HSM Construction Services, Inc. v. MDC Systems, Inc.

239 F. App'x 748
CourtCourt of Appeals for the Third Circuit
DecidedJuly 16, 2007
Docket06-2584
StatusUnpublished
Cited by2 cases

This text of 239 F. App'x 748 (HSM Construction Services, Inc. v. MDC Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HSM Construction Services, Inc. v. MDC Systems, Inc., 239 F. App'x 748 (3d Cir. 2007).

Opinion

OPINION

SLOVITER, Circuit Judge.

Appellants HSM Construction Services, Inc. (“Construction”) and HSM Management Services, Inc. (“Management”) (jointly referred to as “HSM” unless otherwise noted) appeal from the District Court’s order confirming an arbitration award in favor of the appellee, MDC Systems, Inc. HSM argues that the Arbitration Panel manifestly disregarded the law and was evidently partial to MDC Systems, Inc. 1

*750 I.

Because the parties are familiar with the facts, we adopt the factual scenario as stated by the District Court in its opinion:

The present case stems from a lawsuit regarding the construction of the Rosewood Care Center of St. Charles, Illinois, in which Construction was a named defendant. To aid in its defense of that lawsuit, Construction hired MDC Systems, Inc. (“MDC”) to prepare expert engineering reports.
By a letter dated July 18, 2002, MDC drafted a Proposal of Expert Consulting Services. Throughout the Proposal, MDC refers to the other party to the contract as “HSM” and does not specify whether it is referring to “HSM Management” or “HSM Construction.” By a letter dated July 19, 2002, printed on “HSM Management Services, Inc.” letter head, “HSM” provided supplementary terms and conditions. The fax also included the signature page of the Proposal, which was signed by General Counsel for “HSM.” Afterwards, HSM Management Services, Inc. paid the initial retainer and made two subsequent partial payments to MDC.
Construction and Management argue[d] that MDC prepared an unusable expert disclosure report. As a result, MDC was not paid for the balance due under the contract. MDC then submitted a Demand for Arbitration to the American Arbitration Association (“AAA”) seeking relief of $80,662.53 in unpaid fees from only “HSM Management Services, Inc.” Construction was not named as a party on MDC’s initial Demand.
On March 16, 2004, the arbitration Panel conducted a preliminary hearing conference call. Management argued that it was not a party to the contract in question. The Panel later amended the caption from “HSM Management, Inc.” to “HSM, Inc., HSM Management, Inc., and HSM Construction Services, Inc.”

HSM Constr. Serv., Inc. v. MDC Sys., Inc., 2006 WL 1030229, at *1 (E.D.Pa. Apr. 13, 2006).

At the conclusion of the arbitration, the panel issued a decision in favor of MDC and held Construction and Management jointly and severally liable for $86,969. HSM raises two issues in its appeal. It argues first, that “the District Court errfed] in determining that the arbitration panel did not manifestly disregard the law by finding Management liable to MDC where Management was not a party to the agreement between Construction and MDC[.]” Appellants’ Br. at 3. Second, it argues that the District Court erred in determining that the arbitration panel was not evidently partial to MDC.

II.

A.

We consider first which law applies. HSM argued in the District Court that the Federal Arbitration Act (“FAA”) applies, whereas MDC argued that the Delaware Uniform Arbitration Act (“DUAA”) applies. The District Court decided that “the provisions of the FAA and the DUAA that are applicable in this case, the ‘evidently partial’ standard and the ‘manifest disregard of the lavP standard, are identical” and therefore it declined to decide which law applies because the result would be the same. 2006 WL 1030229, at *2. We agree with the District Court in this respect.

*751 This court reviews a district court’s denial of a motion to vacate a commercial arbitration award de novo. Dluhos v. Strasberg, 321 F.3d 365, 369 (3d Cir.2003). In reviewing a district court’s order confirming an arbitration award, this court reviews the district court’s factual findings for clear error and exercises plenary review over the district court’s determination on questions of law. See China Minmetals Materials Imp. & Exp. Co., Ltd. v. Chi Mei Corp., 334 F.3d 274, 278-79 (3d Cir.2003) (citing First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 947-48, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995)); Kaplan v. First Options of Chicago, Inc., 19 F.3d 1503, 1509 (3d Cir.1994), aff'd, 514 U.S. 938, 115 S.Ct. 1920, 131 L.Ed.2d 985 (1995).

B.

HSM contends that Management was never a party to the agreement with MDC (the “Agreement”) because it neither signed the Agreement nor was a party to the underlying lawsuit concerning the construction of the Rosewood Care Center. Because the issue as to whether Management was a party to the arbitration agreement is an issue of arbitrability, the court must make an independent determination. See First Options, 514 U.S. at 943-45, 115 S.Ct. 1920.

The parties’ objective manifestations control in deciding whether they formed a contract by mutual assent. Management’s outward words and acts indicate that it is a party to the Agreement. First, the signature page of MDC’s Proposal and the July 19, 2002 letter from “HSM” to MDC (the “Letter”) were both signed by Dennis McCubbin, the General Counsel of Management and Construction, on behalf of “HSM.” Although neither MDC nor McCubbin explicitly specified whether “HSM” referred to Management or Construction, both the Letter and its fax cover sheet were on Management’s letter head. “HSM Management Services, Inc.,” as it appears on both the letter head and fax cover page, is the only full name on those documents that is consistent with the abbreviation of “HSM.” This leads to the conclusion that the “HSM” referred to in the Letter as a party must be “HSM Management Services, Inc.”

Second, Management is the entity that paid MDC’s fees for its service. The checks payable to MDC for its service were all under Management’s name. Indeed, it paid the initial retainer and the two subsequent partial payments. Although Management contends that it paid the check on behalf of Construction, there was no outward indication of such subjective and undisclosed intention. From the objective acts of Management, it was Management who signed the Agreement and performed the obligation to pay under the Agreement. Thus, Management is a party to the Agreement.

Management argues that it never was a party to the underlying Rosewood Care Center lawsuit, and therefore it could not be a party to the Agreement, which retained MDC to provide expert services for the underlying proceeding. However, Management had an interest in the proceeding, because it possessed one of the claims for which Construction sought indemnification in the Rosewood Care Center lawsuit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stone v. Bear, Stearns & Co.
872 F. Supp. 2d 435 (E.D. Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
239 F. App'x 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hsm-construction-services-inc-v-mdc-systems-inc-ca3-2007.