In Re City of Virginia Beach, Commonwealth of Virginia, Amicus Curiae

42 F.3d 881, 40 ERC (BNA) 1058, 1994 U.S. App. LEXIS 36200, 1994 WL 709574
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 22, 1994
Docket94-1904
StatusPublished
Cited by19 cases

This text of 42 F.3d 881 (In Re City of Virginia Beach, Commonwealth of Virginia, Amicus Curiae) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re City of Virginia Beach, Commonwealth of Virginia, Amicus Curiae, 42 F.3d 881, 40 ERC (BNA) 1058, 1994 U.S. App. LEXIS 36200, 1994 WL 709574 (4th Cir. 1994).

Opinion

*883 OPINION

NIEMEYER, Circuit Judge:

The City of Virginia Beach, Virginia, petitions this court for a writ of mandamus, pursuant to 28 U.S.C. § 1651, to compel the Federal Energy Regulatory Commission (FERC) to enter, by a date certain,^ final decision on an application for approval of a water pipeline from Lake Gaston, located on the North Carolina-Virginia border, to Virginia Beach. The petition, which is an interlocutory request for relief, essentially states that FERC is unnecessarily delaying entry of its decision on this long-pending project for arbitrary and capricious reasons. Although we share, to some extent, Virginia Beach’s concerns about the administrative burdens imposed on this project and, in particular, about the delay experienced in obtaining FERC’s decision, we deny the petition, relying in large part on the assurances given to us by FERC, both at oral argument and thereafter.

In July 1983, Virginia Beach applied for a permit from the Army Corps of Engineers, as required by the Rivers and Harbors Appropriation Act of 1899 and the Clean Water Act, to construct a pipeline from Lake Ga-ston to Virginia Beach to carry 60 million gallons of water per day for use by the people of Virginia Beach. This permit was approved in early 1984. Virginia Beach then approached Virginia Electric and Power Company (VEPCO), which held a license from FERC to construct and operate Lake Gaston as a hydropower project, to request that VEPCO file an application with FERC for approval to use the water and its surroundings at Lake Gaston for the pipeline project. VEPCO, which had agreed to provide Virginia Beach with the necessary easements at Lake Gaston, nevertheless declined to file an application with FERC until the Army Corps of Engineers’ permit had been The history of judicial review of that permit, extending from 1984 until 1991, is recounted in our earlier opinions. See Roanoke River Basin Ass’n v. Hudson, 940 F.2d 58 (4th Cir.1991), cert. denied, — U.S. -, 112 S.Ct. 1164, 117 L.Ed.2d 411 (1992); State of North Carolina v. City of Virginia Beach, 951 F.2d 596 (4th Cir.1991). affirmed by the courts.

In February 1991, seven years after Virginia Beach obtained its permit from the Army Corps of Engineers, VEPCO submitted its application to FERC for permission to transfer those necessary easements at Lake Ga-ston to Virginia Beach. For almost two years thereafter, FERC stayed its hand, suspending processing of VEPCO’s application while the Department of Commerce considered an objection made by North Carolina that the proposed pipeline project was inconsistent with North Carolina’s Coastal Zone Management Program. 1 Yet 18 months later, FERC concluded, reversing an earlier position taken by its staff and adopting a position contrary to other agencies that had reviewed the project, that it must draft an environmental impact statement (EIS), which it expected would be completed by June 30, 1995 (about four and one-half years after FERC initially received VEPCO’s application). Upon the announcement of this decision in July 1994, Virginia Beach filed this petition, generally contending that its vital water project “continues to be egregiously and unreasonably delayed” by FERC’s arbitrary and capricious decision to prepare an EIS after having initially concluded, in light of past reviews of the project, that an EIS was not necessary. Virginia Beach’s petition for a writ of mandamus requests an order from us directing FERC to enter a final decision on VEPCO’s application no later than August 25, 1994, a date that we allowed to pass when we scheduled oral argument. *884 Virginia Beach contends that the writ is imperative “to alleviate a public water supply crisis that threatens the health and safety of nearly one million people and the operational readiness of the largest naval complex in the entire free world.”

