Huron Valley Outfitters LLC v. Charter Township of Lyon

CourtMichigan Court of Appeals
DecidedJanuary 18, 2024
Docket361871
StatusUnpublished

This text of Huron Valley Outfitters LLC v. Charter Township of Lyon (Huron Valley Outfitters LLC v. Charter Township of Lyon) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huron Valley Outfitters LLC v. Charter Township of Lyon, (Mich. Ct. App. 2024).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

HURON VALLEY OUTFITTERS, LLC, UNPUBLISHED January 18, 2024 Plaintiff-Appellant,

v No. 361871 Oakland Circuit Court CHARTER TOWNSHIP OF LYON, LC No. 2020-179677-CK

Defendant-Appellee.

Before: GLEICHER, P.J., and BORRELLO and SHAPIRO, JJ.

PER CURIAM.

In this appeal by right, plaintiff Huron Valley Outfitters, LLC, challenges the trial court’s grant of summary disposition in favor of defendant Charter Township of Lyon (the Township) on plaintiff’s breach-of-contract claim. For the reasons set forth in this opinion, we affirm.

I. BACKGROUND

In 2016, plaintiff purchased vacant land from the Township. The Purchase Agreement contained the following clause:

2.2 Seller shall reserve unto itself, a non-exclusive and assignable Easement for the construction of a Ring Road which shall traverse the Property in a roughly easterly/westerly direction and which Ring Road shall ultimately connect to Milford Road and Grand River Avenue, as generally depicted on attached “Exhibit C” (the “Ring Road”). The Ring Road, when constructed, shall be entirely located within the area reserved by Seller as illustrated in Exhibit C. The easement shall reserve unto Seller a 120’ wide easement area for the construction of the planned Ring Road, which, when constructed, shall be a dedicated public roadway, along with the installation and maintenance of any and all utilities which Seller shall desire to place or cause to be placed within the easement, and such other ancillary items as may be reasonably related to the development and construction of the Ring Road, including the construction of same. Upon the establishment of the final specific location of the roadway and utilities, such easement shall be reduced to the actual size required to accommodate the required road right-of-way,

-1- and the easement over the residual area shall be terminated and released so as to provide for Ring Road frontage and unencumbered Ring Road access along the entire length of the Property. Notwithstanding anything to the contrary contained in this Agreement, Purchaser shall not be responsible for the performance of work or the payment of any costs associated with the reservation of the Ring Road Easement or the construction and installation of the Ring Road or any utilities or such ancillary items as may be placed within the Ring Road Easement area or which may be reasonably related to the development and construction of the Ring Road.

The parties also executed an agreement titled “Roadway Easement Agreement.” This agreement, in which plaintiff was designated “Grantor” and the Township was designated “Grantee,” provided in relevant part as follows:

1. Grant of Easement. For the sum of One Dollar ($1.00), Grantor, as the owner of certain land located in the Township of Lyon, County of Oakland, State of Michigan, and more particularly described on the attached Exhibit A, incorporated herein by reference (the “Property”) does hereby grant to Grantee a non-exclusive, perpetual, assignable easement for public roadway purposes (the “Roadway Easement”) and to construct, operate, maintain, repair, and/or replace roadways, utilities (either overhead or underground), and other infrastructure improvements in, over, under, upon, and through the following described portion of the Property:

SEE LEGAL DESCRIPTION OF 120 FOOT WIDE RIGHT OF WAY AND SURVEY DRAWING ATTACHED AS EXHIBIT B AND INCORPORATED HEREIN BY REFERENCE (the “Roadway Easement Area”).

2. Construction. Grantee and/or its assigns shall have the right to design, construct, improve, repair, and maintain a road (the “Roadway”) and/or public and franchise utilities and such other improvements that Grantee, in its sole discretion deems necessary to provide continuous, adequate, convenient, and reasonable means of ingress and egress access through the Roadway Easement Area to, from, and throughout the Property, and the neighboring properties (collectively, the “Roadway Improvements”). Any such Roadway Improvements contemplated herein shall be at no cost to Grantor, except that any improvements required to provide Grantor with access to the Roadway Easement Area, when so improved, shall be the responsibility of Grantor.

