Ich 3 Atlanta Sugarloaf Apartments, L.P. v. Hart Gaugler and Associates, Inc.

CourtCourt of Appeals of Georgia
DecidedMarch 16, 2026
DocketA25A1894
StatusPublished

This text of Ich 3 Atlanta Sugarloaf Apartments, L.P. v. Hart Gaugler and Associates, Inc. (Ich 3 Atlanta Sugarloaf Apartments, L.P. v. Hart Gaugler and Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ich 3 Atlanta Sugarloaf Apartments, L.P. v. Hart Gaugler and Associates, Inc., (Ga. Ct. App. 2026).

Opinion

FIRST DIVISION BROWN, C. J., BARNES, P. J., and WATKINS, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

March 16, 2026

In the Court of Appeals of Georgia A25A1894. ICH 3 ATLANTA SUGARLOAF APARTMENTS, L. P. v. HART GAUGLER AND ASSOCIATES, INC. A25A1895. ICH 3 ATLANTA SUGARLOAF APARTMENTS, L. P. v. WAKEFIELD BEASLEY & ASSOCIATES, INC. et al.

BARNES, Presiding Judge.

These companion appeals arise from the construction of a mixed use apartment

complex purchased by ICH 3 Atlanta Sugarloaf Apartments, L. P. (“ICH”). In Case

No. A25A1894, ICH appeals the grant of summary judgment to Hart Gaugler and

Associates (“Hart Gaugler”) in its professional negligence claim against that

structural engineering firm,. In Case No. A25A1895, ICH appeals the trial court’s

grant of summary judgment to Wakefield Beasley & Associates (“WBA”) in ICH’s

defective design and construction claim against that architectural firm. For the reasons

that follow, we reverse the judgment in both cases. “On appeal from a trial court’s grant or denial of summary judgment, our

review of the record is de novo, and we construe the facts and all inferences drawn

from them in the light most favorable to the nonmoving party.” Centurion Indus. v.

Naville-Saeger, 352 Ga. App. 342, 343 (834 SE2d 875) (2019) (citation and

punctuation omitted).

So viewed, the record demonstrates that in 2017, Sugarloaf Walk Apartments,

L. P., a non-party, hired WBA to provide architectural services related to the

construction of Sugarloaf Walk Mixed Use Project (“the Project”), a five building

apartment complex. WBA subcontracted Hart Gaugler to perform structural

engineering services in connection with the project. The Project was completed in

2019, and in 2020, ICH purchased the finished Project from Sugarloaf Walk

Apartments. In August of 2021, there were reports of moisture intrusion at various

locations on the property. A subsequent “Exterior Condition Survey” identified

various issues with all five buildings, including water intrusion and moisture damage,

structural defects, and other issues. ICH filed the complaint against WBA, Hart

Gaugler, and multiple other parties involved in construction of the property. ICH

alleged that WBA and Hart Gaugler were negligent in “preparing designs, plans and

2 specifications for the construction” of the Project, and had a duty, as licensed design

professionals, to, among other things, perform work in accordance with industry

standards, and had breached that duty. ICH further alleged that the negligent design

work was responsible for safety issues and extensive property damage to the Project’s

buildings, including shrinkage of wood framing, deformities in the window sills and

flashing, and reverse sloping with water being directed to the exterior walls. ICH also

alleged that the defects and deficiencies in the plans and design documents of WBA

and Hart Gaugler “caused damage at various locations where contractors had installed

their work in compliance with the plans and design documents.” Other allegations

included that Hart Gaugler and WBA’s negligently prepared design plans and

documents were not clear and were subject to foreeseeable misinterpretation. ICH

also alleged that WBA negligently performed construction phase services during the

construction.

Regarding damages, ICH claimed that,

actual damages include, but are not limited to, (1) the costs of identifying the cause of the property damage in the Sugarloaf Project and designing proper remediation; (ii) the costs of removing and re-placing non- damaged property as needed to expose and repair damaged materials and the defective conditions causing such damage; (iii) the costs of repairing

3 damaged property; (iv) the costs associated with financing remedial work; (v) the loss of use of portions of the Sugarloaf Project; (vi) the loss of revenue resulting from the pervasive defects; (vii) the cost of reputational harm and any diminution in the value of the Sugarloaf Project resulting from the pervasive and serious defects and damage; and (viii) attorney fees and litigation expenses incurred in bringing these claims, all caused by acts of the Defendants.

