In re Appeal of Beckstrom

2004 VT 32, 852 A.2d 561, 176 Vt. 622, 2004 Vt. LEXIS 38
CourtSupreme Court of Vermont
DecidedApril 8, 2004
DocketNo. 03-274
StatusPublished
Cited by21 cases

This text of 2004 VT 32 (In re Appeal of Beckstrom) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Appeal of Beckstrom, 2004 VT 32, 852 A.2d 561, 176 Vt. 622, 2004 Vt. LEXIS 38 (Vt. 2004).

Opinion

¶ 1. H.A. Manosh Corp. appeals from a decision of the environmental court declaring that a permit to erect a radio tower and support building was rendered null and void by its failure to commence construction within one year. Neighbors, comprised of persons who live in the vicinity of the proposed tower, have cross-appealed from the court’s determination that the permit was not also rendered void by Manosh’s alleged misrepresentations in the permit application. We affirm the court’s ruling on the misrepresentation claim, but reverse its decision that the permit was void for failure to commence construction within one year.

¶ 2. This case has a complex procedural history. Manosh owns a radio tower located on what the parties refer to as the Jones property in the Town of Hyde Park. On April 18, 1997, Manosh applied for a zoning permit to erect a radio tower and support building on a separate twenty-nine-acre parcel that it owns in the town. The application described the tower as 100 feet high and the building as a “cement block structure.” Several witnesses at trial testified that Manosh informed the zoning administrator at the time of the application that the company’s intent was to relocate the Jones tower to the twenty-nine-acre parcel site, but that intention was not stated in the permit application, and it was established at trial that the Jones tower is closer to seventy-five feet tall, measured to the base of the metal structure rather than the foot of its concrete base.

¶ 3. The administrator approved the application as a permitted use. In fact, however, the tower was not a permitted use in the zoning district where the site was located, but no party appealed the issuance of the permit and it became final. The application form signed by Manosh stated that “[a]ny permit issued as a result of this application shall be null and void in the event of misrepresentation or failure to undertake construction within one year of approval of this Zoning Permit.” The permit was issued on April 23, 1997, and showed an expiration date of April 23,1998.

¶ 4. Within several months after issuance of the permit, Manosh became interested in revising its plans in order to relocate a different 150-foot tower (later determined to be closer to 160 feet), owned by the Lamoille County Sheriff’s Department, from its existing location in the Village of Hyde Park to the new twenty-nine-acre site. In July 1997, the zoning administrator granted Manosh’s request to amend the permit to allow a 150-foot tower. The amended permit was appealed shortly thereafter by an adjoining landowner, but no hearing before the zoning board of adjustment was convened. In September, Manosh applied for an Act 250 permit to erect a 150-foot tower and support building at the new site by relocating the so-called village tower and shifting the antennas from the Jones tower to the village tower, and to upgrade a logging road for access to the site. The permit was granted in November, but was later revoked in February 1999.

¶ 5. In the meantime, in August 1998, neighbors appealed the original zoning permit to the ZBA, which ruled the appeal untimely. Neighbors also appealed the administrator’s decision not to institute enforcement proceedings based on neighbors’ allegations that the permit was void for failure to undertake construction within one year. The ZBA ruled that the permit had not expired, citing [623]*623Manosh’s undertakings in laying underground electrical conduits and upgrading the access road. The ZBA later ruled that the initial appeal of the amended permit in July had been timely, that the tower was not a permitted use, and that a conditional use permit would be required. In March 1999, the ZBA granted Manosh’s application to amend the April 1997 permit, and issued a conditional use permit and site plan approval authorizing Manosh to relocate the village tower to the new site.

