ICF Kaiser Engineers, Inc. v. Superior Court

89 Cal. Rptr. 2d 88, 75 Cal. App. 4th 226, 99 Cal. Daily Op. Serv. 7999, 99 Daily Journal DAR 10143, 1999 Cal. App. LEXIS 874
CourtCalifornia Court of Appeal
DecidedSeptember 27, 1999
DocketB131431
StatusPublished
Cited by7 cases

This text of 89 Cal. Rptr. 2d 88 (ICF Kaiser Engineers, Inc. v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ICF Kaiser Engineers, Inc. v. Superior Court, 89 Cal. Rptr. 2d 88, 75 Cal. App. 4th 226, 99 Cal. Daily Op. Serv. 7999, 99 Daily Journal DAR 10143, 1999 Cal. App. LEXIS 874 (Cal. Ct. App. 1999).

Opinion

Opinion

VOGEL (Miriam A.),J.

A general contractor agreed to do some work for an owner. was owner part but not all of the contractor’s fees. As they had agreed in advance, the *229 parties then arbitrated their dispute before a distinguished panel of three arbitrators, where the contractor prevailed. When the contractor filed a petition to confirm the arbitrators’ award, the owner alleged—for the first time—that the contractor’s license had been suspended at the time the contract was entered and while the work was being performed. This came as a surprise to the contractor, and the petition to confirm the award was withdrawn so the matter could be investigated. The owner then petitioned to vacate the arbitrators’ award. The contractor opposed that petition, claiming substantial compliance with the licensing statute. An evidentiary hearing was held, after which the trial court entered judgment for the owner and vacated the arbitrators’ award. The contractor applied to us for an extraordinary writ. We grant the contractor’s petition.

Facts

In October 1995, ICF Kaiser Engineers, Inc. (Kaiser) agreed to and did perform earthquake remediation work for Sepulveda Harteras, Ltd., a partnership. 1 By the time the project was concluded, Kaiser had billed Sepulveda about $1.9 million. By October 1996, Sepulveda had paid about $700,000, leaving about $1.2 million still due to Kaiser. As they had agreed they would in the event of a dispute, the parties submitted the matter to arbitration. On August 28, 1998, the arbitration panel (James Acret, a lawyer specializing in construction disputes, and two retired judges, Hon. George M. Dell and Hon. Leon Savitch) awarded $800,000 to Kaiser. On September 14, Kaiser filed a petition to confirm the arbitration award. 2

In opposition to Kaiser’s petition, Sepulveda contended that Kaiser’s claim was barred because (according to the records of the Contractors’ State License Board) Kaiser’s contractor’s license had been suspended at the time the contract was entered and during the construction period (specifically, *230 from September 22, 1995, to February 15, 1996). 3 Kaiser, in turn, took its petition off-calendar in order to determine the basis for Sepulveda’s claim and the reason for the problem with the Board’s records. Several months later, Sepulveda filed a petition to vacate the arbitration award (in the mechanic’s lien action, not the action in which Kaiser’s petition to confirm had been filed). Kaiser opposed the petition to vacate. By the time of the hearing on that petition, the evidence before the trial court established that Kaiser, a subsidiary of ICF Kaiser International, Inc., is an international engineering and construction firm. As such, it must comply with the licensing requirements imposed by each state in which it does business. At the times relevant to this dispute, the employee primarily responsible for processing the paperwork necessary to obtain and maintain Kaiser’s licenses was Catherine Howland, a clerk in Kaiser’s legal department.

Leaving to one side whether Kaiser should have known there was a problem with its license, the evidence is undisputed that, until the time Sepulveda opposed Kaiser’s motion to confirm the arbitration award, Kaiser had no actual knowledge that its license had been suspended, and everyone involved believed that Kaiser was properly licensed. Although it usually did so when there was any problem (albeit as a courtesy and not because it was required to do so), the Board did not issue a Notice of Suspension that would have put Kaiser on notice of a problem. In fact, as the result of a computer glitch, the Board itself was (for all practical purposes) unaware of the problem and, as will appear, an inquiry to the Board during the time of the “suspension” would have elicited a response that Kaiser’s license was in good standing.

