Illinois Power Co. v. Commissioner

83 T.C. No. 47, 83 T.C. 842, 1984 U.S. Tax Ct. LEXIS 8
CourtUnited States Tax Court
DecidedNovember 29, 1984
DocketDocket No. 14701-79
StatusPublished
Cited by13 cases

This text of 83 T.C. No. 47 (Illinois Power Co. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Power Co. v. Commissioner, 83 T.C. No. 47, 83 T.C. 842, 1984 U.S. Tax Ct. LEXIS 8 (tax 1984).

Opinion

Wilbur, Judge:

Respondent determined the following deficiencies in petitioner’s Federal income tax:

TYE Dec. 31— Amount
1975 . $7,090,791.12
1976 . 644,094.74

After concessions, two issues remain for our consideration:

(1) Whether unit 3 of petitioner’s Baldwin Power Station was constructed by the petitioner or acquired by the petitioner for purposes of computing the investment tax credit; and

(2) Whether amounts designated as "Rider R Income” collected from certain gas utility customers constitute taxable income in the . year of receipt.

Some of the facts have been stipulated and are found accordingly. The several stipulations of fact and attached exhibits are incorporated herein by reference.

FINDINGS OF FACT

Illinois Power Co. (hereinafter referred to as petitioner or Illinois Power) is an Illinois corporation with its principal office at Monticello, IL. Petitioner filed its Federal income tax returns (Forms 1120) for the taxable years ended December 31, 1975, and December 31, 1976, with the District Director of Internal Revenue at Chicago, IL. Petitioner has been, at all times here pertinent, engaged in the manufacture and sale of electric power to areas in central and southern Illinois aggregating approximately 15,000 square miles. During periods relevant to this case, petitioner also distributed and sold natural gas to approximately 350,000 commercial, industrial, residential, and certain seasonal consumers in the same geographical area.

Unit 3 - Baldwin Power Station

Illinois Power is a public utility within the meaning of article I, section 10, of an act entitled "An Act Concerning Public Utilities,” approved June 29,1921, as amended and now in effect in the State of Illinois. This act is commonly referred to as the "Public Utilities Act.” On August 24,1966, petitioner filed a petition with the Illinois Commerce Commission (ICC), in which it alleged as follows: "To provide adequate operating and reserve capacity for its present and future electric power supply requirements in Illinois, it is necessary that petitioner construct and thereafter operate and maintain additional electric supply facilities.” Illinois Power requested, inter alia, that the ICC issue a certificate of public convenience and necessity to construct, operate, and maintain a multiunit mine-mouth steam electric generating station and substation facilities in Randolph County, IL, to be known as the Baldwin Power Station. After a hearing, a certificate to the effect that public convenience and necessity required the construction, operation, and maintenance of a unit steam electric generating powerplant was granted to petitioner on October 19, 1966.

As of December 12, 1966, Illinois Power owned or had under option approximately 3,546 of the 3,830 acres of land needed to construct the Baldwin Power Station. By a petition dated December 12, 1966, petitioner sought an order, which was subsequently granted, empowering it to use the power of eminent domain of the State of Illinois to obtain title or a perpetual easement to the additional 284 acres required for the construction, operation, and maintenance of the Baldwin Power Station.

Construction of the Baldwin Power Station commenced in March of 1967. Unit 1, with a generating capacity of 605 megawatts, went into commercial service on July 11, 1970.1 The construction of unit 2 commenced in February of 1969. That unit, with a generating capacity of 605 megawatts, was placed in commercial service on May 21, 1973. The construction of unit 3 commenced in 1971. Unit 3, with a nameplate generating capacity of 585 megawatts, was placed in commercial service on June 20, 1975.

The construction of unit 1 included the construction or provision of many facilities which were intended to be and were in fact ultimately utilized in common by all three units, including the following: (1) 2000-acre cooling lake; (2) intake crib and pump house to pump water from Kaskaskia River to the cooling lake; (3) 600-acre ash pond; (4) centralized control room; (5) coal handling facilities, including trash hopper outlets, conveyors, bins, separators, and chutes; (6) railroad spur from Gulf, Mobile & Ohio Railroad; (7) railroad tracks to transport coal to coal handling facilities; (8) computer room; (9) circulating water system; (10) sewage disposal system; (11) parking lot; (12) fencing; and (13) fire protection system. A substantial part of the total construction costs of unit I was for the development of such common facilities and equipment for all three units.

The total cost as of December 31, 1976, of the three units at the Baldwin Power Station (as reported by Illinois Power to the ICC) was $346,903,816. These costs were broken down as follows:

Land and land rights. $2,587,911
Structure and improvements. 80,128,638
Equipment costs. 264.187,267
Total cost. 346,903,816

Unit 3 of the Baldwin Power Station is an extremely complex facility consisting of hundreds of components and was technologically difficult to design and construct. It is approximately the height of a 24-story building, and the boiler alone weighs 10,000 tons. The total cost of unit 3 as computed from reports filed by the petitioner with the ICC, was as follows:

Structures and improvements. $31,638,686
Equipment costs. 95.670.814
Total cost. 2127,309,500

In addition, the land and land rights for all three units amounted to $2,587,911.

Illinois Power had a construction department, but did not itself perform the physical construction work required when a new generating plant was built or an addition made to an existing plant. The primary function of petitioner’s construction department was to oversee and monitor such work performed by outside contractors. Petitioner’s construction department included approximately 24 supervisory and professional employees who were trained engineers. This number also included inspectors responsible for the construction work performed by contractors on petitioner’s transmission lines and substation facilities. Illinois Power did not have sufficient personnel to construct a powerplant utilizing only its own employees.

Sargent & Lundy is an engineering partnership specializing in the design of steam-generated electrical power plants. Its capabilities range from partial assistance in designing a project to complete construction management. The particular services it provides are determined by the requirements of the client. Sargent & Lundy itself does not engage in the physical construction of power plants. It views itself as a professional service organization, and its philosophy is that the professional services it provides should be separate from construction contracting and labor. Illinois Power has been a client of Sargent & Lundy since 1947.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vandenbosch v. Comm'r
2016 T.C. Memo. 29 (U.S. Tax Court, 2016)
Comptroller of the Treasury v. Washington Gas Light Co.
650 A.2d 241 (Court of Appeals of Maryland, 1994)
Continental Illinois Corp. v. Commissioner
1989 T.C. Memo. 636 (U.S. Tax Court, 1989)
Carlstedt Associates, Inc. v. Commissioner
1989 T.C. Memo. 27 (U.S. Tax Court, 1989)
American Tel. & Tel. Co. v. Commissioner
1988 T.C. Memo. 35 (U.S. Tax Court, 1988)
Indianapolis Power & Light Co. v. Commissioner
88 T.C. No. 52 (U.S. Tax Court, 1987)
Iowa Southern Utilities Co. v. United States
11 Cl. Ct. 868 (Court of Claims, 1987)
Miyamoto v. Commissioner
1986 T.C. Memo. 313 (U.S. Tax Court, 1986)
Costello v. Commissioner
1985 T.C. Memo. 571 (U.S. Tax Court, 1985)
Illinois Power Co. v. Commissioner
83 T.C. No. 47 (U.S. Tax Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
83 T.C. No. 47, 83 T.C. 842, 1984 U.S. Tax Ct. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-power-co-v-commissioner-tax-1984.