Hydrothermal Energy Corp. v. United States

38 Cont. Cas. Fed. 76,423, 26 Cl. Ct. 1091, 1992 U.S. Claims LEXIS 480, 1992 WL 312153
United States Court of Claims·Decided August 17, 1992·No. No. 116-87C·Published·Cited by 1 cases

Opinion

ORDER

ANDEWELT, Judge.

In this government contract action, plaintiff, Hydrothermal Energy Corp. (HEC), entered a contract with the United States Department of Energy (DOE) to develop a geothermal heating system in Reno, Nevada. DOE subsequently terminated the contract for the convenience of the government. In an April 17, 1992, opinion, this court denied plaintiff’s claim for $1,300,000 relating to its alleged title to the wells and related licenses and permits, and concluded that the contract’s Limitation of Funds clause created a $935,300 ceiling on the total due plaintiff under the contract. Hydrothermal Energy Corf. v. United States, 26 Cl.Ct. 7 (1992) {HEC L). Plaintiff has received $924,693 in payments under the contract and now seeks an additional payment of all reimbursable or “allowable” costs under the contract, including costs related to defendant’s termination for convenience.1 Defendant contends that it [1095] has overpaid plaintiff and has filed a counterclaim for a refund of most of the $924,-693 it has already paid. The sole issue remaining before the court is the total amount of plaintiffs allowable costs under the contract. For the reasons set forth below, the court concludes that plaintiff’s total allowable costs are less than the payments plaintiff has already received. Accordingly, plaintiff’s complaint shall be dismissed and defendant’s counterclaim is granted in part.

A.

The facts and claims in this contract action are set forth in detail in HEC I and will not be repeated here. The court notes that its task of determining the total amount of allowable costs has been greatly complicated by the litigation strategies adopted by the parties. At trial, each party presented a witness who had examined plaintiff’s records, and each party asked the court to rely heavily upon its witness’ conclusions. Defendant’s witness was an experienced government CPA auditor who detailed alleged serious problems that he confronted when auditing plaintiff’s records. The auditor repeatedly asked plaintiff for additional information to support plaintiff’s claims. When the additional information supplied was found adequate, the auditor made appropriate adjustments in plaintiff’s favor but, ultimately, concluded that the information submitted was inadequate to support large amounts of plaintiff’s monetary claims.2 In turn, plaintiff relied upon an expert in government contract accounting (not a CPA) who testified that plaintiff’s records were typical for a small business with government contracts and, therefore, under generally accepted accounting principles, should have been deemed sufficient to support all of plaintiff’s claims.

But, while each party asked the court to rely heavily upon the conclusions of its witness, neither party provided the court with a complete set of materials on which its witness had based his conclusions. For example, the government auditor had reviewed plaintiff’s check registers and other documentation in evaluating the claims but these materials were not presented into evidence in their entirety. In addition, neither party permitted the court to assess allowable costs by studying the work actually performed under the contract since neither party presented detailed evidence supporting the reasonableness, or unreasonableness, of the cost of such work. In this setting, the court is not in a position to review for itself the entire basis of certain of the respective witnesses’ conclusions as to allowable costs.

As explained below, this seemingly high-risk strategy utilized by the parties has prevented this court from immersing itself into the facts of the case and coming to its own determination as to allowability of certain costs. See, e.g., WRB Corp. v. United States, 183 Ct.Cl. 409, 426 (1968). It has also prevented the court in certain areas from relying with full confidence on the testimony of either plaintiff’s expert or defendant’s CPA auditor. Apparently because of this incompleteness of the record, each party seeks to prevail based on broad principles. But, ultimately, neither party is successful.

B.

Defendant relies upon Roberts v. United States, 174 Ct.Cl. 940, 949, 357 F.2d 938, 944-45 (1966), and Malissa Co. v. United States, 18 Cl.Ct. 672, 674-75 (1989), two cases in which a government contractor’s claims were denied because the contractor had failed to present sufficient evidence. In Roberts, the court stressed that the “appearance [of a cost claim] on plaintiff’s damage schedule does not by itself amount to probative evidence in the absence of anything else.” 174 Ct.Cl. at 949, 357 F.2d at 944. In Malissa, the court concluded that plaintiff’s “confusing” presentation of evidence and “hodge-podge” of [1096] witnesses made it impossible to find a reasonable basis for an award to plaintiff. 18 Cl.Ct. at 675. Herein, defendant asserts that plaintiffs entire claim must be rejected, and defendant’s counterclaim granted, because plaintiff’s evidence is as deficient as the evidence presented in Roberts and Malissa.

But, while the evidence plaintiff presented at trial is clearly insufficient to support some claims, it is adequate to support other claims. Plaintiff did not rely merely upon the listing of the costs in its damage claim. Plaintiff provided copies of documents that it had submitted to the government auditor in response to the auditor’s requests for supplemental information, and plaintiff presented testimony not only from its expert in government contract accounting, as noted above, but also from fact witnesses, including plaintiff’s president, Dr. David J. Atkinson, who took charge of the contract for plaintiff, and Mr. Kenneth R. Zahora, DOE’s representative who monitored plaintiff’s contract performance. In addition, unlike the witnesses in Malissa, plaintiff’s witnesses were able to explain adequately the meaning of certain documents upon which plaintiff relied.3

Plaintiff seeks to prevail on the broad premise that its expert in government contract accounting testified that plaintiff’s records were typical of a small business and thus should have been accepted as supportive of all of plaintiff’s claims. But this testimony was contradicted by the government auditor, who testified to the effect that plaintiff’s documentary support for its claims was clearly deficient when compared to typical small business government contractors,4 and was so terribly deficient in some areas that even a reasonable person could not come up with a reasonable estimate of allowable costs.5 Because plaintiff’s expert testimony was disputed by the government auditor, the court will not allow any of plaintiff’s claims based exclusively on its expert’s conclusion that plaintiff's record keeping was adequate.

Free access — add to your briefcase to read the full text and ask questions with AI

Hydrothermal Energy Corp. v. United States, 38 Cont. Cas. Fed. 76,423, 26 Cl. Ct. 1091, 1992 U.S. Claims LEXIS 480, 1992 WL 312153 (cc 1992).

38 Cont. Cas. Fed. 76,423 (Hydrothermal Energy Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Abadie v. Organization for Environmental Growth, Inc.
806 A.2d 1225 (District of Columbia Court of Appeals, 2002)