HRFH v. Pourlos Enterprises

CourtCourt of Appeals of South Carolina
DecidedJuly 5, 2006
Docket2006-UP-308
StatusUnpublished

This text of HRFH v. Pourlos Enterprises (HRFH v. Pourlos Enterprises) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HRFH v. Pourlos Enterprises, (S.C. Ct. App. 2006).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS 
PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


HRFH, LLC, Respondent,

v.

Pourlos Enterprises, Inc., Steve C. Pourlos and J. Allen  Howell, Appellants.


Appeal From Greenville County
 G. Edward Welmaker, Circuit Court Judge


Unpublished Opinion No. 2006-UP-308
Submitted June 1, 2006 – Filed July 5, 2006


AFFIRMED


Adam Fisher, Jr., of Greenville, for Appellants.

Melvin Hutson, and Lynn Hudson, of Greenville, for Respondent.

PER CURIAM:  In this breach of contract case, Pourlos Enterprises, Inc. (PEI), Steve C. Pourlos, and J. Allen Howell appeal from the jury’s verdict in favor of HRFH, LLC.  We affirm.[1]

FACTS

HRFH employed the services of Foothills Real Estate, the Windsor/Aughtry Company, and agent Charles Reyner, Jr., (collectively, real estate agencies and agent) to locate a tenant for its soon-to-be renovated historic building in downtown Greenville.  The real estate agencies and agent located PEI.  On October 26, 2000, PEI entered into a ten-year lease with HRFH for the first floor and basement of the building to open a fine dining restaurant to be called the Vault.  PEI’s president, Pourlos, and financial officer, Howell, signed a personal guarantee for the obligations of PEI under the lease.  The term of the lease was to commence January 1, 2001, and PEI was required to pay two month’s rent in advance.  The lease provided that rent would then commence forty-five days after the space was delivered for PEI’s upfits for the restaurant.  An addendum to the lease provided that HRFH would be responsible for certain renovations prior to delivering the space to PEI and that PEI was responsible for installing the remaining walls, furniture, fixtures, and kitchen infrastructure necessary for the restaurant.  

To enable PEI to open the Vault by the end of March 2001, the parties agreed PEI could contract with the same construction firm hired by HRFH to perform demolition and upbuilding on the building, Raby Construction.  Thus, HRFH’s upbuilding and PEI’s upfits could be performed simultaneously.  However, HRFH’s construction was delayed while PEI sought plans and permits to upfit the space for the restaurant.  PEI also requested several changes to the building, including moving the proposed location of the bathrooms and changing the floors, that required additional delay.  PEI finally obtained architectural plans on January 2, 2001, which were not approved by DHEC until February 1, 2001.  Although it would have taken another thirty days to obtain a permit before construction could begin from that point, Pourlos never directed Raby Construction to proceed.  In addition to the construction delays, the chef hired to create the menu and cook at the Vault quit.  Throughout this time period, Pourlos and Howell sought additional investors for PEI. 

PEI alleged that HRFH breached the lease by not delivering the renovated space for their upfits by January 1, 2001.  On February 7, 2001, Pourlos’s attorney sent a request to HRFH for $139,000 to release HRFH from any further liability for breaching the lease.  After requesting further assurances from PEI and being informed that Pourlos wanted to get out of the lease, HRFH sent Pourlos a letter on April 12, 2001, indicating the premises would not be delivered to PEI because it had breached the agreement in numerous respects, including:  Howell’s failure to provide financial disclosures; Pourlos’s express repudiation of the lease; Pourlos’s actions that amounted to purposeful delay of the renovations of the building; and PEI’s subletting of the space to Fovos, Inc., without approval of HRFH.   

HRFH filed the underlying lawsuit for, among other claims, breach of contract against PEI, Pourlos, Howell, and the real estate agencies and agent.  PEI, Pourlos, and Howell counterclaimed, alleging breach of contract, fraud, and equitable indemnity.  The real estate agencies and agent were eventually dismissed from the action.  A trial was held in June 2004.  After the presentation of all of the evidence, both parties moved for a directed verdict.  The trial judge directed a verdict for PEI, Pourlos, and Howell (collectively, Appellants) on HRFH’s claim for breach of contract accompanied by a fraudulent act.  The judge also directed a verdict for HRFH on Appellants’ claims of fraud, breach of contract accompanied by a fraudulent act, and equitable indemnity.  Both parties’ claims of breach of contract went to the jury.  The jury returned a verdict in favor of HRFH in the amount of $190,000 on its breach of contract claim and also found in favor of HRFH on Appellants’ breach of contract claim.  The trial judge denied Appellants’ post-trial motions.  This appeal followed. 