In 2020, after the Township had not initiated construction of the Ring Road over plaintiff’s property, plaintiff filed the present action alleging, as relevant to the instant appeal, that the Township had breached the parties’ agreement by not constructing the road. Plaintiff contended that the Township was contractually required to build the Ring Road.

On June 3, 2020, the trial court denied plaintiff’s motion for summary disposition under MCR 2.116(C)(9) on the contract claim and allowed the parties to engage in discovery. On September 14, 2020, the trial court denied the Township’s motion for summary disposition under MCR 2.116(C)(10) on the contract claim, concluding that § 2.2 of the Purchase Agreement was

-2- “unambiguous as to the party’s intent to reserve the easement, its purpose, and its location,” but that the language was ambiguous “as to its construction (e.g., who and when).” The judge originally assigned to this case retired and was replaced by a successor judge. On September 1, 2021, the trial court granted summary disposition in favor of the Township under MCR 2.116(C)(10) on the contract claim, reasoning that “this Court cannot find that defendant [Township] breached the terms of the Purchase Agreement or the Roadway Easement Agreement because it did not expressly obligate defendant to construct Ring Road or that the construction had to be completed by a certain timeframe.” The court therefore dismissed the breach of contract claim.

The Township subsequently sought attorney fees and costs pursuant to § 14 of the Purchase Agreement. The trial court denied the Township’s motion in a June 8, 2022 order. This appeal followed. Further facts relevant to the resolution of the issues on appeal will be discussed as necessary below.

II. JURISDICTION

We first address the Township’s challenge to this Court’s appellate jurisdiction over “any issues adjudicated by the trial court on, or prior to, December 10, 2021, including the September 1, 2021 Opinion and Order.” The Township previously filed a motion in this Court to limit the scope of this appeal to issues related to the June 8, 2022 order and to dismiss as untimely the appeal of any issues related to the September 1, 2021 or December 10, 2021 orders. The Township argued that a December 10, 2021 order was a final order under MCR 7.202(6)(a)(i) because it was “the first judgment or order that dispose[d] of all the claims and adjudicate[d] the rights and liabilities of all the parties . . . .” Additionally, the Township further argued that the June 8, 2022 order was a subsequent, separate final order under MCR 7.202(6)(a)(iv) because it was a postjudgment order awarding or denying attorney fees. Plaintiff filed its appeal on June 21, 2022. Consequently, the Township argued that although plaintiff’s appeal was timely filed within 21 days of the June 8, 2022 order, see MCR 7.204(A)(1), plaintiff’s appeal was limited to the issues decided in the June 8, 2022 order regarding attorney fees and costs. See MCR 7.203(A)(1) (“An appeal from an order described in MCR 7.202(6)(a)(iii)-(v) is limited to the portion of the order with respect to which there is an appeal of right.”). The Township contended that plaintiff’s appeal of issues decided in the earlier orders were untimely and should be dismissed. See MCR 7.204(A) (“The time limit for an appeal of right is jurisdictional.”). This Court denied the Township’s motion.1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quality Products and Concepts Co. v. Nagel Precision, Inc.
666 N.W.2d 251 (Michigan Supreme Court, 2003)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Children's Hospital v. Auto Club Insurance
545 N.W.2d 592 (Michigan Supreme Court, 1996)
Meagher v. Wayne State University
565 N.W.2d 401 (Michigan Court of Appeals, 1997)
Fleet Business Credit, LLC v. Krapohl Ford Lincoln Mercury Co.
735 N.W.2d 644 (Michigan Court of Appeals, 2007)
Green v. Ziegelman
767 N.W.2d 660 (Michigan Court of Appeals, 2009)
Chen v. Wayne State University
771 N.W.2d 820 (Michigan Court of Appeals, 2009)
Village of Edmore v. Crystal Automation Systems Inc
911 N.W.2d 241 (Michigan Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Huron Valley Outfitters LLC v. Charter Township of Lyon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huron-valley-outfitters-llc-v-charter-township-of-lyon-michctapp-2024.