Huntington Ingalls Incorporated v. Ministry of Defense of the Bolivarian Republic of Venezuela

CourtDistrict Court, District of Columbia
DecidedJune 13, 2019
DocketCivil Action No. 2018-0469
StatusPublished

This text of Huntington Ingalls Incorporated v. Ministry of Defense of the Bolivarian Republic of Venezuela (Huntington Ingalls Incorporated v. Ministry of Defense of the Bolivarian Republic of Venezuela) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huntington Ingalls Incorporated v. Ministry of Defense of the Bolivarian Republic of Venezuela, (D.D.C. 2019).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

) HUNTINGTON INGALLS ) INCORPORATED, ) ) Petitioner, ) ) v. ) No. 1:18-cv-0469 (KBJ) ) MINISTRY OF DEFENSE OF THE ) BOLIVARIAN REPUBLIC OF ) VENEZUELA, ) ) Respondent. ) )

MEMORANDUM OPINION

Petitioner Huntington Ingalls Incorporated has filed a petition asking this Court

to recognize and enforce an arbitration award that an arbitral tribunal issued on

February 19, 2018, in Huntington Ingalls’s favor. (See Pet., ECF No. 1, ¶¶ 22–23; see

also Pet’r’s Opp’n to Resp.’s Mot. to Dismiss (“Pet’r’s Opp’n”), ECF No. 22, at 8

(explaining that Huntington Ingalls seeks “recognition and enforcement of” an

arbitration award).) 1 But the undisputed genesis of the arbitration award at issue is a

lawsuit that a predecessor in interest to Huntington Ingalls instituted in the United

States District Court for the Southern District of Mississippi in 2002. (See Pet. ¶ 10 &

n.3.) And in 2010, when the Southern District of Mississippi compelled the arbitration

proceedings that eventually gave rise to the instant enforcement action, that court

specifically confirmed its intention to “retain jurisdiction in order to bring this matter to

1 Page-number citations to the documents that the parties have filed refer to the page numbers that the Court’s electronic filing system automatically assigns. conclusion after arbitration.” Northrop Grumman Ship Sys., Inc. v. Ministry of Def. of

Republic of Venez., No. 1:02cv785, 2010 WL 5058645, at *5 (S.D. Miss. Dec. 4, 2010);

(see also Pet. ¶¶ 16–20).

Given this case history, the undersigned issued an Order to Show Cause why

Huntington Ingalls’s petition for enforcement should not be transferred to the Southern

District of Mississippi or dismissed. (Order to Show Cause Why This Matter Should

Not Be Transferred or Dismissed (“Order to Show Cause”), ECF No. 25.) In its

response to that Order—which is before this Court at present—Huntington Ingalls

vigorously maintains that the United States District Court for the District of Columbia

should inject itself into a long-running legal dispute that is still pending in the Southern

District of Mississippi, by granting Huntington Ingalls’s enforcement petition and

turning the arbitration award (which, again, resulted from arbitration proceedings that

the Mississippi district judge initiated) into a judgment of this Court. (See Pet’r’s Resp.

to Order to Show Cause (“Pet’r’s Resp.”), ECF No. 27, at 5.)

As explained fully below, Huntington Ingalls provides no good cause for this

Court to be the tribunal that recognizes and enforces the arbitration award at issue, and

the undersigned cannot fathom any reason for exercising this Court’s enforcement

authority at the final stage of a matter that is plainly pending for resolution elsewhere.

Therefore, Huntington Ingalls’s (misplaced) enforcement petition will be DENIED

without prejudice, and the instant case will be DISMISSED. A separate order

consistent with this Memorandum Opinion will follow.

2 I. BACKGROUND

A. The Origins Of The Instant Dispute

The original lawsuit from which the instant enforcement matter derives was filed

17 years ago. According to Huntington Ingalls’s petition, on December 17, 1997,

Ingalls Shipbuilding, Incorporated, entered into a contract with Respondent Ministry of

Defense of the Bolivarian Republic of Venezuela (“the Ministry”), the object of which

was “to refurbish two LUPO-class missile-armed frigates in the Venezuelan Navy[.]”

(Pet. ¶ 5.) The contract was worth $315 million, with an allowance for additional

compensation for “absolutely necessary” work. (Id. ¶¶ 5, 6.) The contract also

contained an arbitration clause, which explained that “[s]hould the parties fail to

resolve [a dispute] within thirty (30) days of the emergence of the dispute, then at the

request of either party the matter shall be submitted for arbitration[.]” (Id. ¶ 8.) The

arbitration clause further provided that “any arbitration . . . shall take place in Caracas,

Venezuela.” (Id. (alteration omitted).)

