Horosz v. Alps Estates, Inc.

642 A.2d 384, 136 N.J. 124, 1994 N.J. LEXIS 494
CourtSupreme Court of New Jersey
DecidedJune 13, 1994
StatusPublished
Cited by18 cases

This text of 642 A.2d 384 (Horosz v. Alps Estates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horosz v. Alps Estates, Inc., 642 A.2d 384, 136 N.J. 124, 1994 N.J. LEXIS 494 (N.J. 1994).

Opinion

The opinion of the Court was delivered by

GARIBALDI, J.

This appeal concerns the narrow question whether N.J.S.A 2A14-1.1 prohibits a homeowner from recovering against a builder-developer for that builder’s subsequent repair work. Specifically, we address whether the ten-year statute of repose bars a lawsuit brought ten years after the initial construction of the house, but within ten years of the builder-developer’s substantial repairs to the house.

I

On June 14,1977, plaintiffs, Carl and Mary Horosz, purchased a home at 19 Stagg Road, Wayne, New Jersey, from defendant Alps Estates, Inc. (“Alps”), a builder-developer. In 1981, the Horoszes experienced problems with the house. In particular, they felt cold air coming into the house from the washroom in the right rear of the dwelling. As a result, the Horoszes contacted Jacob Kurzer, a representative of Alps.

*127 Alps began repair work on the house in October 1982. Thomas E. Tully, a “soil engineer,” performed “test borings” of the soil underneath the right rear of the house. Tully discovered that that section of the house had been constructed on fill, thereby causing the house to sink. To prevent the house from sinking further, Alps inserted concrete and steel in the ground under that part of the house and replaced the foundation. Alps did not insert concrete and steel under the entire house. The Horoszes claim that they asked Alps to underpin the entire house but that Alps assured them that shoring up the fill under part of the house was sufficient to prevent continued sinkage. Alps completed that “underpinning” process on January 26,1983, and all related work by April 25, 1983, and did not charge the Horoszes for the work.

The Horoszes and Alps did not communicate further until January 1989 when the Horoszes once again felt cold air blowing through the house. Mrs. Horosz discovered that the wind was coming from a bedroom window that would not close because one side of the window frame tilted below the other. Mrs. Horosz also noticed that the garage doors were not properly aligned and that the floors in two of the bedrooms slanted downward from right to left.

The Horoszes again communicated with Jacob Kurzer, the Alps representative, and he examined the premises on May 3, 1989. According to the Horoszes, Kurzer promised to have the house inspected and to provide a report within two weeks. Alps, however, did nothing further.

The house continued to deteriorate. The Horoszes hired a company to jack-up the house and to excavate to determine the source of the problem. The excavation revealed that the source of the sinkage was fill under the foundation. The excavators discovered the fill a few feet away from the spot at which Alps had stopped its work in April 1983.

The Horoszes initiated this lawsuit on September 28, 1989, alleging that Alps had negligently repaired the house in 1983, knowingly concealed a material fact, violated the Consumer Fraud *128 Act, and had breached express and implied warranties. Alps’ answer included a defense based on N.J.S.A 2A:14-1.1, the ten-year statute of repose.

Prior to trial, the trial court, after a hearing on the applicability of N.J.S.A 2A:14-1.1, ruled that the statute applied and that the ten years had begun to run when title passed from Alps to the Horozes in 1977. The trial court therefore dismissed the complaint.

On the Horoszes’ appeal, the Appellate Division reversed and remanded the case for trial. 266 N.J.Super. 382, 629 A.2d 1350 (1993). The Appellate Division agreed with the trial court that the statute of repose applied. However, it concluded that because the defect had arisen from the 1983 repair work and not from the original construction completed in 1977, the statute had started to run in April 1983 at the conclusion of Alps’s repairs. Id. at 385, 629 A.2d 1350. We granted defendants’ petition for certification, 134 N.J. 565, 636 A.2d 522 (1993), and now affirm.

II

As the trial court and the Appellate Division held, N.J.S.A 2A:14-1.1, the ten-year statute of repose, applies. N.J.S.A 2A:14-1 was enacted in 1967, L.1967, c. 59, ¶ 1, and is similar to legislation enacted in thirty other states. See Newark Beth Israel Hosp. v. Gruzen, 124 N.J. 357, 362, 590 A.2d 1171 (1991). The purpose of the statute of repose was to limit the expanding liability of contractors, builders, planners, and designers, see id. at 362, 590 A.2d 1171 (stating, “we have concluded that the Legislature enacted the statute in response to the expanding application of the ‘discovery rule’ ..., the abandonment of the ‘completed and accepted rule’ ..., and the expansion of strict liability in tort for personal injuries caused by defects in new homes to builder/sellers of those homes”); see also E.A. Williams, Inc. v. Russo Dev. Corp., 82 N.J. 160, 164-65, 411 A.2d 697 (1980) (discussing history and purpose of statute); O’Connor v. Altus, 67 N.J. 106, 117, 335 A.2d 545 (1975) (same); Rosenberg v. Town of N. Bergen, 61 N.J. *129 190, 195-98, 293 A.2d 662 (1972) (same). Based on that legislative purpose, we have tended to read the statute broadly. See, e.g., Newark Beth Israel Hosp., supra, 124 N.J. at 363, 590 A.2d 1171; Rosenberg, supra, 61 N.J. at 198, 293 A.2d 662.

N.J.S.A. 2A: 14-1.1 provides:

No action whether in contract, in tort, or otherwise to recover damages for any deficiency in the design, planning, supervision or construction of an improvement to real property, or for an injury to property, real or personal, or for an injury to the person, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribution or indemnity for damages sustained on account of such injury, shall be brought against any person performing or furnishing the design, planning, supervision of construction or construction of such improvement to real property, more than 10 years after the performance or furnishing of such services and construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Elizabeth v. Reinforced Earth Co.
New Jersey Superior Court App Division, 2024
Donald D. McDermid v. 3m Company
New Jersey Superior Court App Division, 2024
State v. Perini Corporation (070558)
113 A.3d 1199 (Supreme Court of New Jersey, 2015)
Joseph Cherilus v. Federal Express
87 A.3d 269 (New Jersey Superior Court App Division, 2014)
State v. Perini Corp.
39 A.3d 918 (New Jersey Superior Court App Division, 2012)
Port Imperial v. Hovnanian Port
17 A.3d 283 (New Jersey Superior Court App Division, 2011)
Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Dziewiecki v. Bakula
824 A.2d 241 (New Jersey Superior Court App Division, 2003)
Diana v. Russo Development Corp.
799 A.2d 689 (New Jersey Superior Court App Division, 2002)
Ebert v. South Jersey Gas Co.
723 A.2d 599 (Supreme Court of New Jersey, 1999)
Ebert v. South Jersey Gas Co.
704 A.2d 579 (New Jersey Superior Court App Division, 1998)
Gordon v. Western Steel Co.
950 S.W.2d 743 (Court of Appeals of Texas, 1997)
Russo Farms, Inc. v. Vineland Board of Education
675 A.2d 1077 (Supreme Court of New Jersey, 1996)
Russo Farms, Inc. v. Vineland Board of Education
655 A.2d 447 (New Jersey Superior Court App Division, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
642 A.2d 384, 136 N.J. 124, 1994 N.J. LEXIS 494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horosz-v-alps-estates-inc-nj-1994.