Huron Center v. Carlson and Durrant Group v. Zurbrigen Industries

2002 SD 103
CourtSouth Dakota Supreme Court
DecidedAugust 14, 2002
DocketNone
StatusPublished

This text of 2002 SD 103 (Huron Center v. Carlson and Durrant Group v. Zurbrigen Industries) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huron Center v. Carlson and Durrant Group v. Zurbrigen Industries, 2002 SD 103 (S.D. 2002).

Opinion

Unified Judicial System

Huron Center, Inc., d/b/a/ Crossroads

Hotel and Convention Center
Plaintiff and Appellant,

v.

Henry Carlson Co., Durrant

Group, Inc., and Durrant

Construction Mangement Inc.,
Defendant and Appellee,

and

Durrant Group, Inc., and Durrant

Construction Management,Inc.,
Defendant and Appellee,

Zurprigen Industries, Inc.
(formerly Concrete Products Company)
Third Party Defendant and Appellee.

South Dakota Supreme Court
Appeal from the Circuit Court of
The Third Judicial Circuit
Beadle County, South Dakota
Hon. Eugene L. Martin, Judge

Rodney Freeman, Jr.
Jeff Burns of
Churchill, Manolis, Freeman, Kludt & Shelton

Huron, South Dakota
Attorneys for plaintiff and appellant.

William G. Beck of

Woods, Fuller, Shultz and Smith

Sioux Falls, South Dakota

Attorneys for defendant and appellee Henry Carlson.

Gary J. Pashby of

Boyce, Murphy McDowell and Greenfield

Attorneys for defendant and appellee Durrant Group.

Michael L. Luce of
Davenport, Evans, Hurwitz and Smith
Sioux Falls, South Dakota

Attorneys for third party defendant and appellee Zubrigen.

Considered on Briefs May 28, 2002

Opinion Filed 8/14/2002

#22219
MILLER, Acting Justice.

[¶1.]                 Huron Center, Inc., d/b/a Crossroads Hotel and Convention Center (Huron Center) sued Henry Carlson Co. and Durrant Group, Inc., for breach of contract as a result of a claimed defective design and the substandard construction of a hotel in Huron, South Dakota.  Although the exact date is disputed, deterioration of the exterior panels began in the early 1990’s.  Huron Center, however, did not commence this action until April 1997.  After four years of discovery, the defendants moved for summary judgment on the grounds that the six-year statute of limitations period had expired.  The trial court granted the motion.  We reverse and remand.

FACTS AND PROCEDURE

[¶2.]                 In 1985, Huron Center contracted with Durrant, an architectural firm, and Carlson, a general contractor, to build a hotel in Huron.  Huron Center specified that the hotel would be built using pre-cast building panels manufactured by Concrete Products Company, n/k/a Zurbrigen Industries, Inc.  Construction of the hotel was completed on May 1, 1987.

[¶3.]                Prior to July 1990 (the exact date is unknown) Huron Center began having problems with Zurbrigen’s pre-cast concrete panels.  The panels gradually began to crack and discolor in various areas.  Huron Center paid contractor Travis Dryvit to fix the problems by scraping away the crumbling concrete and replacing it with a styrofoam base, which was then covered with a finishing coat.  In July 1990, when Steve Oetken replaced Richard Johnson as Huron Center’s general manager, he noticed the exterior wall problems.  In the spring of 1991,[1]  Oetkin contacted Dryvit to come make repairs.  Dryvit fixed the exterior wall deterioration that had developed since his last repair job.  While Dryvit has annually repaired the exterior panels since 1990, it was not until 1992 that he also began to inspect the interior walls.

[¶4.]                In 1995, Huron Center began experiencing problems with the interior walls.  Sheet rock on the walls of several rooms was deteriorating to the point that it would not hold the wall coverings.  The walls were also retaining a significant amount of moisture.  In the fall of 1995 or spring of 1996, Oetkin wrote a letter to Carlson and Durrant explaining the problems, requesting advice as to why

they were occurring, and asking who was responsible.  Carlson sent an engineer to review the problems and Durrant sent Randy Hoscheid to perform some tests on the exterior panels.  Hoscheid’s testing revealed that the exterior panel design and construction were defective.

[¶5.]                In April 1997, Huron Center sued Carlson and Durrant for breach of contract.  Durrant brought a third party complaint against Dakota Engineering and Testing Co. and Zurbrigen.  The trial court granted summary judgment in favor of Carlson, Durrant and Zurbrigen (collectively Defendants).  Huron Center moved to vacate the grant of summary judgment, which motion was denied.  Huron Center appeals, raising the following issue:

1.         Whether the time of accrual of Huron Center’s cause of action

raises a genuine issue of material fact.

In this appeal, Defendants raise the following issue:

2.         Whether Huron Center properly preserved the substantive issue

for appeal.

For obvious reasons, we will address these issues in reverse order.

STANDARD OF REVIEW

[¶6.]                 This case involves the review of a trial court’s grant of summary judgment. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strassburg v. Citizens State Bank
1998 SD 72 (South Dakota Supreme Court, 1998)
Greene v. Morgan, Theeler, Cogley & Petersen
1998 SD 16 (South Dakota Supreme Court, 1998)
Wissink v. Van De Stroet
1999 SD 92 (South Dakota Supreme Court, 1999)
Cooper v. James
2001 SD 59 (South Dakota Supreme Court, 2001)
Salem School District 43-3 v. Puetz Construction, Inc.
353 N.W.2d 51 (South Dakota Supreme Court, 1984)
Haberer v. First Bank of South Dakota (NA)
429 N.W.2d 62 (South Dakota Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
2002 SD 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huron-center-v-carlson-and-durrant-group-v-zurbrigen-industries-sd-2002.