In re 95 Lorimer, LLC

6 Misc. 3d 500
CourtNew York Supreme Court
DecidedNovember 17, 2004
StatusPublished
Cited by1 cases

This text of 6 Misc. 3d 500 (In re 95 Lorimer, LLC) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re 95 Lorimer, LLC, 6 Misc. 3d 500 (N.Y. Super. Ct. 2004).

Opinion

OPINION OF THE COURT

Ira B. Harkavy, J.

[501]*501Defendant third-party plaintiff the Insurance Company of the State of Pennsylvania (ICP) moves for an order, pursuant to CPLR 3211 and 3212, summarily dismissing plaintiff 95 Lorimer, LLC’s (Lorimer) amended complaint and separate causes of action on the ground, inter alia, that the action is time-barred and/or the complaint fails to state a cause of action. Lorimer cross-moves for an order precluding ICP’s examination before trial of plaintiff in this action based upon ICP’s alleged failure to comply with a prior discovery order of this court.

Factual Background

On or about July 10, 1998, Lorimer and Iroquois Demolition Corporation, also known as Iroquois Wrecking Corp. (Iroquois), entered into a written agreement (the contract) wherein Iroquois agreed to perform certain demolition and removal work at a property located at 95-107 Lorimer Street in Kings County and owned by Lorimer.

On or about July 13, 1998, ICP (as surety) issued a payment and performance bond on the contract on behalf of Iroquois (as contractor, principal and obligor) to Lorimer (as owner and obligee). The bond was executed on behalf of Iroquois by its vice-president, third-party defendant Charles Walker. The bond contains a limitations period requiring that any suit seeking recovery thereunder be commenced within two years after the contractor/obligor ceases to perform under the contract.

Commencing on or about May 26, 1998, and continuing at the time it entered into the subject contract and performance bond, Iroquois was an entity incorporated by and under the laws of the State of New York, pursuant to a certificate of incorporation duly filed by Iroquois with the Secretary of State.

It is undisputed that Iroquois performed under the subject contract and received payment from Lorimer for said performance up to and until June 18, 1999.

Lorimer asserts that, sometime between June 18 and August 4, 1999, Philip Schwab, known by Lorimer to be an owner and principal of Iroquois, informed Lorimer that Iroquois had changed its name to Irondequoit Corporation (the third-party defendant, hereinafter Irondequoit) and that all payments under [502]*502the contract, formerly made by Lorimer to Iroquois, were now to be issued to Irondequoit.1

There is absolutely no indication on the record, and Lorimer does not allege, that the surety, ICP was either informed of the purported “name change” or notified that payment under the subject contract would now be issued by Lorimer to Irondequoit, rather than Iroquois. Equally apparent from the record is the fact that Lorimer did not then seek ICP’s permission to change the obligor on the bond from Iroquois to Irondequoit. Nevertheless, Lorimer, starting on August 4, 1999, began making all payments under the contract to Irondequoit, and not to Iroquois.

At the time Lorimer issued this first, August 4, 1999, payment to Irondequoit, Irondequoit had not yet achieved official status as a corporate entity. Irondequoit did, on November 19, 1999, file incorporation papers with the New York Secretary of State. At the time of said incorporation by Irondequoit, Iroquois was still a separately incorporated business entity in the State of New York.2

Eventually, a dispute arose between Lorimer and Irondequoit concerning Irondequoit’s performance, or lack thereof, under the contract. Specifically, Lorimer alleges that, during the demolition and excavation of the subject property, Iroquois and/or Irondequoit buried debris at the premises, resulting in a dangerous sinkhole situation which Irondequoit thereafter failed or refused to correct.

It further appears from the record that Lorimer accelerated the contract payments, first to Iroquois, then to Irondequoit; issued the last contract payment to Irondequoit on April 27, 2001; and payed or issued the full contract price to those two entities prior to the completion of all of the work and, more specifically, although much or all of the excavation work had allegedly not been performed.

Lorimer did not notify ICP of the change in the corporate recipient of payments under the subject contract until December 2001, more than two years after Lorimer made its last payment [503]*503to Iroquois and sometime after Irondequoit apparently refused to perform the requested excavation work unless it received additional payment.

By correspondence dated December 12, 2001, Lorimer notified ICP that payment of the contract had been rendered in full by Lorimer upon the contractor’s completion of the demolition work; that the contractor had failed and refused to complete the excavation; and that Lorimer was considering declaring a contractor default under the bond. A second correspondence of the same date from Lorimer to ICP included the aforementioned undated correspondence to Lorimer from Mr. Scott, Irondequoit’s vice-president, agreeing that payments to Irondequoit were to be credited to the original amount of the contract entered into by Iroquois.

Thereafter, on December 17, 2001, ICP responded in two letters wherein it, in essence, refused its consent to a change in the bond obligor from Iroquois to Irondequoit, noting, inter alia, that ICP “never consented or authorized [Lorimer] to release payments under the[ ] contract to any firm other than the bonded contractor, Iroquois”; Lorimer may have prejudiced ICP’s rights “by releasing 100% of the contract funds to two different entities,” even though the project had not yet been completed; and Lorimer had issued payments to Irondequoit at its own peril.

Irondequoit was eventually declared in default by Lorimer; ICP refused to honor the bond; and the instant action ensued.

Procedural History

Lorimer commenced the main or underlying action in or about May 2002, and the third-party action was commenced by ICP in or about November 2002. Lorimer thereafter served and filed an amended complaint wherein it enlarges the monetary damages sought.

Discovery in the main action has commenced and proceeded, albeit, haltingly; discovery material has been exchanged, but depositions are outstanding. As to the third-party action, ICP asserts that it has been hindered or unable to proceed with its prosecution of that action due to its inability to locate third-party defendant Charles Walker (Iroquois’ vice-president and individual bond guarantor), and because Iroquois has vacated its corporate premises and closed its operations. The record reveals that Iroquois was dissolved on June 26, 2002 by [504]*504proclamation of the Secretary of State and pursuant to the Tax Law, for nonpayment of taxes.3

A prior motion by ICP seeking the dismissal of the main action on limitations grounds was denied by the court in November 2003, with leave to renew upon the completion of discovery which, at that time, was scheduled to be completed by January 31, 2004.

The Instant Motion

ICP citing, inter alia, the expiration of the two-year contractual limitations period, again moves for summary dismissal of the complaint, pursuant to CPLR 3211 and/or 3212.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spizz v. Eluz (In re Ampal-American Israel Corp.)
543 B.R. 464 (S.D. New York, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
6 Misc. 3d 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-95-lorimer-llc-nysupct-2004.