Hughes v. Mill Creek Properties, Unpublished Decision (12-29-2006)

2006 Ohio 7008
CourtOhio Court of Appeals
DecidedDecember 29, 2006
DocketNo. 2005-T-0151.
StatusUnpublished
Cited by2 cases

This text of 2006 Ohio 7008 (Hughes v. Mill Creek Properties, Unpublished Decision (12-29-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hughes v. Mill Creek Properties, Unpublished Decision (12-29-2006), 2006 Ohio 7008 (Ohio Ct. App. 2006).

Opinions

OPINION
{¶ 1} Mary and Chester Hughes appeal from the grant of summary judgment by the Trumbull County Court of Common Pleas to Mill Creek Enterprises, Inc., and Mill Creek Properties, Ltd., on their action for trespass and personal injuries resulting from an alleged diversion of natural surface water flow. We affirm in part, reverse in part, and remand this matter.

{¶ 2} Since 1991, Mr. and Mrs. Hughes have owned a house located at 424 Niles-Cortland Road (State Route 46), in Howland Township, Trumbull County, Ohio. They used the house, which is located on the west side of the road, at an elevation below the road grade, both as a residence and business location. In the summer of 1999, Mill Creek Enterprises, Inc., acquired one or more residential properties on the east side of the road. This property was developed into the Howland Professional Center, 405-425 Niles-Cortland Road. Mill Creek Enterprises retained Western Reserve Land Consultants, Inc. to prepare site plans, excavation and ground level determinations, and storm runoff/drainage calculations for the project. The plans were submitted to the Trumbull County Engineer's Office, and the Ohio Department of Transportation for approval, which was received, after modifications. As part of the drainage system, a thirty-four foot trench drain was built across the driveway to the Professional Center. The trench drain empties into two retention ponds, one on each side of the entrance. It is undisputed that this drainage system, as designed and built, should be sufficient to prevent any runoff from a "ten-year intensity storm."

{¶ 3} The Professional Center was completed in 2000 or 2001. March 28, 2001, Mill Creek Enterprises conveyed the property to Mill Creek Properties, Ltd. July 23, 2002, a heavy rain occurred. This rain was not sufficient to constitute a "ten-year" rain. Mrs. Hughes, Mr. Frank Nemeth, a neighbor, and Mr. Tom Mariani, the Hughes' sewer man, observed rain flowing from the driveway of the Professional Center, across the Niles-Cortland Road, and into the Hughes' driveway. Part of the Hughes' house was flooded, and suffered damage.

{¶ 4} After complaints to Mr. Salata, the principal of the various Mill Creek entities, went unheeded, the Hughes' filed a complaint against him, Mill Creek Enterprises, and Mill Creek Properties, in August, 2002. July 21, 2003, another heavy rain occurred, causing flooding to the Hughes' house. Mr. Hughes suffered injuries when he was knocked off his feet by water pouring down his driveway, while trying to emplace sandbags. In the aftermath of the rain, Mrs. Hughes observed traces of mulch, similar to that used in the landscaped portions of the Professional Center's parking lot, in her yard.

{¶ 5} August 29, 2003, a further heavy rain fell. Once again, the Hughes' house flooded. Mr. Hughes observed a buildup of water in the driveway of the Professional Center, and crossing over the road into his driveway.

{¶ 6} December 8, 2003, Mr. and Mrs. Hughes filed an amended and supplemental complaint against the Mill Creek entities, with three counts of trespass, relating to the specific incidents of flooding; one count of continuing trespass; and one count each of battery and personal injury due to negligence, relating to Mr. Hughes' fall during the storm of July 21, 2003. Essentially, the Hughes alleged that the Mill Creek entities had altered the natural flow of surface water from the Professional Center in an unreasonable fashion, causing them damage.

{¶ 7} Mill Creek Enterprises and Mill Creek Properties answered, and, eventually moved for summary judgment. In support of their motions, the Mill Creek entities relied heavily on three affidavits. These included the affidavit of Mr. Joseph Gonda, P.E., of Western Reserve Land Consultants, who had prepared the plans for the Professional Center, and who testified that the plans and construction of the project were in accordance with all applicable government and professional requirements. The Mill Creek entities also introduced the affidavit of Mr. James Mahoney, P.S., who testified that he had conducted the "as-built" survey of the Professional Center property.

{¶ 8} Primarily, the Mill Creek entities relied on the affidavit of Mr. James Shurell, P.E., L.S.I.T. Mr. Shurell used Mr. Mahoney's surveys to determine that the plans for the Professional Center complied with the facilities actually completed. He further calculated the rain flows occurring due to the three storms complained of by the Hughes, and determined that the driveway drainage system of the Professional Center was more than adequate to accommodate the flows which occurred. He testified to a reasonable degree of engineering certainty that the flooding experienced by the Hughes was not due to the improvement of the Professional Center. Finally, Mr. Shurell testified, "within a reasonable degree of professional certainty," that the flooding of July 23, 2002, was caused by blockage to a 24-inch, reinforced concrete culvert, which was part of the roadway drainage system prior to construction of the Professional Center.

{¶ 9} The Mill Creek entities further relied on the depositions of Mr. and Mrs. Hughes, in which they admitted that they could not affirm that any diversion of water off the Professional Center's property was unreasonable.

{¶ 10} In opposing the summary judgment motions of the Mill Creek entities, Mr. and Mrs. Hughes relied on their own testimony, that no flooding had ever occurred to their property prior to construction of the Professional Center, as well as their own observations, and those of Mr. Nemeth and Mr. Mariani, of water flowing over the Professional Center's trench drain toward the Hughes property. Through the affidavit of Mr. George Sanders, the prior owner of the property, the Hughes admitted that severe flooding to the property had occurred in or around 1975, when the creek across the road overflowed. Mr. Sanders attributed this flooding to a plugged drain, evidently related to the road. The Hughes further obtained the affidavit of Mr. J. Robert Lyden, P.E. Mr. Lyden offered his professional opinion that the trench drain and retention pools at the Professional Center were sufficient to handle a "ten-year" rain, unless the drain was obstructed by debris. Throughout the proceedings in the trial court, Mr. and Mrs. Hughes insisted that the trench drain across the Professional Center's driveway was obstructed with debris.

{¶ 11} November 28, 2005, the trial court granted summary judgment to Mill Creek Enterprises, and Mill Creek Properties. December 27, 2005, Mr. and Mrs. Hughes timely noticed appeal, making three assignments of error:

{¶ l2} "[1.] The court below erred in granting summary judgment in favor of Appellees upon Count One and Count Three of the Amended and Supplemental Complaint pertaining to the events occurring on July 23, 2002, and on August 29, 2003.

{¶ l3} "[2.] The court below erred in granting summary judgment in favor of Appellees upon Counts Two, Five and Six of the Amended and Supplemental Complaint pertaining to events occurring on July 21, 2003.

{¶ l4} "[3.] The court below erred in granting summary judgment in favor of Appellees upon Count Four of the Amended and Supplemental Complaint alleging continuous trespass resulting form the events occurring July 23, 2002, July 21, 2003 and August 29, 2003."

{¶ 15}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Novy v. Ferrera
2014 Ohio 1776 (Ohio Court of Appeals, 2014)
Creech v. Brock & Associates Construction, Inc.
918 N.E.2d 541 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 7008, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hughes-v-mill-creek-properties-unpublished-decision-12-29-2006-ohioctapp-2006.