Hyatt Cheek Builders-Engineers Co. v. Board of Regents

607 S.W.2d 258, 1980 Tex. App. LEXIS 3774
CourtCourt of Appeals of Texas
DecidedJuly 29, 1980
Docket8738
StatusPublished
Cited by24 cases

This text of 607 S.W.2d 258 (Hyatt Cheek Builders-Engineers Co. v. Board of Regents) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hyatt Cheek Builders-Engineers Co. v. Board of Regents, 607 S.W.2d 258, 1980 Tex. App. LEXIS 3774 (Tex. Ct. App. 1980).

Opinions

CORNELIUS, Chief Justice.

This suit arose out of a contract for the construction of the Callier Center for Speech and Hearing in Dallas, Texas, an independent organization when the contract was signed, but which later became a part of the University of Texas at Dallas. The appellant, Hyatt Cheek Builders-Engineers Company, was the general contractor for the project and it engaged Appellee Burden Brothers, Inc. as subcontractor to do the plumbing and other mechanical work. After the building was completed, one of the water mains leading to the building ruptured, causing extensive flooding and damage to the building and its contents. The University sued both Hyatt Cheek and Burden Brothers, alleging negligence and breach of contract. Trial was to a jury which found that both Burden Brothers and Hyatt Cheek were negligent in installing the .pipe, and that such negligence was a proximate cause of the damages. The jury also found that Burden Brothers and Hyatt Cheek failed to perform their work in a good and workmanlike manner as required by the contract, and that such failure was a proximate cause of the damage. Based on the jury’s findings of damages,1 the trial court rendered judgment for the University for $268,925.00 together with pre-judgment interest, for a total award of $337,600.31. Hyatt Cheek appeals, assigning 62 points of error. Burden Brothers assigns 37 cross-points.

Hyatt Cheek’s first 32 points attack the sufficiency of the evidence to support the findings of negligence and proximate cause under Special Issues 3 and 4. In answer to those issues the jury found that Hyatt Cheek was negligent in failing to require Burden Brothers to perform the work properly. The general contract obligates Hyatt Cheek to supervise and assume responsibility for the work of all subcontractors and their employees. The points of error assert that because of a three -way contract which Burden Brothers executed with Callier and the City of Dallas, Hyatt Cheek was relieved of its duty to supervise. The argument is based on three theories: (1) that the three-way contract constituted a novation; (2) that the three-way contract made [262]*262Hyatt Cheek’s supervision under the general contract impossible; and, (3) that the three-way contract is inconsistent with the general contract and therefore supersedes it. In addition, Hyatt Cheek contends that if it is liable to the University, the court should have granted it indemnity against its subcontractor, Burden Brothers.

The general contract is a standard form agreement dated August 25, 1966, between the owner, Callier Hearing and Speech Center, and the contractor, Hyatt Cheek. The contract grants Hyatt Cheek authority to award subcontracts for any part of the construction work, but it provides in Article 36 that:

“The Contractor agrees that he is as fully responsible to the Owner for the acts and omissions of his subcontractors and of persons either directly or indirectly employed by them, as he is for the acts and omissions of persons directly employed by him.
“Nothing contained in the Contract Documents shall create any contractual relation between any subcontractor and the Owner.”

Article 37(a) of the general contract provides that:

“The Subcontractor agrees-
“(a) To be bound to the Contractor by the terms of the Agreement, General Conditions of the Contract, the Supplementary General Conditions, the Drawings and Specifications, and to assume toward him all the obligations and responsibilities that he, by those documents, assumes toward the Owner.”

The general contract also contemplates the three-way contract with the City of Dallas. One clause of the general contract provides:

“The water and sanitary sewer consists of mains as shown on sheets A-3 and A-4. The water and sanitary sewer shall be constructed by a contractor approved by the architect/engineer. The contractor shall enter into a three-way contract between the Callier Hearing and Speech Center, the City of Dallas and himself for the construction of the system in accordance with the standards of the City of Dallas Water Department.” (Emphasis added.)

