment [Welch’s] claim for a mechanic’s lien against the property of the [Debt- or] described in the attached notice of lien.... ” Because the automatic stay was and remains in effect, this Court assumes the circuit court did not enter an order on the Amended Petition or any further orders relating to the Arbitration Award or Welch’s sought-after mechanic’s lien.

Finally, Welch filed with this Court, a pleading titled Supplemental Authorities in Support of Motion For Relief From Stay (the “Supplement”) in which Welch ar *287 gued, “The bankruptcy court should abstain from deciding the perfection issue to allow the state court or the arbitrator to complete the award or resolve the ambiguity.” This Court interprets the Motion and the Supplement as together requesting relief from the stay or abstention by this Court, to allow Welch not only to take the steps necessary to perfect or maintain his mechanic’s lien under applicable state law, but also to allow the state circuit court to go forward with the establishment and enforcement of the lien, which will require an adjudication of the validity and extent of the lien. 3

On July 30, 2007, the Chapter 7 Bankruptcy Trustee in this case, Rocco J. Leo (the “Trustee”), filed a Final Report of Trustee in No Asset Case; however, on August 6, 2007, the Trustee filed a Notice of Withdrawal of Final Report. Thus, the Property remains property of the bankruptcy estate under Section 1306 of the Bankruptcy Code. 4

CONCLUSIONS OF LAW:

Relief From Automatic Stay

Welch was an original, or general contractor under the Agreement with the Debtor. A general contractor is required to take two steps to maintain his inchoate mechanic’s lien for any unpaid balance due on a construction contract involving Alabama real property. First, he must file a verified statement of lien in proper form and containing the statutorily required information with the office of the judge of probate of the county where the construction project is located. 5 AlaCode § 35-11-213 (1975);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Nebraska, 2026
Portage Park Capital, LLC v. A.L.L. Masonry Construction Co.
2024 IL App (1st) 240344 (Appellate Court of Illinois, 2024)
In re: John Badea
Ninth Circuit, 2018
In re Jefferson County
474 B.R. 228 (N.D. Alabama, 2012)
In Re Jefferson County, Ala.
465 B.R. 243 (N.D. Alabama, 2012)
In Re Means
454 B.R. 636 (D. South Carolina, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
384 B.R. 282, 2008 Bankr. LEXIS 131, 2008 WL 141659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-cook-alnb-2008.