Horth v. American Aggregates Corp.

35 N.E.2d 592, 31 Ohio Law. Abs. 331
CourtOhio Court of Appeals
DecidedFebruary 6, 1940
DocketNo. 565
StatusPublished
Cited by11 cases

This text of 35 N.E.2d 592 (Horth v. American Aggregates Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horth v. American Aggregates Corp., 35 N.E.2d 592, 31 Ohio Law. Abs. 331 (Ohio Ct. App. 1940).

Opinions

OPINION

By BARNES, J.

The above entitled cause is now being determined as an error proceeding by reason of defendant’s appeal on questions of law from the judgment of the Court of Common Pleas oi Darke County, Ohio.

Plaintiff’s action was predicated upon the claim that the defendant maliciously induced the Cable Co., Inc., Canton, Ohio, to breach a contract which the plaintiff had with the Cable Co., to' plaintiff’s damage in the sum of $29,-594.00, with interest.

During the month of May, 1935, the United States Government duly advertised for bids for furnishing of labor, equipment, and materials for the doing of certain work, more fully covered in certain specifications, for the relocation of the Baltimore & Ohio Railroad-Beach City Reservoir.

'This Government contract was very large and attracted a great many bidders under the separately numbered specifications.

The Cable Co., a Canton. Ohio, corporation engaged in construction work, was interested in certain items under the specifications.

Prior. to the date set in the advertisement for presentation of bids, the Cable Co. wrote to the plaintiff in Cleveland, Ohio, (the latter being a largé railroad construction company) asking if the latter would be interested in bidding them on certain named specifications, and,, if so, to submit proposals.

The plaintiff, H. H. Horth, doing business under the trade name of Acme Railroad Construction Company, was interested and so informed the Cable Co. and prior to the day of bidding submitted written proposal on certain designated numbers and specifications, and stipulated that it was desired that the-Cable Co. indicate before the time of opening bids whether or not plaintiff’s proposition would be accepted.

The designated date for submitting and opening bids was May 7, 1935.

On the evening before the day of the bidding the plaintiff and representatives of the Cable Co. met at a room in a hotel and after conference and some modifications the Cable Co. in writing accepted plaintiff’s proposals. The Government had previously prepared and [332]*332made available for all interested parties blank forms of contract with specifications and plainly indicating where and how blanks were to be filled out by prospective bidders.

The Cable Co. submitted its bid on one of these general forms and using under the numbered specifications, upon which plaintiff had submitted proposals, the identical figures furnished by plaintiff and agreed upon in writing on the evening of the day previous. When the bids were opened, it was apparent that the Cable Co. was the low bidder. The Cable Co. iii their bid on page “i” of the specifications in answering data under the heading, “TRACK LAYING AND BALLAST EQUIPMENT,” inserted the following: “Will sublet to Acme Railroad Construction Co. of Cleveland who will have all the necessary equipment for this work.” The formal contract between the Cable Co. and the United States Government was executed May 23, 1935, but was executed subject to a stipulation that the same would be approved by the Government Engineers.

Such approval was entered by R. G. Powell of the Corps of Engineers oh July 2, 1935. Plaintiff claims this written proposal and the Cable Company’s executed acceptance thereof constituted a binding contract, and, if nothing to the contrary appears, we think this claim is correctly made.

However, there is a serious question as to whether or not the parties so treated it. On the day following the opening of the bids the plaintiff returned to Cleveland, and thereafter within the next week or two at irregular intervals there were communications between the plaintiff and Cable Co. by telephone or otherwise resulting in plaintiff and his counsel going to Canton and meeting with officers of the Cable Co. at the office of Judge Clark, the latter’s counsel. In the conference there developed some differences. At this meeting, or a subsequent meeting, plaintiff through his attorney submitted what he designated as a supplemental or working agreement covering details. This was rather a lengthy document. The Cable Co. made some objections to it, but apparently not on the ground that plaintiff’s proposal and the Cable Company’s acceptance on May 6th constituted the contract. In the trial of the case the question was raised that the Secretary of the Cable Co. did not have the authority to sign for the company. We do not think that this claim is well grounded, and, therefore, dismiss from further . comment. Both parties in their conference following the opening of bids seemed to proceed on the theory that it was customary under such circumstances for the contractor and subcontractor to enter into a formal contract covering detail and working arrangements. The Cable Co. contended that the supplemental or working contract submitted by plaintiff altered the terms of plaintiff’s original proposal.

Plaintiff denies this claim. This document was introduced in evidence as Exhibit 10. At a subsequent meeting sometime in July the Cable Co. claimed that the question was raised and discussed that plaintiff had quoted to other bidders a lower price than was made in his written proposal and that this was in violation of his inducing proposal, that he had made no quotations to any other contractor at a lower price, except to one where an $800.00 deduction had been made. The plaintiff denies much, if not all, of this detail. In any event, the supplemental contract was never executed and plaintiff did not do the work.

Defendant in its answer, among other things, denied the allegations of the petition that it had maliciously induced the Cable Co. to breach its contract. In the trial of the case a verdict was returned for the plaintiff in the sum of $13,300.00. Motion for new trial was duly filed, overruled, and judgment entered on the verdict.

This is the final order from which defendant prosecutes appeal in this court on question of law. Appellant sets [333]*333out 12 separately numbered assignments of error as follows:

“1. The Common Pleas Court erred at the trial in overruling the defendant’s motion for judgment on the pleadings.

2. The Common Pleas Court erred at the trial in overruling the defendant’s motion at the conclusion of the plaintiff’s case, and after plaintiff had rested nis case, to arrest the case from the jury and to direct a verdict in favor of the defendant.

3. Said Common Pleas Court erred at the trial in overruling the defendant’s motion at the conclusion of all the testimony offered in this case, and after both plaintiff and defendant had rested, to arrest the crse from the jury and to direct a verdict in favor of the defendant.

4. Said Common Pleas Court erred in overruling the motion of the defendant for final judgment, notwithstanding the verdict.

5. The verdict and judgment in the Common Pleas Court are against the weight of the evidence and contrary to law.

6. Said Court erred in admitting evidence offered by plaintiff and objected to by defendant, to the admission of which the defendant, at the time, excepted.

7. The Court erred in excluding evidence offered by the defendant, to the exclusion of which, by the Court, the defendant, at the time, excepted.

8. The Court erred in refusing to ¡charge the jury as requested by defendant.

9. The Court erred at the trial in giving to the jury before argument, special instructions Nos.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Province v. Cleveland Press Publishing Co.
787 F.2d 1047 (Sixth Circuit, 1986)
James Province v. Cleveland Press Publishing Co.
787 F.2d 1047 (Third Circuit, 1986)
Heheman v. Scripps Company
661 F.2d 1115 (Sixth Circuit, 1981)
Heheman v. E. W. Scripps Co.
661 F.2d 1115 (Sixth Circuit, 1981)
McAlpine v. AAMCO Automatic Transmissions, Inc.
461 F. Supp. 1232 (E.D. Michigan, 1978)
Hammonds v. Aetna Casualty & Surety Company
237 F. Supp. 96 (N.D. Ohio, 1965)
Hance v. Peacock
169 N.E.2d 564 (Shelby County Court of Common Pleas, 1960)
Wolf v. Perry
339 P.2d 679 (New Mexico Supreme Court, 1959)
Pestel Milk Co. v. Model Dairy Products Co.
52 N.E.2d 651 (Ohio Court of Appeals, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
35 N.E.2d 592, 31 Ohio Law. Abs. 331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horth-v-american-aggregates-corp-ohioctapp-1940.