ICH’s experts averred to numerous instances of professional negligence alleged

to have caused damage to the Property. Among the extensive findings listed in his

report, the engineering expert averred that WBA’s plans were “unclear, inconsistent,

incomplete and ambiguous to such an extent that they failed to guard against the

foreseeable possibility that a contractor could misinterpret or fail to follow [WBA’s]

intent.” The expert also averred that

[c]ritical portions of [WBA’s] plans and specifications for the roof, exterior walls, balconies, elevated walkways, below grade waterproofing, framing, and other portions of the exterior building envelope of the buildings in [the Project] were not clear and definitive, and were instead incomplete, inconsistent, ambiguous and or subject to foreseeable misinterpretation.

The expert noted that “multiple contractors performed careless work without seeking

clarifications from [WBA],” and opined “to a reasonable degree of certainty” that

4 “[WBA] delivered drawings that, when followed, resulted in a Project that violates the

building code because the plans fail to provide an adequate exterior wall envelope

design.”

ICH’s architecture expert averred that he “noted the same instances of

defective plans, that, when constructed lead to defective construction.” He further

averred that for the same reasons identified in the engineer’s affidavit, “the

architect’s contract administration services failed to meet the standard of care by

ignoring, failing to reject, and ultimately approving significant defective construction

in place.” He opined that “the deviations from the standard of care amount to

professional negligence by [WBA].”

The trial court granted Hart Gaugler and WBA’s subsequent motions for

summary judgment, and these appeals ensued.

Case No. A25A1894.

1. In its motion for summary judgment, Hart Gaugler asserted, among other

things, that ICH’s claims “are tort claims (negligence), and the alleged duties arise

only out of the Hart Gaugler agreement with WBA. The undisputed facts demonstrate

that [ICH] is not in privity of contract with Hart Gaugler. Therefore, [ICH’s] claims

5 are barred by OCGA § 51-1-11 (a).[1] Hart Gaugler owes [ICH] no duty with regard to

the Sugarloaf Walk Project[.]” In opposing summary judgment ICH argued, among

other things, that there remained material issues of fact that wood shrinkage was

responsible for damage to the property, and that Hart Gauger did not adequately

accommodate for the shrinkage in its engineering plans.

Following a hearing on the motion, the trial court granted summary judgment

to Hart Gaugler. The trial court found that,

[ICH] seeks to recover the costs to repair and remediate the Sugarloaf Walk Apartment Project, which costs are economic losses as a matter of law. [ICH’s] professional negligence claim is not subject to any recognized exception under Georgia law. Since [ICH] seeks to hold Hart Gaugler liable for violation of duties that arise from the contract between

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strozier v. Simmons U. S. A. Corp.
385 S.E.2d 677 (Court of Appeals of Georgia, 1989)
Versico, Inc. v. Engineered Fabrics Corp.
520 S.E.2d 505 (Court of Appeals of Georgia, 1999)
Driebe v. Cox
416 S.E.2d 314 (Court of Appeals of Georgia, 1992)
Howard v. Dun & Bradstreet, Inc.
220 S.E.2d 702 (Court of Appeals of Georgia, 1975)
Richmond County v. Sibert
126 S.E.2d 761 (Supreme Court of Georgia, 1962)
Covil v. Robert & Co. Associates
144 S.E.2d 450 (Court of Appeals of Georgia, 1965)
Cowart v. Widener
697 S.E.2d 779 (Supreme Court of Georgia, 2010)
Dominic v. Eurocar Classics
714 S.E.2d 388 (Court of Appeals of Georgia, 2011)
Jai Ganesh Lodging, Inc. v. David M. Smith, Inc.
760 S.E.2d 718 (Court of Appeals of Georgia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Ich 3 Atlanta Sugarloaf Apartments, L.P. v. Hart Gaugler and Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ich-3-atlanta-sugarloaf-apartments-lp-v-hart-gaugler-and-associates-gactapp-2026.