The problem that resulted in the suspension occurred because Kaiser, as a corporation, can qualify for a contractor’s license only through a “responsible managing officer” (RMO) or “responsible managing employee” (RME) who meets the Board’s requirements for a contractor’s license. (§ 7068, subd. (b)(3).) The RMO or RME (the qualifier) must be an officer or employee of the corporation, and must be actively engaged in the work covered by the license. (§§ 7068, subd. (d), 7068.1.) Until June 24, 1995, Kaiser’s qualifier was Richard Scott Hergenrader, but Hergenrader’s association with Kaiser ended on June 24. Hergenrader’s disassociation triggered a 90-day period within which Kaiser had to replace him with another *231 qualifier or suffer a suspension of its license. (§ 7068.2 [if a corporation’s qualifier leaves the corporation’s employ, the corporation or the qualifier must notify the Board in writing, and the corporation must replace the qualifier within 90 days by filing a new application designating the new qualifier].) On July 18, Kaiser submitted an application to the Board to substitute Christopher Meyer as its qualifier. Meyer, who had not taken the necessary licensing examination, was scheduled by the Board to take the test on October 10 (more than three weeks before Kaiser entered its contract with Sepulveda).

On August 14, the Board returned Kaiser’s application to substitute Meyer for Hergenrader, explaining that the application could not be processed because there had been no formal notification of Hergenrader’s departure from Kaiser. Kaiser resubmitted the application, this time accompanied by a notice of Hergenrader’s disassociation, but the paperwork was returned again on September 13, this time because Kaiser had failed to identify the effective date of Hergenrader’s disassociation. On September 19, Kaiser resubmitted its application, which was accepted. On September 20, the Board sent Kaiser a form notice confirming the date of Hergenrader’s disassociation and advising Kaiser that its license would be suspended unless, within 90 days from the date of disassociation (that is, by September 22), Hergenrader was replaced with a qualified RMO. In the same notice, the Board advised Kaiser that it had received and was processing Meyer’s application to serve as Kaiser’s qualifier.

On October 10, Meyer took and passed the examination. On the same day, the Board notified Kaiser that it had satisfied the necessary requirements to replace its qualifier and that,, by January 9, 1996, it should submit a “Bond of Qualifying Individual (Q.I. bond). (§ 7074, subd. (e) [an application for a change of qualifier becomes void if the applicant, after notice to do so, fails to file a Q.I. bond within 90 days from the date of the notice].) On October 18, the Board notified Kaiser that the Q.I. bond had to be received by January 16, 1996 (not January 9) and, in the same notice, requested specified insurance certificates, which were submitted by Kaiser on October 23, 1995.

On October 26, the Q.I. bond for Meyer was issued and sent by the surety to Catherine Howland at Kaiser. As the result of a clerical oversight, the bond was not submitted by Howland to the Board (years later, the original bond, dated October 26, 1995, was found in Kaiser’s licensing file), and was not in the Board’s possession on October 30, the date Kaiser entered its contract with Sepulveda.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Caisson & Shoring v. Bernards Bros. CA2/3
236 Cal. App. 4th 1246 (California Court of Appeal, 2015)
Pacific Caisson & Shoring v. Bernards Bros.
California Court of Appeal, 2015
Pacific Caisson & Shoring, Inc. v. Bernards Bros.
198 Cal. App. 4th 681 (California Court of Appeal, 2011)
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co.
115 P.3d 41 (California Supreme Court, 2005)
Slatkin v. White
126 Cal. Rptr. 2d 54 (California Court of Appeal, 2002)
Smith v. Workers' Compensation Appeals Board
116 Cal. Rptr. 2d 728 (California Court of Appeal, 2002)
Pacific Custom Pools, Inc. v. Turner Construction Co.
94 Cal. Rptr. 2d 756 (California Court of Appeal, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
89 Cal. Rptr. 2d 88, 75 Cal. App. 4th 226, 99 Cal. Daily Op. Serv. 7999, 99 Daily Journal DAR 10143, 1999 Cal. App. LEXIS 874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/icf-kaiser-engineers-inc-v-superior-court-calctapp-1999.