ICE Corp. v. Hamilton Sundstrand Inc.

444 F. Supp. 2d 1165, 2006 U.S. Dist. LEXIS 55455, 2006 WL 2255698
CourtDistrict Court, D. Kansas
DecidedAugust 7, 2006
Docket05-4135-JAR
StatusPublished
Cited by22 cases

This text of 444 F. Supp. 2d 1165 (ICE Corp. v. Hamilton Sundstrand Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ICE Corp. v. Hamilton Sundstrand Inc., 444 F. Supp. 2d 1165, 2006 U.S. Dist. LEXIS 55455, 2006 WL 2255698 (D. Kan. 2006).

Opinion

MEMORANDUM AND ORDER

ROBINSON, District Judge.

The Court now considers defendants Hamilton Sundstrand Inc. and Ratier-Fig-eac, S.A.’s motions to dismiss (Docs.15-16). Defendants contend that the first through fourth claims in the Complaint should be dismissed because plaintiff does not allege facts to support them. The motion is now fully briefed and the Court is prepared to rule. Defendants’ motions to dismiss are granted in part and denied in part as described more fully below.

1. Standard

Dismissal under Fed.R.Civ.P. 12(b)(6) is appropriate only if it is clear that no relief could be granted under any set of facts that could be proved consistent with the allegations. 1 The purpose of Rule 12(b)(6) is to allow a defendant to test whether, as a matter of law, the plaintiff is entitled to legal relief even if everything alleged in the complaint is true. 2

*1168 On a Rule 12(b)(6) motion, the court judges the sufficiency of the complaint, accepting as true the well-pleaded factual allegations and drawing all reasonable inferences in favor of the plaintiff. 3 These deferential rules, however, do not allow the court to assume that a plaintiff can prove facts that it has not alleged or that the defendants have violated the laws in ways that have not been alleged. 4 If the facts narrated by the plaintiff “do not at least outline or adumbrate” a viable claim, the complaint cannot pass Rule 12(b)(6) muster. 5 Dismissal is a harsh remedy to be used cautiously so as to promote the liberal rules of pleading while protecting the interest of justice. 6

II. Background

The following facts are alleged in the Complaint, and the Court draws all reasonable inferences in favor of plaintiff. Plaintiff ICE Corporation (“ICE”) is engaged in the business of design, development, production and manufacture of anti-icing equipment and components for various kinds of aircraft. ICE entered into a Memorandum of Understanding (“MOU”) on November 8, 2004, to conduct research and development of a deicing propeller system for an A400M military transport aircraft being developed by EADS.

The MOU lists ICE and defendant Ratier-Figeac, S.A. (“Ratier”) as parties. Its stated purpose “is to authorize ICE, subject to the conditions of this agreement, to proceed with design and development, procurement of material, and the manufacture, assembly, and test of hardware of the Deicing System.” The MOU states its estimated value as $3.36 million. The Complaint alleges defendants misrepresented to ICE that they were retaining ICE to perform all work, including design, development, manufacture and production, in connection with the deicing systems and controller for the Airbus A400M project. The Complaint further alleges defendants misrepresented that the value of the MOU, governing ICE’s work on the project, had a minimum value of $3.36 million.

One of the terms of the MOU is that ICE agrees to maintain its current pricing “on the ‘New* Hamilton Sundstrand Long Term Agreement for a maximum of three (3) years.” The Complaint alleges Hamilton Sundstrand Inc. (“Hamilton”) used the MOU as a negotiating tool to reduce their cost on all products covered by a separate long-term agreement signed by ICE with Hamilton.

Prior to executing the MOU, ICE had a long-standing business relationship with defendant Hamilton. ICE alleges Ken Mantha of Hamilton initially contacted ICE concerning the development of the deicing product. The Complaint alleges Mantha advised ICE that Ratier was a totally owned subsidiary of Hamilton and that it was in charge of the engineering development effort, including the deicing product. The Complaint alleges that “each defendant was acting partner, joint venturer, agent and/or representative of the other, and entered into the agreements and understood the conduct described .” Further, the Complaint states that under agency theory, “each defendant acted with the knowledge of, instruction by, or apparent, implied or actual authority of the oth *1169 er defendant, or acted on behalf of both defendants.”

During the development phase of the project, Ratier changed a number of specifications and requirements, causing the selling price to rise. ICE alleges it consulted with Hamilton about these changes before placing purchase orders. Hamilton authorized ICE to proceed in designing the deicing system to meet certain new requirements. Soon after, ICE received a memorandum that they were to proceed with an upgraded design system to meet new requirements. The Complaint alleges these notifications to proceed continued to misrepresent that defendants were retaining ICE to perform all work on the Airbus A400M project.

The parties entered into a new round of negotiations for an increased price of the system. In June 2005, Ratier and Hamilton rejected all of ICE’s proposals and demanded a fixed price per unit over a twenty-year period of time. Ratier then instructed ICE to stop all development work on the product. The MOU provides that it may only terminate upon either (1) the award of a Master Term Agreement, a Purchase Agreement, and a Product Support Agreement to ICE, or (2) agreement of the parties.

III. Analysis

ICE alleges five claims for relief in the Complaint against both defendants: (1) breach of contract; (2) breach of implied contract; (3) unjust enrichment; (4) negligent misrepresentation; and (5) misappropriation of trade secrets. Defendant Hamilton moves to dismiss the first four claims, and defendant Ratier moves to dismiss claims two, three and four. The Court will address each claim in turn.

A. Breach of Written Contract against Hamilton (Claim 1)

The elements for a breach of contract claim are: (1) the existence of a contract between the parties; (2) consideration; (3) the plaintiffs performance or willingness to perform in compliance with the contract; (4) defendant’s breach of the contract; and (5) that plaintiff was damaged by the breach. 7 Hamilton disputes only the allegation that it was a party to the contract, arguing the face of the MOU shows that it neither incurred obligations nor was a signatory to the contract. 8 ICE maintains that Hamilton is either a subsidiary, an alter-ego, or an agent of Ratier, such that it is a party to the MOU.

A parent corporation may be held liable for the contractual obligations of its subsidiary corporation when the subsidiary is no more than the agent or “alter ego” of the parent corporation. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 F. Supp. 2d 1165, 2006 U.S. Dist. LEXIS 55455, 2006 WL 2255698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ice-corp-v-hamilton-sundstrand-inc-ksd-2006.