Opinion

Holmes, J.

This litigation arose out of contracts awarded by. the State Building Commission of the State of Mississippi.to Arthur Horne, d/b/a Horne Plumbing, Electric and Supply Company, in.connection with the construction of’the State Office Building and the Mississippi Schools, for the Blind and Deaf.

On January 16, 1948, the State Building Commission awarded to Arthur Horne, d/b/a Horne Plumbing, Electric and Supply Company, a contract for the electrical work in connection with the construction of the-State Office Building. The contract price was $257,456.00. Horne furnished a performance bond, dated January 21, 1948, in the amount of the contract with Western Casualty and Surety Company as surety. • ......

On May 8,1948, the State Building Commission awarded to Arthur Horne, d/b/a Horne Plumbing, Electric and Supply Company, a contract for the mechanical work, consisting of plumbing and heating, in connection with the construction of the Mississippi Schools for the Blind and Deaf. The contract price was $279,051.00. Horne furnished a performance bond for this job, dated May 8, 1948, in the amount of the contract with the same surety, Western Casualty and Surety Company.

In each instance, Horne executed to the surety a written application for the performance bond. The applications and the bonds were of like tenor and effect, except as to the amount and the work to be performed. The application for the bond on the State Office Building job was dated January 21, 1948. The application for the bond on the Schools for the Blind and Deaf job was dated May 8, 1948. The applications contained the following pertinent provisions:

(a) The principal ¿greed to indemnify the surety against all loss, costs, damages, expenses and attorneys’ *814 fees, and against any and all liability sustained or incurred by the surety by reason of the execution of the bonds.

(b) The surety was to have the right and was authorized but not required to take possession of the work in case of default and to complete the same at the expense of the principal, or to contract for the completion of the same, or to consent to the reletting or completion of the contract by the obligee, and the surety was also given the right to adjust, settle, or compromise any claim or demand.

(c) The principal agreed to assign, and did assign, transfer and set over to the surety as collateral to secure the obligations of the bond, and any other indebtedness or liability of the principal to the surety, with said assignment to become effective as of the date of the contract, and, in the event of any abandonment, forfeiture, or breach of said contract, or of any breach of any bonds executed on behalf of the principal, or in the event of any proceeding which deprived the principal of the right to proceed with the contract, the assignment was then made to cover all rights of the principal in and growing out of the contract and any and all percentages retained on account of the contract, and any and all sums due under the contract at the time of abandonment, forfeiture, or breach, or might thereafter become due.

(d) It was provided that the liability of the principal should include all sums paid by the company on good faith under the belief that it was liable therefor whether liable or not.

(e) It was provided that in the event of such payment in good faith, an itemized statement thereof sworn to by any officer of the surety, or the voucher or vouchers of other evidences of such payment should be prima facie evidence of the fact of payment and the extent of the principal’s liability.

The following provisions are quoted verbatim from the applications:

*815 ‘ ‘ That liability hereunder shall extend to, and include, the full amount of any and all sums paid by the company in settlement or compromise of any claims, demands, suits, and judgments upon said bond or bonds, or any of them, on good faith, under the belief that it was liable therefor whether liable or not, as well as any and all disbursements on account of costs, expenses, attorneys’ fee, as aforesaid, which may be made under the belief that such were necessary whether necessary or not.”
“That in the event of payment, settlement or compromise, in good faith of liability, loss, costs, damages, expenses and attorneys fees, claims, demands, suits and judgments as aforesaid, an itemized statement thereof, sworn to by any officer of the company, or the voucher or vouchers or other evidence of such payment, settlement or compromise shall be prima facie evidence of the fact and extent of the liability of the undersigned, in any claim or suit hereunder, and in any and all matters arising between the undersigned and the company.....”

The State Office Building job was completed according to contract and accepted by the State Building Commission on August 30, 1950, at which time there were retainage funds in the hands of the State Building Commission amounting to $43,812.36.

