in Re Application of Dte Electric Company for 2015 Reconciliation

CourtMichigan Court of Appeals
DecidedDecember 6, 2018
Docket339557
StatusUnpublished

This text of in Re Application of Dte Electric Company for 2015 Reconciliation (in Re Application of Dte Electric Company for 2015 Reconciliation) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
in Re Application of Dte Electric Company for 2015 Reconciliation, (Mich. Ct. App. 2018).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS In re APPLICATION OF DTE ELECTRIC COMPANY FOR 2015 RECONCILIATION.

DTE ELECTRIC COMPANY, UNPUBLISHED December 6, 2018 Petitioner-Appellant,

v No. 339557 MPSC MICHIGAN PUBLIC SERVICE COMMISSION, LC No. 00-017680-R

Appellee.

Before: RIORDAN, P.J., and RONAYNE KRAUSE and SWARTZLE, JJ.

PER CURIAM.

Petitioner, DTE Electric Company (DTE), appeals as of right an order entered by the Michigan Public Service Commission (PSC) that, in relevant part, disallowed DTE’s request to include a refund in its 2015 power supply cost recovery (PSCR) reconciliation balance under MCL 460.6j.1 The refund was issued by DTE in 2015, as a consequence of overbilling a major customer for electrical power between 2008 and 2014. The PSC concluded that because the refund was for power consumed outside of the 12-month reconciliation period for 2015, it could not be included in the reconciliation. The PSC therefore denied DTE’s request. We reverse in part and remand.

I. INTRODUCTION

One of the ways in which an electric utility can recover its power supply costs from its customers is by including a “PSCR clause” in its rate schedule. See In re App of Consumers Energy Co for Reconciliation of 2009 Costs, 307 Mich App 32, 35 n 1; 859 NW2d 216 (2014),

1 While this matter was pending in the PSC, the Legislature amended MCL 460.6j pursuant to 2016 PA 341. The PSC did not specify which version of the statute it used; however, neither we nor the parties have discovered any substantive alterations of relevance to the instant appeal. Therefore, all references to MCL 460.6j in this opinion will be to the prior version of the statute, which was in effect during the 2015 reconciliation period at issue.

-1- aff’d on alternative grounds 499 Mich 885 (2016). “PSCR” stands for “power supply cost recovery.” See MCL 460.6j(1). This Court has explained the PSCR process as follows:

A PSCR clause is “a clause in the electric rates or rate schedule of a utility which permits the monthly adjustment of rates for power supply to allow the utility to recover the booked costs, including transportation costs, reclamation costs, and disposal and reprocessing costs, of fuel burned by the utility for electric generation and the booked costs of purchased and net interchanged power transactions by the utility incurred under reasonable and prudent policies and practices.” MCL 460.6j(1)(a). Each year, a utility with a PSCR clause in its rate schedule must file a PSCR plan for the upcoming year and a five-year forecast of power supply requirements. MCL 460.6j(3) and (4). The PSC approves, disapproves, or modifies the proposed PSCR plan. MCL 460.6j(6). After the end of the year, the PSC conducts a reconciliation case in which it makes adjustments to take into account the utility's true cost of supplying power. MCL 460.6j(12) and (13). [In re App of Indiana Michigan Power Co, 275 Mich App 369, 370- 371; 738 NW2d 289 (2007).]

“Electric utilities can recover two types of power supply costs through a PSCR clause: (1) ‘booked costs, including transportation costs, reclamation costs, and disposal and reprocessing costs, of fuel burned by the utility for electric generation;’ or (2) ‘booked costs of purchased and net interchanged power transactions.’ ” Attorney General v Pub Service Comm, 483 Mich 998, 998; 764 NW2d 278 (2009), quoting MCL 460.6j(1)(a).

In very general terms, the PSC compares an electric utility’s revenues to its costs, “reconciles” the two, and permits the electric utility to adjust its rates accordingly. See Attorney General v Pub Service Comm, 237 Mich App 27, 30; 602 NW2d 207 (1999). If the utility collected more revenue than its costs, it must refund or credit the excess to its customers. MCL 460.6j(14) and (16). If it collected less revenue than its costs, it may recover the difference from its customers. MCL 460.6j(15) and (16).2

II. FACTUAL BACKGROUND

2 In part, MCL 460.6j(16) states, “Costs incurred by the utility for refunds and interest on refunds shall not be charged to customers.” In context, this appears to refer to refunds issued as a consequence of the reconciliation process and therefore does not pertain to the refund at issue here. Furthermore, DTE argued at oral argument, and the PSC did not dispute, that the term “costs . . . for refunds” is understood to mean ancillary costs such as postage, processing, or programming, rather than the refund itself. Either understanding is supported by the lack of discussion of this sentence below. Consequently, we conclude that this sentence is irrelevant to the instant appeal. The Severstal refund is an entirely different kind of refund than a reconciliation refund, which “enjoys a broader meaning” because it can also encompass an adjustment of future rates in addition to a direct repayment of money. In re Detroit Edison Co Application, 297 Mich App 377, 385-387; 823 NW2d 433, 437 (2012), result aff’d but criticized on other grounds 495 Mich 884 (2013).