¶ 6. All of the ZBA rulings were appealed to the environmental court. In response to cross-motions for summary judgment, the court ruled that the original April 1997 permit was final, notwithstanding the fact that it authorized a nonpermitted use in the district, but that material facts were in dispute as to whether it had expired for lack of construction or was void based on alleged misrepresentations in the application. The court further ruled that the July 1997 amendment authorizing a 150-foot tower required a conditional use application, but remanded to the town’s planning agency for further proceedings, including the filing of a more complete application and a determination whether the new permit complied with an interim bylaw, enacted by the town in January 1999, imposing a moratorium on the erection of communications towers (the April 1997 permit was exempt from the bylaw in question).

¶ 7. An evidentiary hearing addressed solely to the issues concerning the April 1997 permit was then held over two separate days in May and November 2002. In May 2003, the court issued a written decision, rejecting neighbors’ claim that Manosh had made fraudulent misrepresentations in applying for the permit, but finding nevertheless that the permit had expired and was void because Manosh had failed to undertake construction within one year of its issuance. Both parties have appealed from the court’s decision.

¶ 8. Manosh contends the court erred in concluding that the permit had expired due to the failure to undertake construction within one year of its issuance. The trial court found in this regard that from January 1998 to the expiration date in late April, Manosh performed work on the road leading up to the site and installed underground electrical conduit along the roadway. The court also found that additional work “may” have been done at the tower site itself, including clearing and “some subsurface concrete work.” The evidence underlying these findings shows that, during the four-month period in question, Manosh committed almost 400 work-hours to the tower project, incurring expenses in excess of $26,000. Time-sheets and testimony established without contradiction that Manosh installed utility lines, graded and graveled the road leading to the site, cleared the site, and poured concrete. Although the evidence does not identify the purpose of the poured concrete, it is reasonable to infer that it was related to construction of the “cement-block” support building specified in the permit.

¶ 9. Although we will not — absent clear error — disturb the trial court’s factual findings, “[questions of law are reviewed de novo, allowing us to proceed with a nondeferential, on-the-record review.” In re Gulli, 174 Vt. 580, 582, 816 A.2d 485, 488 (2002) (mem). In concluding that Manosh failed to commence construction within the one-year permit period, the trial court here applied a legal standard which precluded consideration of work other than that directly related to the structures specified in the permit — the tower and support building. Thus, the court found that grading the access road, laying utility lines, and clearing the tower site were immaterial, and appeared to further conclude that the pouring of concrete at the site — without [624]*624more specific information •— was inadequate to demonstrate that construction had commenced.

¶ 10. Although Vermont law provides little guidance on this issue, other jurisdictions have taken a broader view of what constitutes a commencement of “construction” than the trial court here, holding that the standard to be applied should reflect the purpose to be served.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Wagner & Guay Permit (Mary Bourassa, Appellant)
2016 VT 96 (Supreme Court of Vermont, 2016)
In re R.W. and N.W.
2011 VT 124 (Supreme Court of Vermont, 2011)
Brandan Plaza CU Permit
Vermont Superior Court, 2011
State v. Thayer
2010 VT 78 (Supreme Court of Vermont, 2010)
Sprague Farms, LLC CU & SP
Vermont Superior Court, 2010
Sprague Farms, LLC
Vermont Superior Court, 2009
Centre/Hannaford Plaza PUD
Vermont Superior Court, 2009
Freedom Foods LLC Site Plan
Vermont Superior Court, 2009
Curry Variance Application
Vermont Superior Court, 2009
Ledgewood Condo PUD CU Amend Application
Vermont Superior Court, 2008
In Re Appeal of Shaw
2008 VT 29 (Supreme Court of Vermont, 2008)
In re Appeal of Jolley Associates
181 Vt. 190 (Supreme Court of Vermont, 2006)
In Re Jolley Associates
2006 VT 132 (Supreme Court of Vermont, 2006)
In re Appeal of Armitage
2006 VT 113 (Supreme Court of Vermont, 2006)
In Re Armitage
2006 VT 113 (Supreme Court of Vermont, 2006)
Town of Victory v. State
2004 VT 110 (Supreme Court of Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2004 VT 32, 852 A.2d 561, 176 Vt. 622, 2004 Vt. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeal-of-beckstrom-vt-2004.