In re: Christopher Michael Cote

CourtUnited States Bankruptcy Appellate Panel for the Ninth Circuit
DecidedJuly 27, 2015
DocketNC-14-1025-TaPaJu
StatusUnpublished

This text of In re: Christopher Michael Cote (In re: Christopher Michael Cote) is published on Counsel Stack Legal Research, covering United States Bankruptcy Appellate Panel for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re: Christopher Michael Cote, (bap9 2015).

Opinion

FILED JUL 27 2015 1 NOT FOR PUBLICATION SUSAN M. SPRAUL, CLERK 2 U.S. BKCY. APP. PANEL OF THE NINTH CIRCUIT 3 UNITED STATES BANKRUPTCY APPELLATE PANEL 4 OF THE NINTH CIRCUIT 5 In re: ) BAP No. NC-14-1025-TaPaJu ) 6 CHRISTOPHER MICHAEL COTE, ) Bk. No. 12-53464 ) 7 Debtor. ) Adv. Pro. No. 12-05160 ______________________________) 8 CHRISTOPHER MICHAEL COTE, ) ) 9 Appellant, ) ) 10 v. ) MEMORANDUM* ) 11 AL V., INC., ) ) 12 Appellee. ) ______________________________) 13 Argued and Submitted on February 19, 2015 14 at San Francisco, California 15 Filed - July 27, 2015 16 Appeal from the United States Bankruptcy Court for the Northern District of California 17 Honorable Stephen L. Johnson, Bankruptcy Judge, Presiding 18 ________________________________ 19 Appearances: Charles Alex Naegele argued for Appellant Christopher Michael Cote; Mark B. Freschi argued 20 for Appellee Al V., Inc. __________________________________ 21 Before: TAYLOR, PAPPAS, and JURY, Bankruptcy Judges. 22 23 24 25 26 * This disposition is not appropriate for publication. 27 Although it may be cited for whatever persuasive value it may have (see Fed. R. App. P. 32.1), it has no precedential value. 28 See 9th Cir. BAP Rule 8024-1(c)(2). 1 INTRODUCTION 2 Chapter 71 debtor Christopher Cote appeals from the 3 bankruptcy court’s judgment after trial awarding damages of 4 $490,883.85 to appellee Al V., Inc. (“Contractor”) and declaring 5 this debt excepted from discharge under § 523(a)(2)(A). 6 Contractor sought a nondischargeable judgment based on 7 alleged fraud relating to a construction contract between it and 8 Cote. Its alleged damages consisted primarily of amounts in 9 excess of its right to recovery under the construction contract 10 at its formation. 11 The bankruptcy court found that Cote intentionally deceived 12 Contractor by knowingly misrepresenting his ability to perform 13 under the construction contract. It then determined that this 14 proximately caused damages to Contractor. We determine that 15 these findings were clearly erroneous. 16 The record is inconsistent with a determination that Cote 17 lacked necessary funding at initiation of the construction 18 contract. It also does not support the conclusion that the 19 damages awarded were contemplated by the construction contract 20 at formation or that they were completely recoverable under the 21 construction contract as thereafter amended. Therefore, we 22 REVERSE. 23 FACTS 24 The Agreements Between Cote and Contractor. Contractor, a 25 licensed general contracting company owned by Al Valles and his 26 1 Unless specified otherwise, all chapter and section 27 references are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, and all “Rule” references are to the Federal Rules of Bankruptcy 28 Procedure, Rules 1001-9037. - 2 - 1 wife,2 entered into a construction contract with Cote's 2 development company3 to build 10 homes (“Phase I”) of a planned 3 18-home solar-powered residential subdivision called Hanna 4 Square in Gilroy, California.4 5 At the beginning of the relationship, the parties signed a 6 Letter of Understanding & Confidentiality Agreement dated 7 June 4, 2007 (the “Confidentiality Agreement”). Cote agreed to 8 provide financial, technical, and management data to Contractor, 9 which included bank construction loan approval letters and 10 banking data. Valles testified at trial that this 11 Confidentiality Agreement somehow prohibited him from contact 12 with Cote’s construction lender. 