-2- Between 2008 and 2014, DTE overbilled one of its large customers for electricity, due to an undiscovered technical error. The customer, Severstal Dearborn, LLC (Severstal), which is not a party to the instant matter, discovered the error in 2014, whereupon it filed a complaint against DTE with the PSC. In 2015, the PSC ordered DTE to repay approximately $19.65 million to Severstal, plus 7% interest. Notably, it is undisputed, and in fact expressly admitted by both parties at oral argument, that because of Severstal’s overpayment, DTE’s other customers enjoyed artificially lowered energy rates in 2008 through 2014. Consequently, DTE did not profit from the overbilling.

The instant proceeding is a separate reconciliation proceeding. In relevant part, DTE sought to have approximately $13.45 million of the Severstal refund considered a “negative revenue” in 2015 for the purpose of reconciliation. DTE contends that this amount reflects only “the PSCR portion” of the Severstal refund, and it therefore excludes the substantial interest DTE was required to pay.3 If that amount is “reconciled,” DTE would be permitted to raise its energy rates to counteract that loss. In effect, DTE would theoretically recoup the windfall from the same customers who previously enjoyed it. The PSC rejected DTE’s request. The PSC held that the Severstal refund could not be reconciled in 2015 because it represented “lost PSCR revenue from the cost of power supply consumed between the years 2008 and 2014,” and therefore outside “[t]he 12-month period covered by DTE Electric’s PSCR plan [which] began on January 1, 2015 and ended December 31, 2015.”

III. STANDARD OF REVIEW

As this Court recently explained in In re Reliability Plans of Electric Utilities for 2017- 2021, ___ Mich App ___, ___; ___ NW2d ___ (2018) (Docket No. 340600), slip op at 8, lv pending:

To be valid, a final order of the MPSC must be authorized by law, and also must be supported by competent, material, and substantial evidence on the whole record. Const 1963, art 6, § 28; Attorney General v Pub Serv Comm, 165 Mich App 230, 235; 418 NW2d 260 (1988). Agencies have authority to interpret the statutes that they administer and enforce, Clonlara, Inc v State Board of Ed, 442 Mich 230, 240; 501 NW2d 88 (1993), and we respectfully consider an agency’s interpretation of a statute that it is empowered to execute, and will not overrule that construction absent cogent reasons. In re Complaint of Rovas Against SBC Mich, 482 Mich 90, 103; 754 NW2d 259 (2008). But the construction the [PSC] gives to a statute is not binding on the courts. Id. Ultimately, the statutory language itself is controlling, id. at 108, and this Court will neither abandon nor delegate its responsibility to determine legislative intent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Complaint of Rovas Against Sbc
754 N.W.2d 259 (Michigan Supreme Court, 2008)
Attorney General v. Michigan Public Service Commission
764 N.W.2d 278 (Michigan Supreme Court, 2009)
Womack-Scott v. Department of Corrections
630 N.W.2d 650 (Michigan Court of Appeals, 2001)
Clonlara, Inc v. State Board of Education
501 N.W.2d 88 (Michigan Supreme Court, 1993)
Young v. Robin
382 N.W.2d 182 (Michigan Court of Appeals, 1985)
Consumers Energy Co. v. Public Service Commission
707 N.W.2d 633 (Michigan Court of Appeals, 2005)
In Interest of GB
418 N.W.2d 258 (Nebraska Supreme Court, 1988)
McGrath v. Clark
280 N.W.2d 480 (Michigan Court of Appeals, 1979)
Rafferty v. Markovitz
602 N.W.2d 367 (Michigan Supreme Court, 1999)
General v. Public Service Commission No 1
602 N.W.2d 207 (Michigan Court of Appeals, 1999)
Consumers Power Co. v. Public Service Commission
596 N.W.2d 126 (Michigan Supreme Court, 1999)
Champion's Auto Ferry, Inc v. Public Service Commission
588 N.W.2d 153 (Michigan Court of Appeals, 1998)
People v. McIntire
599 N.W.2d 102 (Michigan Supreme Court, 1999)
Piccalo v. Nix
643 N.W.2d 233 (Michigan Supreme Court, 2002)
In Re Indiana Michigan Power Co.
738 N.W.2d 289 (Michigan Court of Appeals, 2007)
In Re the Wayne County Treasurer for Foreclosure
777 N.W.2d 507 (Michigan Court of Appeals, 2009)
Madugula v. Taub
853 N.W.2d 75 (Michigan Supreme Court, 2014)
in Re Application of Consumers Energy to Increase Electric Rates
891 N.W.2d 871 (Michigan Court of Appeals, 2016)
in Re Certified Question (Deacon v. Pandora)
885 N.W.2d 628 (Michigan Supreme Court, 2016)
Rovas v. SBC Michigan
482 Mich. 90 (Michigan Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
in Re Application of Dte Electric Company for 2015 Reconciliation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-application-of-dte-electric-company-for-2015-reconciliation-michctapp-2018.