Houston Belt & Terminal Ry. Co. v. Scheppelman

203 S.W. 167, 1918 Tex. App. LEXIS 436
CourtCourt of Appeals of Texas
DecidedApril 1, 1918
DocketNo. 335.
StatusPublished
Cited by4 cases

This text of 203 S.W. 167 (Houston Belt & Terminal Ry. Co. v. Scheppelman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Houston Belt & Terminal Ry. Co. v. Scheppelman, 203 S.W. 167, 1918 Tex. App. LEXIS 436 (Tex. Ct. App. 1918).

Opinion

BROOKE, J.

Appellee sued the Houston Belt & Terminal Railway Company, claiming damages on account of personal injuries to Ms wife, Mrs. Kate Scheppelman, the injuries haying been caused by a fall. It is alleged that the Houston Belt & Terminal Railway Company is liable to plaintiff for said injuries thus sustained, because at tire point where plaintiff’s wife fell the sidewalk was in a defective condition, due to the defendant’s negligence.

The negligence alleged was, in substance, that the defendant constructed, or caused tb be constructed, a sewer at the corner of Preston avenue and La Branch street, in the city of Houston, and negligently and carelessly failed "to properly fill up, pack, and ram down tight the earth taken from under said sidewalk, and from adjacent thereto, and so negligently and carelessly refilled the excavations that the earth under said sidewalk and adjacent thereto gradually sank until it caused the said sidewalk to sink in one place and buckle up in another, and caused one portion of said walk to be raised several inches higher than the adjoining portion of said walk, and caused same to project several inches above the surface, so as to make it very dangerous for pedestrians crossing the said street and using said walk, and especially to persons using said sidewalk to cross from the northeast side of Preston avenue to the southwest side of Preston avenue, the said projection having a tendency to trip pedestrians and throw them on the said concrete pavement. It was alleged that the work of construction was done either' by the defendant directly or through the Hedges Construction Company, a contractor. In addition to the averment of negligence, as aforesaid, the violation of the city ordinance was also specified with reference to the matter of refilling the excavation and packing the earth. Damages in the amount of $20,000 were claimed in the petition.

The defendant answered with a general demurrer and general denial, and averments that it should not be held liable on account of any of the matters and things set out in plaintiff’s petition, since the work of construction was done by the Hedges Construction Company, a corporation, under a contract of date August 25, 1908, the terms of which constituted said Hedges Construction Company an independent contractor, and as such said Hedges Construction Company completed the work of construction, and controlled all of the details thereof. Defendant further alleged that there should be no recovery against it, since prior to the accident in question, which was alleged to have occurred on November 20, 1912, the city of Houston had taken over the said sewer constructed by Hedges Construction Company under the contract mentioned, and the defendant had surrendered any and all control, and any and all connection with, and any and all rights in, said sewer to the city of Houston; which arrangement was consummated in the year 1909, more than three years prior to the accident in question. Defendant further alleged contributory negligence on the part of Mrs. ‘Scheppelman.

The cause was tried on November 14, 1916, and submitted to the jury by special issues. Upon the jury’s verdict, in response to the issues propounded, the court entered judgment against the defendant and in favor of the plaintiff, E. Scheppelman, in the sum of $7,-500, with interest and costs of court.

On December 5, 1916, the amended motion for new trial was overruled, the defendant excepted to the action of the court in overruling same, and filed its supersedeas bond. The case was appealed to the Court of Civil Appeals for the First Supreme Judicial District of Texas at Galveston, and has been transferred to this court, and is now before us for consideration.

By the first assignment of error it is claimed that the court erred to the prejudice of defendant in failing and refusing, upon defendant’s request, to instruct the jury peremptorily in behalf of the defendant, it appearing that plaintiff is not entitled to recover, because the evidence is wholly insufficient to raise the issue of any duty owing by the defendant to the plaintiff or plaintiff’s wife with reference to any of the matters and things set out in plaintiff’s petition. Under this assignment are submitted many propositions and counter propositions. Among others, it is urged by appellee that, when the appellant made an excavation in a public street and under and adjacent to a public sidewalk, it owed to the plaintiff and his wife, and to the public generally, the duty to use proper precautions to see that the excavation was properly refilled and tamped, so that there would be no such subsidence of the surface as would create an obstruction or pitfall dangerous to pedestrians.

It seems that this sewer was constructed along Preston avenue, from St. Emanuel street to the Austin street sewer, between the sidewalk and the curb, and that the sewer ditch was an open excavation; that is, an open ditch was excavated, the pipe was put at the bottom of the excavation, and then the excavation was refilled. At the place where Mrs. Scheppelman fell the ditch was originally 10 or 12 feet deep. At the time this excavation was made there was an ordinance of the city of Houston in force requiring any person or corporation who dug, or caused to be dug, any ditch, or made any opening in, over, or across any street or sidewalk, for the purpose of laying down gas or other pipes, to fill up, pack, and ram down tight the earth *169 taken therefrom, ancl leave such street or sidewalk in as good order or condition as the same was before such excavation was made. The appellant secured from the city council permission to dig the ditch and lay the sewer pipe, and it is urged that it owed to the plaintiff and his wife, and to the public at large, the duty to comply with the ordinance which was enacted to safeguard the public. The permit to put in this sewer was given by the city council to the Houston Belt & Terminal Railway Company. The evidence showed that water tamping was the usual and customary way of tamping the refilling of excavations in public streets, and was the safest and most approved method of tamping, and it is undisputed that the ditch was not water tamped. The testimony showed that the plans and specifications for every foot of the sewer that was laid was filed with the Hedges Construction Company, and the^specifications instructed the Hedges Construction Company as to how the work should be done. The contract between the Houston Belt & Terminal Railway Company and the Hedges Construction Company contained the following provision:

“If necessary to water tamp the refilling of the above sewer, this is to be done at the expense of the company, the contractor to be allowed cost of work plus ten per cent.”

There was no testimony showing that there was any other method of tamping as efficient as water tamping, and no testimony going to show that any other system of tamping would leave the street or sidewalk in as good condition as it was before the excavation was made.

The jury found that the Houston Belt & Terminal Railway Company retained control and supervision of the work. STom the record it appears that the appellant’s engineer was on the ground while the refilling of this excavation was being done, and that such refilling was done under the direction of defendant and its engineer, and the jury found that as the work progressed the appellant and its engineer dictated as to how the refilling was to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. L. Martin, Inc. v. Kyser
104 S.W.2d 592 (Court of Appeals of Texas, 1937)
Prairie Oil & Gas Co. v. Wright
238 S.W. 974 (Court of Appeals of Texas, 1921)
Houston Belt & Terminal Ry. Co. v. Scheppelman
235 S.W. 206 (Texas Commission of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
203 S.W. 167, 1918 Tex. App. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/houston-belt-terminal-ry-co-v-scheppelman-texapp-1918.