In Re Approximately Forty Acres

566 N.W.2d 652, 223 Mich. App. 454
CourtMichigan Court of Appeals
DecidedAugust 6, 1997
DocketDocket 188886
StatusPublished
Cited by5 cases

This text of 566 N.W.2d 652 (In Re Approximately Forty Acres) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Approximately Forty Acres, 566 N.W.2d 652, 223 Mich. App. 454 (Mich. Ct. App. 1997).

Opinion

Murphy, J.

Appellant appeals as of right the trial court’s order imposing a lien on the property in question in favor of the state. We affirm.

This case involves interpretation of the Natural Resources and Environmental Protection Act (nrepa), MCL 324.101 et seq.; MSA 13A.101 et seq. Particularly MCL 324.20138; MSA 13A.20138, which provides in relevant part:

(1) All unpaid costs and damages for which a person is liable under [MCL 324.20126; MSA 13A.20126] constitute a lien in favor of the state upon a facility that has been the subject of response activity by the state and is owned by that person. A lien under this subsection has priority over all other liens and encumbrances except liens and encumbrances recorded before the date the lien under this subsection is recorded. A lien under this subsection arises when *457 the state first incurs costs for response activity at the facility for which the person is responsible[ 1 ]
(2) If the attorney general determines that the lien provided in subsection (1) is insufficient to protect the interest of the state in recovering response costs at a facility, the attorney general may file a petition in the circuit court of the county in which the facility is located seeking either or both of the following:
(a) A lien upon the facility subject to response activity that takes priority over all other liens and encumbrances that are or have been recorded on the facility. [ 2 ]

The property at issue in this case is one of four adjoining parcels of land, used previously as a landfill, owned by Howard and Leona Fenske. The three other parcels are located in Kent County and are not at issue in the instant matter. Appellant, Jack Dykstra Excavating, Inc., has a construction lien, in excess of $300,000, on the parcel at issue for excavating work performed on the site. As a result of the landfill operation, the parcel is contaminated. The Department of Natural Resources petitioned the trial court, seeking a superpriority lien in favor of the state for all past and future costs associated with response activity on the parcel. At the time of the petition, costs amounted to $33,000, and testimony at the hearing regarding the petition indicated that total costs may exceed $1,000,000. Following a hearing, the trial court granted the lien.

*458 i

First, appellant claims that the trial court improperly inteipreted the nrepa as leaving the decision whether to impose a superpriority lien solely to the discretion of the Attorney General. Appellant argues that in cases such as this it is improper for a trial court not to exercise discretion and to simply accede to the will of the Attorney General. We agree that the trial court must arrive at its own conclusion and not simply accede to the will of the Attorney General, but disagree with appellant’s characterization of the trial court’s actions in this case.

We interpret MCL 324.20138(2); MSA 13A.20138(2) to mean that if, in the Attorney General’s opinion, a lien pursuant to subsection 1 is insufficient, the Attorney General may seek a superpriority lien pursuant to subsection 2 by petitioning the circuit court to render its opinion regarding the necessity of the superpriority lien. We consider the fact that the statute provides that a superpriority lien can be obtained only following a hearing regarding the petition, MCL 324.20138(3); MSA 13A.20138(3), to implicitly bestow discretion upon the trial court regarding the propriety of the superpriority hen. A lien pursuant to subsection 1 does not require a petition to be filed or a hearing to be held, and because the Legislature placed such requirements on obtaining a superpriority lien pursuant to subsection 2, we must construe them to have some meaning. See Frank v William A Kibbe & Associates, Inc, 208 Mich App 346, 350-351; 527 NW2d 82 (1995). In our opinion, if the trial court had no discretion, the petition and hearing requirement would become superfluous. We therefore conclude that the Legislature intended the petition and hearing require- *459 merit to act as a check on the authority and discretion of the Attorney General by allowing the circuit court to make an independent determination regarding whether a lien under subsection 1 would indeed be “insufficient to protect the interest of the state in recovering response costs at a facility . . .

In this case, our review of the record does not lead us to the conclusion that the trial court simply acceded to the will of the Attorney General and did not exercise its own discretion. A hearing was held with regard to the petition, and testimony concerning the condition of the property and the projected cost to the state was presented. During the hearing, the trial court asked the petitioner precisely why the Attorney General was of the opinion that a standard lien would be insufficient. Thereafter, the trial court concluded, on the basis of the evidence presented, that a superpriority lien was, in its words, “appropriate and necessary.” We find no error requiring reversal.

n

Next, appellant claims that the trial court erred in allowing the superpriority lien to secure future response costs. We disagree.

MCL 324.20138(2); MSA 13A.20138(2) allows a superpriority lien to be ordered to protect the state’s interest in recovering “response costs” at a facility. MCL 324.20101(l)(ff); MSA 13A.20101(l)(ff) defines such costs as “all costs incurred in taking or conducting a response activity, including enforcement costs.” (Emphasis added). Appellant argues that the Legislature’s use of the past tense indicates an intent to refer to only those costs that have already been *460 incurred and does not include potential future costs. We disagree.

The primary goal of judicial inteipretation of statutes is to ascertain and give effect to the intent of the Legislature. Rowell v Security Steel Processing Co, 445 Mich 347, 353; 518 NW2d 409 (1994). The first step in determining intent is the language of the statute. House Speaker v State Administrative Bd, 441 Mich 547, 567; 495 NW2d 539 (1993). If the plain and ordinary meaning of the language is clear, judicial construction is normally neither necessary nor permitted. Lorencz v Ford Motor Co, 439 Mich 370, 376; 483 NW2d 844 (1992). However, if a literal construction of a statute would produce unreasonable and unjust results that are inconsistent with the purpose of the statute, the court may depart from a literal construction. Rowell, supra at 354. In addition, statutory language should be construed reasonably, keeping in mind the purpose of the act. Dep’t of Social Services v Brewer, 180 Mich App 82, 84; 446 NW2d 593 (1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John R. Sand & Gravel Co. v. United States
62 Fed. Cl. 556 (Federal Claims, 2004)
Ypsilanti Housing Commission v. O'Day
618 N.W.2d 18 (Michigan Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
566 N.W.2d 652, 223 Mich. App. 454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-approximately-forty-acres-michctapp-1997.