13 The parties also entered into a Construction Services 14 Contract (“Initial Contract”) along with an Addendum to and 15 Modification of Construction Services Contract (“Addendum,” and 16 together with the Initial Contract, the “Construction 17 Contract”).5 Contractor later argued that he was fraudulently 18 19 2 Valles had been in the contracting business more than 20 years and had built over 150 custom homes and three 20 commercial buildings; he primarily worked as an owner-builder and not as a third party contractor. 21 3 Cote was the sole owner. At no point did Cote argue 22 that he was not the proper defendant. For simplicity, we refer to the development company and Cote hereinafter as “Cote.” 23 4 Cote’s schedules disclosed that his employment for 24 21 years was as a Safari Guide and that he received $11,000.00 per month in gross income. The record suggests, however, that 25 he may have developed at least one prior project. 26 5 Each party admitted a copy of the Initial Contract into evidence at trial. Both copies contained identical text and 27 contained signatures over the signature line for Valles and the initials “A.V.” on every page. The handwritten dates differ 28 (continued...) - 3 - 1 induced to enter into and to perform under this contract. The 2 Construction Contract’s terms, thus, are critical to the 3 analysis, and we highlight the most relevant terms (or lack 4 thereof) as follows: 5 1. The Construction Contract made clear that it did not 6 provide for the payment of the cost of building the homes in 7 Phase II. This necessarily excluded any of the Phase II “under 8 roof” costs and certain site improvements. Instead, the 9 Construction Contract provided that the parties would proceed to 10 build the eight homes in Phase II within one year of execution 11 of the Construction Contract if the sales of homes in Phase I 12 were sufficient. 13 2. Contractor agreed to construct the 10 homes in Phase I 14 for a maximum “under roof” price of $120.756 per square foot or 15 a total of $1,929,585 ($120.75 multiplied by 15,980 total square 16 feet). The Construction Contract, however, also contained 17 numerous provisions that either required, under certain 18 circumstances, or incentivized Contractor, in all events, to 19 20 (...continued) between the copies. At trial, Valles testified that the signature on his exhibit was not his signature. But, he did not 21 dispute his signature on the Initial Contract introduced into evidence by Cote. Aside from speculation in Contractor’s 22 closing argument, there was no further evidence or discussion regarding the disparity in signature. 23 6 Valles testified at trial that when he was presented 24 with the Initial Contract for execution at the title company, Cote tried to reduce the agreed building costs from $120.75 per 25 square foot to $115 per square foot. Their agreement to $120.75 is contained in the Addendum. As later discussed, Contractor’s 26 theory of the case does not turn on whether $115 might have been sufficiently funded, but $120.75 was not; and Cote never 27 disputed that he agreed to $120.75 per square foot for the under roof building costs when he entered into the Construction 28 Contract. - 4 - 1 construct the 10 homes at a lower cost.7 Based on these 2 provisions, Contractor was aware at the time that it entered 3 into the Construction Contract of Cote's stated goal to have 4 Phase I completed by January 1, 2008. There is no evidence that 5 Contractor advised Cote that his goal was unreasonable. 6 3. The Construction Contract also provided for the payment 7 of certain costs for site improvements and established $589,930 8 as the total maximum price for site improvements for both phases 9 of Hanna Square. Contractor agreed to later provide the 10 allocated cost of Phase I site improvements; there is no 11 evidence in the record that it did so or that the parties ever 12 agreed to a specific number. The bankruptcy court concluded 13 that the agreed upon number for Phase I offsite improvements was 14 $556,461; we disagree. The Initial Contract stated that this 15 was the maximum amount payable for both Phase I and Phase II 16 site improvements. The Addendum increased the site improvement 17 budget for both phases to a maximum of $589,930.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
In re: Christopher Michael Cote, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-christopher-michael-cote-bap9-2015.