After execution of the general contract with Callier, Hyatt Cheek subcontracted with Burden Brothers, Inc. for it “... To furnish all labor, materials and equipment necessary to complete the plumbing, heating, ventilating, air conditioning, water lines, storm sewer & sanitary sewer work as set forth in the plans, specifications, addendum nos. 1, 2, 3 & 4 and Exhibit ‘A’, entitled ‘CALLIER HEARING & SPEECH CENTER, DALLAS, TEXAS’ ...” The subcontract also provided that all of the general contract conditions, plans and specifications for the job were incorporated into and became a part of the subcontract. After execution of the subcontract, Callier and Burden Brothers entered into the three-way contract referred to in the general contract and as required by the Dallas City Code. That contract was required because some of the lines crossed Dallas city property. The three-way contract requires the City of Dallas to inspect the work to insure that the installation is “... in conformity with the layout, plans and specifications approved by the City for the area, ... ”.

The break which caused the damage to Callier’s property occurred in that portion of the work performed by Burden Brothers. It is undisputed that Hyatt Cheek did not supervise Burden’s work in that area, but Hyatt Cheek contends that it was prevented from doing so, or was relieved from the responsibility for doing so, by the execution of the three-way contract which calls for supervision by the City. We cannot agree. Since the jury found Hyatt Cheek failed to properly supervise the work, and no jury issue was submitted on whether it was relieved from that responsibility, Hyatt Cheek can sustain its contentions here only if the execution of the three-way agreement relieved it of the duty of supervision as a matter of law. We do not believe a reasonable construction of the pertinent contracts can lead to such a conclusion. Although the three-way contract provided for supervision by the City, there is no provision in it which expresses or even [263]*263implies that Hyatt Cheek is thereby relieved of its responsibility to supervise. The fact that another is subsequently obligated to supervise work does not necessarily relieve one who has previously contracted to supervise it, unless the subsequently assumed obligation to supervise is incompatible with the former. That is not the case here. Hyatt Cheek, as general contractor, was obligated to supervise the work to insure that it was performed in a good and workmanlike manner; whereas the City’s duty of supervision was primarily concerned with the observance of city ordinances and building codes. While those duties may be duplicative in some respects, they certainly are not incompatible to the extent that they cannot co-exist. Nor did the three-way contract amount to a novation or supersede the general contract and its obligations. A novation requires a new agreement between the same parties that is intended to replace the original obligation. 41 Tex. Jur.2d Novation § 1, p. 546; § 6, p. 551; § 7, p. 554, and cases there cited. The three-way contract did not supersede the general contract as a matter of law, because the two contracts are not inconsistent; indeed, the general contract contemplated and required the execution of the three-way contract. See Chastain v. Cooper & Reed, 152 Tex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jason Jenkins v. Occidental Chemical Corporation
415 S.W.3d 14 (Court of Appeals of Texas, 2013)
American Garment Properties, Inc. v. CB Richard Ellis-El Paso, L.L.C.
155 S.W.3d 431 (Court of Appeals of Texas, 2004)
Friday v. Spears
975 S.W.2d 699 (Court of Appeals of Texas, 1998)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
Hill v. Winn Dixie Texas, Inc.
824 S.W.2d 311 (Court of Appeals of Texas, 1992)
Lone Star Steel Co. v. Scott
759 S.W.2d 144 (Court of Appeals of Texas, 1988)
McDonald v. Brennan
704 S.W.2d 134 (Court of Appeals of Texas, 1986)
Group Hospital Services, Inc. v. One & Two Brookriver Center
704 S.W.2d 886 (Court of Appeals of Texas, 1986)
Channel 20, Inc. v. World Wide Towers Services, Inc.
607 F. Supp. 551 (S.D. Texas, 1985)
Opinion No.
Texas Attorney General Reports, 1984
South Hampton Co. v. Stinnes Corp.
733 F.2d 1108 (Fifth Circuit, 1984)
State v. Weller
666 S.W.2d 362 (Court of Appeals of Texas, 1984)
Mar-Lan Industries, Inc. v. Nelson
635 S.W.2d 853 (Court of Appeals of Texas, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
607 S.W.2d 258, 1980 Tex. App. LEXIS 3774, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hyatt-cheek-builders-engineers-co-v-board-of-regents-texapp-1980.