A dispute subsequently arose, and on April 5, 2002, Northrup Grumman Ship

Systems, Inc. (“Northrup”)—Ingalls Shipbuilding’s successor in interest and

Huntington Ingalls’s predecessor in interest—requested arbitration pursuant to the

contract. (See id. ¶ 9.) Then, in October of 2002, Northrup filed a lawsuit in the United

States District Court for the Southern District of Mississippi seeking an order to compel

arbitration. (See id. ¶ 10); see also Northrop Grumman Ship Sys., Inc. v. Ministry of

Def. of Republic of Venez., No. 1:02cv785 (S.D. Miss. Oct. 24, 2002).

The following year, on April 16, 2003, the Mississippi federal court entered an

order compelling arbitration and finding that, “although . . . the Contract provides for

arbitration in Venezuela, the Court finds that the forum-selection clause should not be

3 enforced because the violently unstable political situation in Venezuela has rendered

that country an unsuitable forum at this time.” Northrop Grumman Ship Sys., Inc. v.

Ministry of Def. of Republic of Venez., No. 1:02cv785, 2003 WL 27383249, at *1 (S.D.

Miss. Apr. 16, 2003). That court proceeded to order that “[t]he arbitration shall take

place in Pascagoula, Mississippi, or such other place inside the United States chosen by

The Ministry[,]” and “[i]f The Ministry prefers a location outside the United States, The

Ministry may move this Court for good cause shown to consider such a request.” Id. at

*2. Notably, in this order compelling arbitration, the Mississippi federal court plainly

stated that the court “will retain jurisdiction . . . to resolve disputes relating to this

Order and to enforce any arbitral award[,]” id. at *1; furthermore, that court specifically

noted that it would “retain jurisdiction to enforce this Order . . . and to enforce the

decision and award rendered by the arbitrators[,]” id. at *2.

According to Huntington Ingalls’s petition, the arbitration was set to take place

in Mexico City (see Pet. ¶ 10), but the Ministry filed a motion to vacate the Mississippi

federal court’s arbitration order, after which that court stayed the arbitration pending its

consideration of the Ministry’s motion (see id. ¶ 11). In September of 2005, a lawyer

for the Ministry allegedly transmitted a settlement offer to Northrup, which was

accepted. (See id. ¶ 12.) However, the Ministry later contested the settlement (see id.),

and the Mississippi district judge upheld the settlement (see id.); see also Northrop

Grumman Ship Sys., Inc. v. Ministry of Def. of Republic of Venez., No. 1:02cv785, 2007

WL 2783343, at *6 (S.D. Miss. Sept. 24, 2007). The Ministry appealed the district

court’s decision to the U.S. Court of Appeals for the Fifth Circuit (see Pet. ¶ 12);

meanwhile, because the arbitration proceedings had been stayed for so long, in

4 November of 2008, the arbitral tribunal responsible for the Mexico City arbitration

terminated the arbitration. (See id. ¶ 13.)

In July of 2009, the Fifth Circuit vacated the district court’s judgment enforcing

the settlement, and also ruled that the termination of the arbitration mooted the district

court’s original order compelling arbitration. (See id. ¶ 14); see also Northrop

Grumman Ship Sys., Inc. v. Ministry of Def.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Continental Grain Co. v. Barge FBL-585
364 U.S. 19 (Supreme Court, 1960)
New Hampshire v. Maine
532 U.S. 742 (Supreme Court, 2001)
Elgin v. Department of the Treasury
132 S. Ct. 2126 (Supreme Court, 2012)
Rogers v. Pitt
535 F. Supp. 2d 29 (District of Columbia, 2008)
Stone & Webster, Inc. v. Georgia Power Company
965 F. Supp. 2d 56 (District of Columbia, 2013)
TermoRio S.A. E.S.P. v. Electranta S.P.
487 F.3d 928 (D.C. Circuit, 2007)
DRC, Inc. v. Republic of Honduras
999 F. Supp. 2d 1 (District of Columbia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Huntington Ingalls Incorporated v. Ministry of Defense of the Bolivarian Republic of Venezuela, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huntington-ingalls-incorporated-v-ministry-of-defense-of-the-bolivarian-dcd-2019.