City of Ellsworth v. Doody

629 A.2d 1221, 1993 Me. LEXIS 166
CourtSupreme Judicial Court of Maine
DecidedAugust 5, 1993
StatusPublished
Cited by5 cases

This text of 629 A.2d 1221 (City of Ellsworth v. Doody) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Ellsworth v. Doody, 629 A.2d 1221, 1993 Me. LEXIS 166 (Me. 1993).

Opinion

CLIFFORD, Justice.

The City of Ellsworth (City) appeals from a judgment entered by the Superior Court (Hancock County, Browne, A.R.J.) following a nonjury trial in which the court determined that F. Beecher Doody (the homeowner) and Richard A. Johnson (Doody’s contractor) had not violated provisions of the City’s zoning ordinance in constructing Doody’s cottage adjacent to Branch Lake. The City contends that the court should have given preclusive effect to the Ells-worth Planning Board’s finding that Doody's cottage was constructed within 75 feet of the normal high water mark of the lake, that the court erred in determining that the only violation of the ordinance related to the placement of docks without a permit, and that the court should have awarded the City its attorney fees. Finding no merit in these contentions, we affirm the judgment.

*1222 In May 1988, after Doody was granted a special exception permit from the City’s Planning Board, the Code Enforcement Officer (CEO) issued Doody a building permit to construct a cottage on his land on Branch Lake. Doody then cleared the site, had a driveway built and a septic system installed. Construction on the cottage itself did not begin until the spring of 1990, when Doody hired defendant Johnson to do the foundation work. In June 1990, the CEO, having received a complaint from another landowner on the lake regarding the construction at the Doody property, sent his assistant to the site to investigate. Following the site visit, the CEO issued a stop work order, because he believed that too many trees had been cut, too much fill had been brought to the site, docks existed for which no permit had been obtained, and the building was too close to the lake. Throughout the summer Doody and the City attempted to resolve the situation. As part of that overall effort to resolve his differences with the City, Doody resubmitted his application for a building permit to the Planning Board. The Planning Board subsequently found that the cottage, as constructed, was 65 feet from the normal high water mark. The City and Doody were unable to settle their dispute.

In November 1990, the CEO filed in the District Court a land use citation and complaint pursuant to M.R.Civ.P. 80K alleging that Doody and Johnson had violated provisions of the zoning ordinance by engaging in earth-moving and fill activities without a permit, by excessive cutting of trees and vegetation, by placing docks on the property without a permit, and by constructing the cottage within 75 feet of the normal high water mark. The case was removed to the Superior Court, and a three-day non-jury trial resulted in a determination that the City had proved only one violation, the placement of docks without a permit. The court rejected the City’s argument that Doody was precluded from relitigating the setback issue concluding that because the Planning Board’s determination of the setback was an integral part of Doody’s unsuccessful effort to settle his dispute with the City, it was inappropriate to bind Doody to the Planning Board finding. The court also declined to award the City its attorney fees because the City had prevailed on only one of five claims.

I.

The City first argues that the Planning Board’s finding that Doody’s cottage had been constructed within 75 feet of the normal high water mark precludes Doody from relitigating the setback issue in the Superior Court. In Town of North Berwick v. Jones, 534 A.2d 667 (Me.1987), we held that the principle of collateral estoppel prevents the relitigation in the Superior Court of an issue decided by a municipal body when the process utilized by the municipality includes all the essential elements of adjudication. Id. at 670. The City argues that the Planning Board procedure in this case included the essential elements of adjudication as set out in North Berwick and that collateral estoppel applies to the Planning Board’s decision as a matter of law. We disagree.

The Superior Court found that Doody resubmitted his application for a building permit to the Planning Board as part of his overall effort to settle with the City the dispute relating to the construction of his cottage. That finding will be overturned only if it is clearly erroneous. Morin Bldg. Prod. Co., Inc. v. Atlantic Design & Constr. Co., Inc., 615 A.2d 239, 241 (Me.1992). Doody testified that the purpose of his reapplication to the Planning Board in the summer of 1990 was to resolve the problems that had arisen in connection with his building project. He offered into evidence a consent agreement, proposed by the City but never executed, that included a provision that Doody reapply to the Planning Board for a permit. Doody had no need to go to the Planning Board other than to attempt to resolve the dispute he had with the City. 1 In the circumstances *1223 of this case, the court’s finding that Doody appeared before the Planning Board as part of a settlement process that ultimately failed, and its conclusion that he was therefore not estopped from relitigating the setback issue are not clearly erroneous.

II.

The City next argues that even if collateral estoppel does not apply, the court's findings that Doody and Johnson did not violate the ordinance’s setback requirement and that Doody did not violate ordinance provisions relating to earth-moving, fill and timber cutting were clearly erroneous. Because it had the burden of proof on these issues at trial, in order to prevail on appeal the City must demonstrate that the court was compelled to find in its favor. Gonthier v. HoRNe, 576 A.2d 745, 747 (Me.1990). The evidence in this case does not compel the conclusion that Doody and Johnson violated the zoning ordinance.

On the issue of the zoning ordinance’s setback requirement, the court concluded that the City failed to prove Doody and Johnson had violated the ordinance provision that structures be set back 75 feet from the normal high water mark. In reaching this conclusion, the court found that the location of the normal high water mark had not been precisely established. Although the City presented evidence that Doody’s cottage was less than 75 feet from the normal high water mark, there was contrary evidence that the cottage was 75 feet from that mark. In addition, a survey- or hired by Doody testified that he could not find with certainty the normal high water mark, because the ordinance definition of normal high water mark was the “equivalent of wrestling with fog.” Based on this evidence, we cannot say the Superi- or Court was compelled to find that Doody and Johnson had violated the ordinance’s setback provision.

The City next takes issue with the court’s finding that Doody had not violated the ordinance's provision relating to earth-moving and fill activities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of China v. Albert Althenn
2013 ME 107 (Supreme Judicial Court of Maine, 2013)
Bennett v. Beaver Ridge Wind
Maine Superior, 2008
In re Appeal of Beckstrom
2004 VT 32 (Supreme Court of Vermont, 2004)
State Ex Rel. Helujon, Ltd. v. Jefferson County
964 S.W.2d 531 (Missouri Court of Appeals, 1998)
McCain Foods, Inc. v. Gervais
657 A.2d 782 (Supreme Judicial Court of Maine, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
629 A.2d 1221, 1993 Me. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-ellsworth-v-doody-me-1993.