Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1

CourtCalifornia Court of Appeal
DecidedJanuary 27, 2015
DocketD063673
StatusUnpublished

This text of Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1 (Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1, (Cal. Ct. App. 2015).

Opinion

Filed 1/27/15 Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

THE HYDRO COMPANY, INC., D063673

Plaintiff and Appellant,

v. (Super. Ct. No. 37-2012-00057077-CU-BC-NC) ELSINORE VALLEY MUNICIPAL WATER DISTRICT,

Defendant and Respondent.

APPEAL from an order of the Superior Court of San Diego County, Timothy M.

Casserly, Judge. Reversed with directions.

Yale & Baumgarten and David W. Baumgarten for Plaintiff and Appellant.

Best Best & Krieger, James B. Gilpin, and Holly E. Cheong for Defendant and

Respondent.

Plaintiff The Hydro Company, Inc., doing business as The Nevada Hydro

Company, Inc. (Nevada Hydro), appeals an order granting the special motion to strike

filed by defendant Elsinore Valley Municipal Water District (the District) under Code of Civil Procedure section 425.16, commonly known as the "anti-SLAPP" statute.1 Nevada

Hydro contends that the court erred in (1) determining that Nevada Hydro's complaint for

breach of contract arose from an act in furtherance of the District's right of petition or free

speech (§ 425.16, subd. (b)(1)); (2) finding that the commercial speech exception to the

anti-SLAPP statute did not apply (§ 425.17, subd. (c)); and (3) concluding that Nevada

Hydro had not established a probability that it would prevail on its claim for breach of

contract (§ 425.16, subd. (b)(1)).

We conclude that Nevada Hydro has established a probability that it will prevail

on its claim. Therefore, even assuming that the trial court did not otherwise err, the

District's anti-SLAPP motion should not have been granted. The order is reversed with

directions to deny the motion.

FACTUAL AND PROCEDURAL BACKGROUND

In 1995, the District obtained a preliminary permit from the Federal Energy

Regulatory Commission (FERC) for the planned Lake Elsinore Pumped Storage project,

later known as the Lake Elsinore Advanced Pumped Storage project (LEAPS). The

project involved construction of the following elements: a reservoir adjacent to Lake

Elsinore, California, at a higher elevation than the lake; a pumping system to deliver

water from Lake Elsinore to the new reservoir; and a series of turbines to generate

electricity when water from the reservoir is released back to the lake. The project would

1 " 'SLAPP' is an acronym for 'strategic lawsuit against public participation.' " (Soukup v. Law Offices of Herbert Hafif (2006) 39 Cal.4th 260, 268, fn. 1 (Soukup).) All further statutory references are to the Code of Civil Procedure unless otherwise stated. 2 pump water into the new reservoir using electricity during periods of low electrical

demand. During periods of high electrical demand, the project would release the pumped

water into the lake, thereby generating electricity that would be sold to a local utility.

In order to transfer the necessary electricity, the LEAPS project included plans for

an electrical transmission line connecting the LEAPS project to the wider power grid.

The nature and configuration of this transmission line would later prove to be

controversial.

The District and Nevada Hydro entered into a Development Agreement for the

LEAPS project. The Development Agreement broadly granted Nevada Hydro the

exclusive right to develop, finance, construct, and operate the project. In exchange,

Nevada Hydro agreed, among other things, to bear the costs of developing, constructing,

and operating the project; to reimburse the District for its expenditures related to the

project; to pay a one-time fee to the District; and to pay the District for water

management services at Lake Elsinore related to the project.2

The Development Agreement authorized Nevada Hydro to obtain all necessary

licenses and permits for the LEAPS project, including a FERC license. It also obligated

Nevada Hydro to use its "best and reasonable judgment" to obtain a FERC license and

construct and operate the project. The Development Agreement required the District to

"make every reasonable effort necessary or appropriate to effectuate" Nevada Hydro's

2 Part of the District's interest in the LEAPS project appears to be related to the District's belief that the LEAPS project would ensure a baseline level of water in Lake Elsinore and improve water quality. 3 development rights and to "use its reasonable best efforts to obtain all

permits . . . necessary in the reasonable opinion of [Nevada Hydro], desirable for the

purpose of . . . enabling [Nevada Hydro] to proceed with development of the Project."

