In Re Advanced Systems, Inc.

257 B.R. 457, 44 U.C.C. Rep. Serv. 2d (West) 882, 2001 U.S. Dist. LEXIS 602, 2001 WL 43599
CourtDistrict Court, E.D. Louisiana
DecidedJanuary 18, 2001
DocketCiv.A. No. 00-2985. Bankruptcy No. 98-10285
StatusPublished
Cited by1 cases

This text of 257 B.R. 457 (In Re Advanced Systems, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Advanced Systems, Inc., 257 B.R. 457, 44 U.C.C. Rep. Serv. 2d (West) 882, 2001 U.S. Dist. LEXIS 602, 2001 WL 43599 (E.D. La. 2001).

Opinion

ORDER AND REASONS

VANCE, District Judge.

Before the Court are three appeals from the August 4, 2000 judgment of the United States Bankruptcy Court, Eastern District of Louisiana in the matter of Advanced Systems, Inc. Appeals were filed by Advanced Systems, Inc., Parish National Bank, and Historic Constriction Incorporated and National Union Fire Insurance Company of Pittsburgh, PA. For the following reasons, the Court affix-ms the Bankruptcy Court.

I. Background

In late 1996, Cotton Mill Limited Partnership decided to renovate an old warehouse situated in the Warehouse District of New Orleans, Louisiana, into apartments and condominiums. The Partnership selected Historic Construction Incorporated as the general contractor. HCI employed ASI in October or November 1996 to sand the floors on a time and materials basis. HCI then decided in February 1997 to enter into a painting and gypsum board subcontract with ASI.

The Bankruptcy Court found a written subcontract dated February 1, 1997, a copy of which ASI’s corporate officers received around March 31, 1997. (Bankr. Ct.’s Mem.Op. at 3.) ASI and HCI, however, did not sign the subcontract until August 9, 1997 and August 11, 1997, respectively. Between October 1996 and August 1997, HCI and ASI negotiated the basis, price, and scope of the subcontract. Notwithstanding these protracted negotiations, the only diffex-ence between the February and August 1997 subcontracts was a reduction in the retainage to ten percent. Both versions stated at Article 11 that the “[cjontract shall not be assigned by Subcontractor without first obtaining permission in writing from Contractor.” (Id. at 4.)

In March 1997, ASI entered into a financing arrangement with Parish National Bank called a “cash manager line of credit.” The arrangement was essentially an accounts receivable financing and included an assignment of ASI’s accounts receivable, including the accounts receivable due under its subcontract with HCI, to PNB. On March 7, 1997, PNB filed a financing statement regarding its security interest in ASI’s property. PNB sent a letter on June 11, 1997 to HCI notifying it of the assignment and directing HCI to fox-ward payment on ASI’s invoices to PNB. Upon receipt of this letter, HCI contacted PNB by telephone stating its objections to the assignment of the accounts receivable. HCI reiterated those objections on August 12,1997.

A document entitled Corporate Authorization Resolution was admitted into evidence at trial. It represented that ASI’s Board of Directors met on Januax-y 1, 1997 and authorized the corporate officers to enter into financial agreements with PNB. The resolution was dated March 28, 1997. The Bankruptcy Coxxrt found, however, that none of the directors remembered meeting on Januaxy 1, 1997 and that the evidence indicated that the resolution “probably was not completely filled out when it was dated.” (Id. at 5.) Notwithstanding the January 1, 1997 meeting, the Bankruptcy Coxxrt found that ASPs Board of Direetoi-s did meet on September 5, 1997 and executed a valid Corporate Authorization Resolution. That resolution ratified the March 1997 loan agreement, approved a proposed assignment to PNB of the subcontract with HCI, and granted the corpox-ate officers the px-oper authority to enter into agreements with PNB. Moreover, on September 5, 1997, ASI actually assigned its rights in the subcontract with HCI to *461 PNB as additional security for advances made. ASI also executed a promissory note in favor of PNB in the amount of $30,334.35 for a loan from PNB advanced to cover ASI’s payroll.

On August 7, 1997, HCI sent ASI a letter putting it on notice of defaults under the contract. To correct the identified problems, the letter mandated implementation of certain remedial measures, including HCI’s paying all vendors and purchasing all materials. This remedial attempt was to last one month, with ASI’s summary termination if the solution proved unworkable. The problems, however, continued, and, on December 4, 1997, HCI sent ASI a termination letter.

On October 22, 1997, PNB filed suit against HCI in the Twenty-Second Judicial District Court for the Parish of St. Tammany seeking to enforce its security interest in ASI’s accounts receivable. The case was ultimately transferred to the Civil District Court for the Parish of Orleans on venue grounds. On January 7, 1998, ASI filed a statement of lien and privilege under the Louisiana Private Works Act against HCI. Two weeks later, on January 23, 1998, ASI filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code. After ASI sought relief in bankruptcy, the case proceeded as an adversarial proceeding in the bankruptcy court.

After a five-day trial, the Bankruptcy Court issued a judgment on August 4, 2000. The Bankruptcy Court recognized the superior lien of PNB on ASI’s accounts receivable, entered judgment in favor of PNB and against HCI and National Union in the amount of $44,854.00 plus interest from the date of judicial demand, and dismissed ASI and HCI’s claims.

ASI, PNB, HCI, and National Union now appeal. ASI presents five issues on appeal: (1) Whether ASI should be awarded $30,600.00 for the equipment confiscated by HCI; (2) whether HCI terminated ASI without cause; (3) whether the Bankruptcy Court should have awarded ASI damages; (4) whether the Bankruptcy Court should have awarded ASI compensation for extra work, change orders, and retainage; and (5) whether the Bankruptcy Court should have awarded ASI interest and attorney fees. PNB also presents five issues on appeal: (1) Whether PNB may recover its entire security interest lien in the amount of $188,349.99; (2) whether it may recover $30,334.35 advanced to ASI on September 5, 1997 to cover the payroll; (3) whether the Bankruptcy Court properly excluded the $74,559.55 retainage from the judgment; (4) whether the Bankruptcy Court incorrectly credited HCI $68,936.34; and (5) whether PNB should have been awarded interest from the date each invoice became due, attorney’s fees, and costs.

HCI and National Union present three issues on appeal: (1) Whether they may setoff $24,982.10 paid by HCI to ASI’s suppliers; (2) whether the anti-assignment clause contained in the subcontract between HCI and ASI prohibited ASI from assigning its accounts receivable to PNB; and (3) whether National Union is liable to PNB.

II. Discussion

A. Jurisdiction

This Court properly has jurisdiction over this case pursuant to 28 U.S.C. § 158(a) and Federal Rule of Bankruptcy Procedure 8001. See 28 U.S.C. § 158(a); Fed.R.BanKR.P. 8001.

B. Standard of Review

The standard of review of a bankruptcy appeal by a district court is the same as when a Court of Appeals reviews a district court proceeding. See 28 U.S.C. § 158(c)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Bancorp South v. Richmond (In Re Richmond)
430 B.R. 846 (E.D. Arkansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
257 B.R. 457, 44 U.C.C. Rep. Serv. 2d (West) 882, 2001 U.S. Dist. LEXIS 602, 2001 WL 43599, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-advanced-systems-inc-laed-2001.