Hostler v. Davison County Drainage Commission

974 N.W.2d 415, 2022 S.D. 24
South Dakota Supreme Court·Decided May 4, 2022·No. 29404·Published·Cited by 2 cases

Opinion

#29404-vacate-JMK 2022 S.D. 24

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

KENNETH HOSTLER, Plaintiff and Appellee, v.

DAVISON COUNTY DRAINAGE COMMISSION, Defendant,

and JOHN MILLAN, Defendant and Appellant.

****

APPEAL FROM THE CIRCUIT COURT OF THE FIRST JUDICIAL CIRCUIT DAVISON COUNTY, SOUTH DAKOTA

****

THE HONORABLE PATRICK T. SMITH Judge

****

DAVID L. GANJE Sun City, Arizona Attorney for plaintiff and appellee.

GARY R. LEISTICO JAYNE E. ESCH of Rinke Noonan, LTD St. Cloud, Minnesota Attorneys for defendant and appellant.

****

CONSIDERED ON BRIEFS

APRIL 26, 2021

OPINION FILED 05/04/22

KERN, Justice [¶1.] John Millan applied for permits from the Davison County Drainage Commission (drainage commission) to install drain tile on his farmland in Davison County. The drainage commission held a public hearing on Millan’s applications, at which Kenneth Hostler, Millan’s downstream neighbor, appeared and objected to the permits. The drainage commission approved the permits, and Hostler appealed to the circuit court. The circuit court reversed, holding that the drainage commission abused its discretion in granting the permits because Millan failed to produce evidence before the drainage commission of compliance with the County drainage ordinances. Millan appeals. Because the circuit court lacked jurisdiction to hear Hostler’s challenge to the drainage commission’s permitting decision, we vacate the circuit court’s findings of fact, conclusions of law, and order.

Factual and Procedural Background [¶2.] Davison County has adopted ordinances governing drainage projects on agricultural land. Per the ordinances, landowners must seek and receive approval in the form of a permit from the drainage commission before installing drain tile. The drainage commission is authorized by SDCL 46A-10A-30 to promulgate ordinances governing drainage permits in rural areas, but must do so consistent with the principles and factors set forth in SDCL 46A-10A-20. [¶3.] Millan owns farmland in Davison County, and in an effort to increase crop yields on his farmland, he applied for multiple drainage permits with the

drainage commission on February 27, 2020. 1 Only four of Millan’s applications are relevant to this appeal, and those applications outlined a planned network of 300,000 feet of perforated drain tile and 15,000 feet of solid drain tile, both of which would help remove excess surface water from 350 acres. [¶4.] After Millan submitted his applications, his neighbors were notified of a hearing on the matter that was set for March 17, 2020. After the drainage commission approved a first set of applications at this hearing, Millan presented the second group of applications, which was composed of the four applications at issue here. These applications proposed to drain water into an outlet at the edge of Millan’s land, and Hostler (Millan’s first downstream neighbor) owned farmland just beyond this outlet. After presentation of this group of applications, Hostler voiced concern. However, at the conclusion of the hearing, the drainage commission voted 5-2 to approve the four permit applications at issue. [¶5.] Shortly thereafter, Hostler filed a two-count complaint with the circuit court against Millan and the drainage commission, asserting the circuit court had jurisdiction to hear his challenge under SDCL 46A-10A-35 and County ordinance § 5:05. 2 Hostler asked the circuit court to declare the permits void and to issue a permanent injunction halting the project. Hostler claimed the drainage commission

1. Millan farms the land and applied for the permits through Millan Acres, John Millan Revocable Trust, and Millan Family Farms Partnership.

2. Hostler initially cited to County ordinance § 5:01 as a jurisdictional basis in his complaint, but he later cited to § 5:05 in other filings. Davison County Drainage Ordinance § 5:05 provides, “Any affected party may appeal the Drainage Commission’s decision on a drainage dispute to circuit court.”

(Emphasis added.) (Latest revisions to the ordinances were effective September 24, 2013.)

abused its discretion by failing to consider certain factors set forth in the relevant ordinances and State statutes. Fifteen days later, on April 18, Hostler moved for partial summary judgment. [¶6.] On June 16, the circuit court heard oral argument on Hostler’s motion. Hostler asserted that Millan’s applications and the record before the drainage commission contained insufficient evidence to support issuance of the permits. The court permitted the parties to submit supplemental arguments in writing following the hearing. In his supplemental brief, Hostler argued that the drainage commission’s “decision fails to state [the drainage commission’s] reasons for the way it decided under the ordinance and statute. If certain facts found or factors under the ordinance and state law were relied on by the Commission in making its decision, it was required to say so . . . .” In response, Millan argued that his applications and presentation at the hearing before the drainage commission were sufficient to apprise the drainage commission of the merits of his drainage plan. [¶7.] On July 28, 2020, the circuit court issued a memorandum opinion and, on August 7, 2020, issued an order and findings of fact and conclusions of law, incorporating the memorandum opinion. The court granted Hostler’s motion for partial summary judgment and voided the four permits, holding that the drainage commission abused its discretion by issuing the permits because Millan failed to provide sufficient evidence to the drainage commission of his compliance with the provisions of the drainage ordinances. [¶8.] Millan appealed, raising multiple issues. However, we identified an issue with the jurisdiction of the circuit court to hear Hostler’s challenge to the

drainage commission’s permitting decision and, on October 1, 2021, ordered supplemental briefing from the parties. Having considered the briefs submitted, we address the dispositive issues set forth below regarding the circuit court’s jurisdiction.

1. Whether the circuit court had jurisdiction under SDCL 46A-10A-35 or any other authority to hear an appeal directly from the drainage commission’s decision.

2. Whether a person objecting to a drainage permit application may bring a declaratory action directly to the circuit court challenging the drainage commission’s decision to grant the permit.

Analysis and Decision

Free access — add to your briefcase to read the full text and ask questions with AI

Hostler v. Davison County Drainage Commission, 974 N.W.2d 415, 2022 S.D. 24 (S.D. 2022).

974 N.W.2d 415 (Hostler v. Davison County Drainage Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Jensen, Hoffman v. Dep't of Corrections
2025 S.D. 35 (South Dakota Supreme Court, 2025)