Hyundai America, Inc. v. Meissner & Wurst GmbH & Co.

26 F. Supp. 2d 1217, 1998 U.S. Dist. LEXIS 17993, 1998 WL 790701
CourtDistrict Court, N.D. California
DecidedNovember 6, 1998
DocketC-98-20835 JF (EAI)
StatusPublished
Cited by12 cases

This text of 26 F. Supp. 2d 1217 (Hyundai America, Inc. v. Meissner & Wurst GmbH & Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hyundai America, Inc. v. Meissner & Wurst GmbH & Co., 26 F. Supp. 2d 1217, 1998 U.S. Dist. LEXIS 17993, 1998 WL 790701 (N.D. Cal. 1998).

Opinion

ORDER GRANTING RESPONDENTS’ MOTION TO DISMISS

FOGEL, District Judge.

Respondents Meissner & Wurst GmbH & Co.—U.S. Operations, Inc., and Meissner + Wurst, U.S. Operations, Inc.’s (collectively “M+W” or “Respondents”) motion to dismiss or, alternatively, for summary judgment came before the Court on October 13, 1998. The Court took the motion under submission for decision on the basis of the papers filed by the parties pursuant to Civil Local Rule 7-l(b). The Court has read the moving and responding papers and considered the applicable law. For the reasons set forth below, the motion to dismiss is granted.

I. BACKGROUND

This action arises out of a petition to consolidate two separate interstate arbitration proceedings. The relevant underlying facts are not in dispute.

On July 27,1995, Petitioner Hyundai Electronics America and Respondents M+W entered into a Professional Services Agreement (the “Design Agreement”) by which M+W was to engineer and design a silicon wafer fabrication facility (the “fab”) in Eugene, Oregon. The parties expressly agreed that any disputes arising from the Design Agreement were to be arbitrated in San Francisco, California, according to California law.

Thereafter, on March 21, 1996, Petitioner Hyundai America, Inc. and Respondents M+W entered into a second agreement, the Construction Contract, by which M+W agreed to assume responsibility for the construction, commissioning, and start-up of the fab. The Construction Contract specifies that any disputes arising under its provisions are to be arbitrated in Eugene, Oregon, according to Oregon law and the applicable laws of the United States.

Since the parties entered into these contracts, disputes have arisen related to the timeliness, quality, and cost of M+W’s per- *1218 formalice under both agreements. On April 24,1998, Petitioners initiated arbitration proceedings under both contracts and contemporaneously requested consolidation before a single arbitration panel. M + W objected. The American Arbitration Association, the entity charged with administering the arbitration proceedings, declined the request for consolidation, claiming that it had no authority to consolidate the proceedings in light of M+W’s objection and the absence of a specific contractual provision calling for such action. Petitioners then filed a Petition for Consolidation of Separate Arbitration Proceedings (the “Petition”) with this Court requesting that the Court order consolidated proceedings pursuant to California Code of Civil Procedure § 1281.3.

M+W now moves to dismiss the Petition pursuant to Federal Rule of Civil Procedure 12(b)(6) or, alternatively, for summary judgment essentially on the grounds that the express terms of the arbitration contracts require two separate arbitration proceedings and that the Federal Arbitration Act, 9 U.S.C. § 1 et seq., which governs the Construction Contract, precludes consolidation in the absence of a contractual provision authorizing such action. 1

II. LEGAL STANDARD

The issue to be decided on a motion to dismiss is whether the moving party has shown beyond a doubt that the opposing party can prove no set of facts in support of its claim entitling it to relief. Conley v. Gibson, 355 U.S. 41, 78 S.Ct. 99, 102, 2 L.Ed.2d 80 (1957). A complaint may be dismissed as a matter of law for two reasons: (1) lack of a cognizable legal theory or (2) insufficient facts under a cognizable legal theory. Robertson v. Dean Witter Reynolds, Inc., 749 F.2d 530, 533-34 (9th Cir.1984)(citing 2A J. Moore, Moore’s Federal Practice V 12.08 at 2271 (2d ed.1982)). In determining a motion to dismiss, all allegations of the complaint should be construed in the opposing party’s favor. Sun Savings & Loan Assoc. v. Dierdorff, 825 F.2d 187, 191 (9th Cir.1987). Moreover, to dismiss, it must appear to a certainty that the plaintiff would not be entitled to relief under any set of facts that could be proved. Wool v. Tandem Computers, Inc., 818 F.2d 1433, 1439 (9th Cir.1987). Therefore, motions to dismiss generally are viewed with disfavor under this liberal standard. Intake Water Co. v. Yellowstone River Compact Commission, 590 F.Supp. 293, 296 (D.C.Mont.1983), aff'd, 769 F.2d 568 (9th Cir.1985), ce rt. denied, 476 U.S. 1163, 106 S.Ct. 2288, 90 L.Ed.2d 729 (1986).

III. DISCUSSION

Despite the parties’ differing formulations of the issue, the central question before the Court is whether this Court can compel consolidation of separate interstate arbitration proceedings under California Code of Civil Procedure § 1281.3 as requested by Petitioners. 2 M+W contends that the express venue and choice of law provisions of the arbitration agreements unambiguously require two separate proceedings. M+W emphasizes that two distinct Hyundai entities agreed to fundamentally different dispute resolution provisions and that, in the absence of some underlying defense to the validity of the contracts, unambiguous contracts must be enforced according to their terms.

“Arbitration is a creature of contract.” Scherk v. Alberto-Culver Co., 417 U.S. 506, 519, 94 S.Ct. 2449, 41 L.Ed.2d 270 (1974). General state law principles of contract interpretation apply to the interpretation of arbitration clauses. Intel Corp. v. Advanced Mi *1219 cro Devices, 12 F.3d 908, 914 (9th Cir.1993). One such well-established principle mandates that unambiguous contracts be enforced according to their terms. See Botefur v. City of Eagle Point, Oregon, 7 F.3d 152 (9th Cir.1993).

Here, the parties clearly agreed to two different arbitration provisions and Petitioners concede that the latter Construction Contract does not supersede the Design Agreement. Petitioners do not challenge the validity of the underlying arbitration clauses in general or the reasonableness of the specific venue provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Antonio v. Thornell
D. Arizona, 2025
John v. United States
D. Arizona, 2023
Gwen v. Mascher
D. Arizona, 2022
Sevelis v. Unknown Party
D. Arizona, 2022
Schaffer v. Shinn
D. Arizona, 2021
Gwen v. Shinn
D. Arizona, 2021
Adkins v. Hetmer
D. Arizona, 2021
Turner Const. v. Central Fl. Equip. Rental
904 So. 2d 474 (District Court of Appeal of Florida, 2005)
Parker v. McCaw
24 Cal. Rptr. 3d 55 (California Court of Appeal, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
26 F. Supp. 2d 1217, 1998 U.S. Dist. LEXIS 17993, 1998 WL 790701, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hyundai-america-inc-v-meissner-wurst-gmbh-co-cand-1998.