LAW/ANALYSIS

I.  Breach of Contract

Appellants argue the trial judge erred by denying their motion for a directed verdict as to their breach of contract claim against HRFH.  They also argue the trial judge erred in denying their post-trial motion for judgment notwithstanding the verdict (JNOV).[2]  We disagree.

In reviewing a denial of motions for directed verdict and JNOV, the evidence and the reasonable inferences that can be drawn therefrom must be viewed in the light most favorable to the non-moving party.  Brady Dev. Co. v. Town of Hilton Head Island, 312 S.C. 73, 78, 439 S.E.2d 266, 269 (1993);  Evans v. Taylor Made Sandwich Co., 337 S.C. 95, 99, 522 S.E.2d 350, 352 (Ct. App. 1999).  The motion should be denied where the “evidence yields more than one inference or its inference is in doubt.”  Evans, 337 S.C. at 99, 522 S.E.2d at 352.  When considering the motion, the appellate court nor the trial court has authority to “decide credibility issues [or] . . . to resolve conflicts in the testimony and evidence.”  Garrett v. Locke, 309 S.C. 94, 99, 419 S.E.2d 842, 845 (Ct. App. 1992).

The parties do not dispute the existence of the written lease agreement in this case.  They only dispute the interpretation of that contract.  “The main guide in contract interpretation is to ascertain and give legal effect to the intentions of the parties as expressed in the language of the lease.”  Gilbert v. Miller, 356 S.C. 25, 30, 586 S.E.2d 861, 864 (Ct. App. 2003).  Where the language of the contract is clear, this court must interpret the lawful meaning of the contract and the intent of the parties according to the plain, ordinary, and popular sense of the terms used in the agreement.  Id. at 30-31, 586 S.E.2d at 864.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Winnsboro v. Wiedeman-Singleton, Inc.
398 S.E.2d 500 (Court of Appeals of South Carolina, 1990)
Town of Winnsboro v. Wiedeman-Singleton, Inc.
414 S.E.2d 118 (Supreme Court of South Carolina, 1992)
Harkins v. Greenville County
533 S.E.2d 886 (Supreme Court of South Carolina, 2000)
Evans v. Taylor Made Sandwich Co.
522 S.E.2d 350 (Court of Appeals of South Carolina, 1999)
Brady Development Co. v. Town of Hilton Head Island
439 S.E.2d 266 (Supreme Court of South Carolina, 1993)
Zaman v. S. C. State Board of Medical Examiners
408 S.E.2d 213 (Supreme Court of South Carolina, 1991)
Gilbert v. Miller
586 S.E.2d 861 (Court of Appeals of South Carolina, 2003)
Brading v. County of Georgetown
490 S.E.2d 4 (Supreme Court of South Carolina, 1997)
Charleston County School District v. Laidlaw Transit, Inc.
559 S.E.2d 362 (Court of Appeals of South Carolina, 2001)
Garrett v. Locke
419 S.E.2d 842 (Court of Appeals of South Carolina, 1992)
Rock Hill Telephone Co. v. Globe Communications, Inc.
611 S.E.2d 235 (Supreme Court of South Carolina, 2005)
Bryant v. Waste Management, Inc.
536 S.E.2d 380 (Court of Appeals of South Carolina, 2000)
Vermeer Carolina's, Inc. v. Wood/Chuck Chipper Corp.
518 S.E.2d 301 (Court of Appeals of South Carolina, 1999)
Cowart v. Poore
523 S.E.2d 182 (Court of Appeals of South Carolina, 1999)
Commerce Center of Greenville, Inc. v. W. Powers McElveen & Associates, Inc.
556 S.E.2d 718 (Court of Appeals of South Carolina, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
HRFH v. Pourlos Enterprises, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hrfh-v-pourlos-enterprises-scctapp-2006.