The general contractor on the project for the construction of the Schools for the Blind and Deaf was M. T. Reed Construction Company. Horne and the general contractor began work on this project under their respective contracts. The general contractor completed his work on or about February 2, 1950, at which time the Commission entered an order reciting the completion of the work of the g'eneral contractor, and setting forth that Horne should complete his work within ten days as provided by the contract. At a meeting of the Commission held on February 15, 1950, the architects on the project for the construction of the Schools for the Blind and Deaf presented to the Commission their certificates certifying *816 that Horne had failed to supply enough skilled workmen and proper materials to complete his contract within the required time and had failed to comply with certain other provisions of his contract, and recommending that for these failures and his persistent disregard of the instructions of the architects, he be declared in default under this contract.

The Commission entered an order accordingly, and then by subsequent order entered on February 20, 1950, granted Horne thirty days from February 20, 1950 to substantially comply with his contract provided he made satisfactory day to day progress. On March 7, 1950, the Commission entered an order declaring Horne in default for .unsatisfactory day to day progress, and for failure to comply with his contract, and terminating his contract, and calling upon the surety to perform the obligations of its bond. Horne demanded an arbitration in accordance with the terms of the contract and the same was had and resulted in an award in favor of the State Building Commission on April 24,1950, finding that there was sufficient cause to warrant the Commission in declaring Horne in default and in terminating his contract. The award was filed in the circuit court and the cause involving the arbitration proceedings was later transferred to the chancery court, where it was numbered Cause No. 40,802 on the docket of that court. The chancellor confirmed the award and on appeal to the Supreme Court, the action of the chancellor was affirmed. Horne v. State Building Commission, 220 Miss. 520, 76 So. 2d 356.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marshall Fisher v. Michael Drankus
204 So. 3d 1232 (Mississippi Supreme Court, 2016)
Arvin D. Rochell v. State of Mississippi
212 So. 3d 772 (Mississippi Supreme Court, 2016)
City of Belmont v. Miss. State Tax Comm'n
860 So. 2d 289 (Mississippi Supreme Court, 2003)
Stokes v. Kemper County Bd. of Sup'rs
691 So. 2d 391 (Mississippi Supreme Court, 1997)
James C. Stokes v. Kemper Cnty Bd of Suprvs
Mississippi Supreme Court, 1994
Presley v. Mississippi State Hwy. Com'n
608 So. 2d 1288 (Mississippi Supreme Court, 1992)
Exxon Corp. v. Crosby-Mississippi Resources, Ltd.
775 F. Supp. 969 (S.D. Mississippi, 1991)
Grantham v. Dept. of Corrections
522 So. 2d 219 (Mississippi Supreme Court, 1988)
State Ex Rel. Pittman v. Ladner
512 So. 2d 1271 (Mississippi Supreme Court, 1987)
Tradigrain, Inc. v. Mississippi State Port Authority
701 F.2d 1131 (Fifth Circuit, 1983)
Pruett v. City of Rosedale
421 So. 2d 1046 (Mississippi Supreme Court, 1982)
Anderson v. Jackson Mun. Airport Auth.
419 So. 2d 1010 (Mississippi Supreme Court, 1982)
Cig Contractors, Inc. v. MISS. STATE BLDG. COM'N
399 So. 2d 1352 (Mississippi Supreme Court, 1981)
Burton v. Waller
502 F.2d 1261 (Fifth Circuit, 1974)
Travelers Indemnity Co. v. Clark
254 So. 2d 741 (Mississippi Supreme Court, 1971)
Lowndes County, Dist. 5 v. MISSISSIPPI STATE HY. COM'N
220 So. 2d 349 (Mississippi Supreme Court, 1969)
Mladinich v. Kohn
186 So. 2d 481 (Mississippi Supreme Court, 1966)
Peerless Insurance Co. v. Cerny & Associates, Inc.
199 F. Supp. 951 (D. Minnesota, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
103 So. 2d 373, 233 Miss. 810, 1958 Miss. LEXIS 444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horne-v-state-building-commission-miss-1958.