Huse v. United States

222 U.S. 496, 32 S. Ct. 119, 56 L. Ed. 285, 1912 U.S. LEXIS 2202
Supreme Court of the United States·Decided January 9, 1912·No. 74·Published·Cited by 6 cases

Opinion

Me. Justice Lueton

delivered the opinion of the court.

The appellant had a four-year contract, commencing *500 July 1, 1902, for screen-wagon mail service between the post-office and railway mail stations at Omaha, Nebraska. On May 20, 1903, the Postmaster General cancelled the contract and relet it to other partiés. Thereupon appellant brought this suit in the Court of Claims, asserting that he had faithfully performed his agreement, but that he had been required to carry mails to and from three railway companies not included in his contract. That his equipment was ample for the service he contracted to render, but that he had been ordered to provide equipment adequate to the excessive service demanded, and that , the cancellation of his contract was therefore unauthorized. His suit was to recover, first, the balance due under the contract as construed by the Department; second, the reasonable value of the excess service he had, under protest, been compelled to render; third, the loss of profit resulting from the-wrongful annulment of his contract; and, finally, the loss sustained in disposing of equipment which had been bought for the purpose of carrying out his contract.

As is the case with mail contracts, the manner and means of performance were carefully prescribed and power ,was reserved to the Postmaster General to require other and further facilities if it should be found necessary for the good of the service. The power of the Postmaster General to supervise and the duty of the contractor to conform to Iris regulations were plainly written down. That vigilant and prompt service might be enforced, he was given the light to make deductions, by way of fines, from compensation earned, for defects in equipment or negligence in the performance of the service. For repeated failures in performance or acts of neglect, or disobedience to orders, he was given power to annul the contract without impairing -the right of the Government to recover damages for non-performance. .

The findings of the court below as to the repeated *501 failures of the appellant in the performance of his contract, the inadequacy of his equipment, and his disobedience to the requirements that he should enlarge and-improve his facilities, make it clear thát the Postmaster General did not act arbitrarily, nor exceed the power reserved, by the infliction of fines or the final cancellation of the agreement on May 20,1903. When the contract was cancelled it was directed that compensation due should be withheld and the contract relet at the contractor’s expense. This re-letting was at a price of some $14,000 in excess of whát the cost would have been if appellant had performed his agreement. The court below found that when the contract was annulled there was due appellant $2,984.72. For this a judgment was asked, but denied, the court below finding that the loss to the Government as a result of reletting the contract was greatly in excess of the amount due to appellant. His petition was therefore dismissed.

If the contract, fairly construed, exacted the amount of service which the Department claimed, the case of appellant must fail, in view of the facts found as to his insufficient performance, and the loss resulting to the Government from the necessity of reletting the unfinished term of the agreement.

The Postmaster General construed the contract as requiring appellant to receive from and deliver to all railroads using the Union Station at Omaha. This construction required him to receive from and deliver to three railroad companies, not specified in the contract, namely, the Wabash, the Chicago and Northwestern and the Chicago, Milwaukee and St. Paul. The case must, therefore, turn upon the question as to whether the service contemplated by his contract included mails to and from the railways mentioned.

Coming, then, to the service required by the contract. The proposal for the Omaha mail-wagon service and its acceptance were according to a printed official form. This *502 proposal and acceptance, making the contract proper, refer to and make the public advertisement of the Postmaster General for proposals a part of the agreement,* and from it the service contemplated is discovered. That advertisement included certain “instructions to bidders,” of which they were required to take notice. Among other things, these “instructions” included the following provision: .

“The foregoing schedules show approximately the service as performed during the week named in the statement of service for each route. Bidders, however, must personally inform themselves of the amount and character of the service that will be required during the contract term, beginning with July 1, 1902. Bidders and their sureties are warned that they should familiarize themselves with the terms of the contract, schedules of service, and instructions contained herein before they shall assume any liabilities as such bidders or . sureties, to prevent misapprehension or cause of. complaint thereafter.”

Under the heading “Union Station,” in the schedule referred to, there appear'the names of four railroad companies opposite the words “Union Station,” applicable to each of the named companies, thus: “Union Station; Illinois Central R. R. Co. (143077); Union Pacific R. R. Co. (157001); Chicago, Rock Island and Pacific Rwy. Co. (157064); Missouri Pacific Rwy. Co. (157075).”

It will be noticed that the named railroads bringing mail into the Union Station do not include the Wabash, the Chicago and Northwestern, or the Chicago, Milwaukee and St. Paul. Notwithstanding this omission, appellant was required to carry to and from the Union Station the mails delivered there by these three companies and to be delivered there from the post office to be carried by the same companies. This appellant did under protest; and upon this his suit is grounded.

But the éxplanátion and answer is simple:.Originally, *503 the contract routes of these companies terminated at the Union Pacific transfer at Council Bluffs, Iowa, where the mail was transferred to the Union Pacific Railway and carried into Omaha. After the construction of the Union Station, each of these companies procured the right to carry their mail over the Union Pacific Railway into the Union Station. This saved delay in. transfer. The court below found that “the trains so performing said service were known and treated by the Post-Office Department as mail trains of the Union Pacific Railroad Company, route No. 157,001, and were operated under the rules of said Union Pacific Railroad Company, and payment was made therefor to the said Union Pacific Company. All weights of mail carried by said three roads were credited to the Union Pacific Railroad route and weighed thereon. The screen-wagon contractor under the preceding advertisement and contract, which were similar to the one in this case, carried mails to and from 'the trains of said three roads as part of his contract, and these facts were, known to persons having knowledge of the service.”

Free access — add to your briefcase to read the full text and ask questions with AI

Huse v. United States, 222 U.S. 496, 32 S. Ct. 119, 56 L. Ed. 285, 1912 U.S. LEXIS 2202 (1912).

222 U.S. 496 (Huse v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ex Parte Keizo Kamiyama
44 F.2d 503 (Ninth Circuit, 1930)
Kamiyama v. Carr
44 F.2d 503 (Ninth Circuit, 1930)
Elbukan Oil Co. v. Lamb
12 F.2d 387 (Eighth Circuit, 1926)
Cygnet Manufacturing Co. v. United States
60 Ct. Cl. 840 (Court of Claims, 1925)
Skinner & Eddy Corp. v. United States
58 Ct. Cl. 663 (Court of Claims, 1923)
Martin v. Imbrie
262 F. 44 (Second Circuit, 1919)