Ims, P.C. v. Aida Alvarez, Administrator, United States Small Business Administration

129 F.3d 618, 41 Cont. Cas. Fed. 77,177, 327 U.S. App. D.C. 126, 1997 U.S. App. LEXIS 26897, 1997 WL 596826
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 30, 1997
Docket96-5073
StatusPublished
Cited by121 cases

This text of 129 F.3d 618 (Ims, P.C. v. Aida Alvarez, Administrator, United States Small Business Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ims, P.C. v. Aida Alvarez, Administrator, United States Small Business Administration, 129 F.3d 618, 41 Cont. Cas. Fed. 77,177, 327 U.S. App. D.C. 126, 1997 U.S. App. LEXIS 26897, 1997 WL 596826 (D.C. Cir. 1997).

Opinion

WALD, Circuit Judge:

IMS, P.C. (“IMS”), a corporation that provides architectural and engineering services, brought an action in the United States District Court for the District of Columbia to challenge the refusal by the Small Business Administration (“SBA”) to revise IMS’s participation term in the SBA’s section 8(a) program for socially and economically disadvantaged businesses. IMS’s dispute with the SBA arose after the passage of the Business Opportunity Development Reform Act of 1988, Pub.L. No. 100-656, 102 Stat. 38.53 (codified as amended at 15 U.S.C. § 631 et seq. (1994)) (“BODR Act”), which, provided for revised participation terms for section 8(a) program participants. Pursuant to the Act, fhe SBA notified IMS, a participant in the section 8(a) program, that it would be given a revised program term of nine years from its first section 8(a) contract, which the SBA had determined to be a contract performed by IMS in January 1987. IMS objected to the new term, claiming that its participation term should not be calculated from the date of the January 1987 contract because that contract was brought into the section 8(a) program in violation of an agency regulation precluding acceptance of a contract that was previously the subject,of specified forms of solicitation. See 13 C.F.R. § 124.301(b)(8) (1987) (subsequently amended and renumbered 13 C.F.R. § 124.309(a) (1997)). The SBA reviewed IMS’s claims, concluded that the term had been correctly calculated, and refused IMS’s request to revise it.

The district court held that the SBA’s decision to include the January 1987 contract in the section 8(a) program did not violate the agency’s regulations and dismissed the suit for failing to state a valid claim and, in the alternative, entered summary judgment on behalf of the SBA. See IMS, P.C. v. Lader, No. 96-23 (D.D.C. Feb. 12, 1996) (unpublished bench opinion) (“Bench Op.”). Because we find that IMS has failed to establish that the SBA violated 13 C.F.R. § 124.301 (1987) when it accepted IMS’s contract with the Veterans Administration (“VA”) into the section 8(a) program, we affirm the district court’s decision to grant the SBA’s motion for summary judgment. 1

I. Background

In December 1985, IMS was accepted into the Small Business Administration’s section *620 8(a) program, which provides “small business concerns owned and controlled by socially and economically disadvantaged individuals” with “contract, financial, technical, and mangement [sic] assistance.” See 15 U.S.C. § 631(f)(2) (1994) (footnote omitted). The company was initially granted a four-year Fixed Program Participation Term that was to begin on the date of the company’s first section 8(a) contract award, subjéct, under the rules then in effect, to limited extension.

In late August 1986, th'e Engineering Department of the VA Medical Center in Bat>via, New York selected IMS to perform a small project. IMS claims, and the SBA offers no evidence to disprove, that IMS was chosen to perform the project after the VA orally solicited several small disadvantaged businesses to submit proposals. The Medical Center was apparently unaware that IMS was a section 8(a) program participant when it selected the company for the project. Accordingly, it was not until after the solicitation and selection of IMS that the project was designated a section 8(a) project.

In November 1988, Congress enacted the BODR Act, which modified the program term for section 8(a) program participants. The final rules implementing the changes required by the Act provided that program participants as of September 1, 1988, would be given a revised program term of “the greater of nine years from the date of the Participant’s first contract pursuant to section 8(a) or the Participant’s Fixed Program Participation Term (FPPT) expiration date, including any extension thereof, plus 18 months.” 13 C.F.R. § 124.110(c) (1989).