Virginia Beach rests its petition on an alleged violation of the Administrative Procedure Act, 5 U.S.C. § 555(b), which mandates that an agency act to conclude matters presented to it “within a reasonable time.” It argues that FERC cannot be acting within a reasonable time when it consumes substantial periods for the pursuit of actions that are arbitrary and capricious. Virginia Beach maintains in particular (1) that FERC has ignored previous environmental analyses conducted by the Army Corps of Engineers and the Secretary of Commerce on the same environmental issues; (2) that FERC’s decision to prepare an EIS is not supported by its own underlying analysis; and (3) that the stated “uncertainty"’ about future consumptive water uses and resulting cumulative impacts on the lower Roanoke River is not a legitimate reason to require the preparation of an EIS. Virginia Beach seeks interlocutory appellate review to “compel agency action unlawfully withheld or unreasonably delayed.” 5 U.S.C. § 706(1).

FERC responds to this petition, noting that the various steps it pursued in the administrative process were legal and that it engaged in no “unwarranted delay in processing VEPCO’s application.” FERC noted that the principal portion of the delay was attributable to a stay pending review by the Secretary of Commerce on North Carolina’s coastal zone objection and that this deference was “nothing other than the routine application of Commission policy and procedure.” It insists that other actions pursued by FERC were also consistent with normal agency procedures. Finally, FERC states that it “has proceeded with dispatch,” upon deciding to prepare an EIS, and has instructed its staff to prepare the EIS “as expeditiously as feasible” and “on a priority basis.” FERC has set June 30, 1995, as a firm deadline for completing the EIS. At argument, FERC continued to assure the court of the project’s high priority, and subsequent to argument FERC advised the court that it has scheduled the release of a draft EIS in February 1995 and expects that a final EIS will be completed in the second calendar quarter of 1995.

Under the All Writs Act, we have the power to issue “all writs necessary or appropriate in aid of [our] ... jurisdiction[ ],” 28 U.S.C. § 1651(a), and because we have exclusive jurisdiction of petitions for final review of FERC decisions, we have jurisdiction to consider interlocutory relief. See 16 U.S.C. § 825i. See also Virginia Dep’t of Educ. v. Riley, 23 F.3d 80 (4th Cir.1994). Whether we exercise the power to grant a petition for writ of mandamus is, however, another question entirely.

It is well established that the remedy of mandamus “is a drastic one, to be invoked only in extraordinary situations.” Kerr v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ahmed v. Bitter
S.D. Texas, 2024
Palacio v. Berryhill
W.D. North Carolina, 2019
State of South Carolina v. United States
907 F.3d 742 (Fourth Circuit, 2018)
Skalka v. Johnson
246 F. Supp. 3d 147 (District of Columbia, 2017)
South Carolina v. United States
243 F. Supp. 3d 673 (D. South Carolina, 2017)
Saleem v. Keisler
520 F. Supp. 2d 1048 (W.D. Wisconsin, 2007)
State v. Libby
Vermont Superior Court, 2005
Natural Resources Defense Council, Inc. v. Fox
93 F. Supp. 2d 531 (S.D. New York, 2000)
United States v. Wiggins
50 F. Supp. 2d 512 (E.D. Virginia, 1999)
Yue Yu v. Brown
36 F. Supp. 2d 922 (D. New Mexico, 1999)
Friends of the Bow v. Thompson
124 F.3d 1210 (Tenth Circuit, 1997)
Advanced Medical Technologies, Inc. v. Shalala
974 F. Supp. 417 (D. New Jersey, 1997)
Independence Mining Co. v. Babbitt
105 F.3d 502 (Ninth Circuit, 1997)
In Re Jimmie Nelson
89 F.3d 829 (Fourth Circuit, 1996)
Nelson v.
Fourth Circuit, 1996
Rudolph L. Lucien v. Watts C. Johnson
61 F.3d 573 (Seventh Circuit, 1995)
Independence Mining Co. v. Babbitt
885 F. Supp. 1356 (D. Nevada, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
42 F.3d 881, 40 ERC (BNA) 1058, 1994 U.S. App. LEXIS 36200, 1994 WL 709574, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-city-of-virginia-beach-commonwealth-of-virginia-amicus-curiae-ca4-1994.