Hydeville Co. v. Eagle Railroad & Slate Co.

44 Vt. 395
Supreme Court of Vermont·Decided February 15, 1872·Published·Cited by 5 cases

Opinion

The opinion of the court was delivered by

Ross, J.

I. The plaintiff claims that the lease of October 1, 1866, took effect and carried rent from its date, and that the only [401] effect of tbe subsequent agreement of March 20, 1867, was to discount $50 from the rent reserved in the lease. Such construction would render the last part of that agreement entirely nugatory. That clause which provides that two hundred dollars shall be paid the plaintiff “instead of the provisions of said lease,” might as well have been unwritten. If this is not the construction to be given to the last part of the agreement, the plaintiff claims that it should bo construed as a substitution of two hundred dollars for the rent named in the lease, and that the rent should commence from October 1, 1866. This construction would render the first part of that agreement repugnant and inharmonious. With this construction the discount from the lease would be $79.16, instead of $50, as stipulated in the first part of the agreement. It is the duty of the court, if possible, to construe the agreement so as to give effect to every part, and form, from the parts, a harmonious whole. If the circumstances under which the agreement was entered into be considered, there will be no difficulty in finding such a construction. By the original lease, the plaintiff was to put the tenements in repair within one week from its date. This was a condition precedent to the defendant’s obligation to take possession and pay rent. The plaintiff made an attempt to make the repair’s, but did not fully perform the condition precedent. The defendant, for that reason, refused to take possession, or to pay rent. Thus matters remained, till the agreement of March 20th was entered into. No obligation rested upon the defendant to pay rent for the time which had elapsed since the making of the-lease. The parties mutually understood that the lease would terminate April 1, 1868. This probably arose from a mistake in reckoning the time the lease was to run. Under these circumstances the plaintiff, in consideration the defendant would put the premises in good repair and surrender them in like good repair, agreed to discount fifty dollars from the lease, and the defendant agreed to pay $200, “ instead of the provisions of said lease.” At this time, as the parties mutually understood, the lease had only about one year to run. Construing the lease under the circumstances for the purposes of rent, as commencing at the time this subsequent agreement was made, and as continuing one year [402] from that time, or to April 1, 1867, (the ten additional days bo. ing used for repairs,) wo can give effect to every part of the agreement, and have all the parts harmonious. The discount is fifty dollars and no more, and the two hundred dollars which the defendant is to pay “ instead of the provisions of the lease” is just the yearly rent reserved in the lease diminished by a discount of fifty dollars. This is the construction which we think should be placed upon the agreement of March 20, 1867. Under this construction the plaintiff is not entitled to recover for the $125 additional rent under the lease allowed by the county court." Neither can he recover for the month from April 1 to May 1, 1870, during which the defendant did not occupy the premises. The parties had, by mutual mistake in regard to the duration of the written lease, terminated it April 1, 1868, and the holding over, provided for, commenced from that date. This is evident from the bill for rent, presented by the plaintiff for the quarter ending March 31, 1870, as well as from the facts found by the court.

Free access — add to your briefcase to read the full text and ask questions with AI

Hydeville Co. v. Eagle Railroad & Slate Co., 44 Vt. 395 (Vt. 1872).

44 Vt. 395 (Hydeville Co. v. Eagle Railroad & Slate Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Appeals of Shantee Point, Inc.
811 A.2d 1243 (Supreme Court of Vermont, 2002)
Erwin v. United Benefit Life Insurance Company
371 P.2d 791 (New Mexico Supreme Court, 1962)
Vermont Shade Roller Co. v. Burlington Traction Co.
150 A. 138 (Supreme Court of Vermont, 1930)
Crosby v. Vermont Accident Insurance
80 A. 817 (Supreme Court of Vermont, 1911)
Kidd v. New Hampshire Traction Co.
66 A. 127 (Supreme Court of New Hampshire, 1907)