The Development Agreement also obligated each party, at the request of the other, to

"execute such additional instruments and take such additional acts as are reasonably

necessary to effectuate this Agreement."

Nevada Hydro and the District obtained a second preliminary permit from FERC.

The second preliminary permit appeared to contemplate that the LEAPS project would be

larger than initially planned. The permit application filed by Nevada Hydro and the

District identified two transmission lines for the project: a southerly line connecting to

San Diego Gas & Electric's Talega-Escondido transmission line and a northerly line

connecting to Southern California Edison's Valley-Serrano transmission line. Together,

the transmission lines for the LEAPS project were called the TE/VS transmission line or

the TE/VS interconnect.

While the application for the second preliminary permit was pending, the

California Independent System Operator identified a need for additional transmission

capability, unrelated to the LEAPS project, in the area where the TE/VS interconnect

would be constructed. The TE/VS interconnect could satisfy this need by transmitting

electricity between the two existing lines maintained by San Diego Gas & Electric and

Southern California Edison. The District initiated a separate environmental review

process for the development of a project covering only the TE/VS interconnect.

4 After obtaining the second preliminary permit, Nevada Hydro and the District

applied for a FERC license for the LEAPS project. FERC prepared a Final

Environmental Impact Statement (EIS) for the project. The Final EIS noted that the

license application included a proposal to build the TE/VS interconnect. In an appendix

to the Final EIS, FERC concluded that the TE/VS interconnect "would be an appropriate

long-term solution to southern California's transmission congestion bottlenecks as well as

the transmission-constrained, generation-deficient San Diego area." FERC noted that in

such a scenario, the TE/VS interconnect would fall outside any FERC license because

FERC generally licenses only primary transmission lines, i.e., transmission lines that

carry electricity solely to or from a FERC-licensed project. Because the TE/VS

interconnect would carry additional electricity, unrelated to the LEAPS project, FERC

could not license it. Instead, the TE/VS interconnect would be within the jurisdiction of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oasis West Realty v. Goldman
250 P.3d 1115 (California Supreme Court, 2011)
Insurance Underwriters Clearing House, Inc. v. Natomas Co.
184 Cal. App. 3d 1520 (California Court of Appeal, 1986)
Haley v. Casa Del Rey Homeowners Ass'n
63 Cal. Rptr. 3d 514 (California Court of Appeal, 2007)
Wall Street Network, Ltd. v. New York Times Co.
164 Cal. App. 4th 1171 (California Court of Appeal, 2008)
Anschutz Entertainment Group, Inc. v. Snepp
171 Cal. App. 4th 598 (California Court of Appeal, 2009)
Morrow v. Los Angeles Unified School District
57 Cal. Rptr. 3d 885 (California Court of Appeal, 2007)
Roberts v. Los Angeles County Bar Assn.
129 Cal. Rptr. 2d 546 (California Court of Appeal, 2003)
Daimlerchrysler Motors Co. v. Lew Williams, Inc.
48 Cal. Rptr. 3d 233 (California Court of Appeal, 2006)
Integrated Healthcare Holdings, Inc. v. Fitzgibbons
44 Cal. Rptr. 3d 517 (California Court of Appeal, 2006)
Navellier v. Sletten
52 P.3d 703 (California Supreme Court, 2002)
Equilon Enterprises v. Consumer Cause, Inc.
52 P.3d 685 (California Supreme Court, 2002)
Wilson v. Parker, Covert & Chidester
50 P.3d 733 (California Supreme Court, 2002)
Soukup v. Law Offices of Herbert Hafif
139 P.3d 30 (California Supreme Court, 2006)
Brown v. Grimes
192 Cal. App. 4th 265 (California Court of Appeal, 2011)
Palp, Inc. v. Williamsburg National Insurance
200 Cal. App. 4th 282 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Hydro Co. v. Elsinore Valley Mun. Water Dist. CA4/1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hydro-co-v-elsinore-valley-mun-water-dist-ca41-calctapp-2015.