In a letter dated December 14, 1988, the SBA informed Iqbal Singh, the president of IMS, that the BODR Act provided IMS with a revised term of participation in the section 8(a) program of nine years from IMS’s first contract under the program, which the SBA had determined to be IMS’s January 1987 contract with the VA. The letter requested that Mr. Singh sign and return the letter, which he did without objection.

Between 1989 and 1994, IMS contacted the SBA several times in an effort to change its program term. IMS claimed then, as it does now, that the VA contract was not the proper starting point of IMS’s section 8(a) program term because the contract was brought into the program only after the VA had engaged in a public solicitation for offers and selected IMS. The SBA maintained in each of its responses that it had found no basis for IMS’s contention that the VA contract was inappropriately brought into the program.

In August 1995, IMS submitted additional materials to the SBA in support of its continuing request to change its program term. 2 The SBA’s District Counsel, -Mollie Gaughan, reviewed the material presented by IMS and concluded that “[t]here is no evidence in the contract file to support the premise that solicitation was previously published” and, therefore, “the program participation date was properly established.” Memorandum from Mollie B. Gaughan, District Counsel, to Michael McHale, Deputy Administrator Minority Enterprise Development (Oct. 4, 1995). In response to Ms. Gaughan’s memorandum, the SBA’s Acting Deputy Associate Administrator, Michael McHale, wrote a memorandum in which he outlined his decision to reject IMS’s request to extend its program term. In his memorandum, he noted: “The documentation provided by your office indicates that proper offer acceptance procedure was followed in taking the requirement into the 8(a) program.” Memorandum from Michael P. McHale, Acting Deputy Associate Administrator, to Millie B. Gaughan, District Counsel (Oct. 31, 1995). On November 1, 1995, Franklin Sciortino, SBA’s District Director for Buffalo, New York, wrote to Mr. Singh at IMS advising him that the Central Office had denied IMS’s request for a new participation term expiration date. See Letter from Frank J. Sciortino, District Director, to Iqbal Singh, President, IMS, P.C. (Nov. 1,1995).

In January 1996, IMS filed a complaint seeking judicial review of the SBA’s refusal to amend its section 8(a) program term and requesting injunctive relief to prevent the expiration of its term. On February 12, *621 1996, the district court dismissed the suit for failing to state a valid claim and, in the alternative, entered summary judgment on behalf of the SBA. This appeal ensued.

II. Analysis

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oceana, Inc. v. Bryson
District of Columbia, 2020
Stone v. U.S. Embassy Tokyo
District of Columbia, 2020
Sec. Univ. v. Acosta
317 F. Supp. 3d 343 (D.C. Circuit, 2018)
Oceana, Inc. v. Pritzker
217 F. Supp. 3d 310 (District of Columbia, 2016)
Save Jobs USA v. U.S. Department of Homeland Security
210 F. Supp. 3d 1 (District of Columbia, 2016)
Reinhard v. Johnson
209 F. Supp. 3d 207 (District of Columbia, 2016)
Butte County, California v. Hogen
197 F. Supp. 3d 82 (District of Columbia, 2016)
University of Colorado Health at Memorial Hospital v. Burwell
151 F. Supp. 3d 1 (District of Columbia, 2015)
Oceana, Inc. v. Gutierrez
126 F. Supp. 3d 110 (District of Columbia, 2015)
Safari Club International v. Jewell
111 F. Supp. 3d 1 (District of Columbia, 2015)
Stand Up for California! v. United States Department of Interior
71 F. Supp. 3d 109 (District of Columbia, 2014)
Silver State Land, LLC v. Beaudreau
59 F. Supp. 3d 158 (District of Columbia, 2014)
National Parks Conservation Ass'n v. Jewell
62 F. Supp. 3d 7 (District of Columbia, 2014)
Cumberland Pharmaceuticals Inc. v. Food and Drug Administration
981 F. Supp. 2d 38 (District of Columbia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
129 F.3d 618, 41 Cont. Cas. Fed. 77,177, 327 U.S. App. D.C. 126, 1997 U.S. App. LEXIS 26897, 1997 WL 596826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ims-pc-v-aida-alvarez-administrator-united-states-small-business-cadc-1997.