Horne v. State Building Commission

76 So. 2d 356, 222 Miss. 520, 1954 Miss. LEXIS 675
CourtMississippi Supreme Court
DecidedDecember 20, 1954
Docket39373
StatusPublished
Cited by16 cases

This text of 76 So. 2d 356 (Horne v. State Building Commission) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horne v. State Building Commission, 76 So. 2d 356, 222 Miss. 520, 1954 Miss. LEXIS 675 (Mich. 1954).

Opinion

*524 Hall, J.

Appellant had a written contract with the State Building Commission for doing the mechanical work in connection with the installation of plumbing and heating in the several buildings of the Mississippi Schools for the Deaf and Blind. In the latter part of 1949 the general *525 contractor had almost completed his work and the architect discovered that the appellant was so far behind with his contract that it would be practically impossible for him to complete it within the time allowed him under the contract. This situation was reported to the State Building Commission in February 1950 and the Commission first determined to cancel the contract in accordance with its terms, but upon assurances from the appellant deferred the matter of cancellation until March 1950, when the architect finally determined and reported to the Commission that appellant was hopelessly in default. Thereupon the Commission declared the contract terminated and called upon appellant’s surety to complete it. Appellant demanded an arbitration in accordance with the terms of the contract. An arbitrator was selected by each party and the two thus chosen selected a third arbitrator. These three were organized into a board of arbitration and conducted a lengthy hearing and after conclusion of evidence taken over a period of about ten days and after having inspected the buildings in question, made a general award in favor of the State Building Commission and found that sufficient cause existed for the issuance of the architect’s certificate for termination of the contract. This award was dated April 24, 1950. The award was subsequently filed in the circuit court and on May 2, 1950, the appellee made a motion to confirm the same. After due notice appellant appeared and filed a motion to transfer the case to the chancery court, where the appellant filed an independent suit for balance due him under his contract and also for balance due under a contract for the electrical work on the State Office Building. On request of appellee the circuit court deferred its action on the motion to transfer the award proceedings to the chancery court, but later on June 3, 1950, entered an order transferring the case to the chancery court; after which the appellant filed a motion to vacate the award of the arbitrators and the appellee filed an amended motion to confirm the arbitration award. *526 The causes were finally consolidated and numerous amendments and other pleadings were filed, which it is not necessary to detail. The1 matter was referred to a special master who finally rendered an opinion on June 3, 1952, to the effect that the award of the arbitrators was incomplete. Objections were made to the master’s report and exceptions taken thereto and finally the court rendered its opinion on April 1, 1953, pursuant to which the master’s report was set aside, the motion to confirm the award was overruled, and the matter was referred back to the board of arbitration for further consideration and findings. The board of arbitration met pursuant to the order of the court, and, instead of the one general finding, the board made fifteen specific findings, all of which were in favor of the Building Commission and all of which were substantially covered by the single finding made in the original award. The board of arbitration called this a supplemental award and did not take any additional evidence prior to making the same. On July 31, 1953, appellant filed a motion to vacate the award and the court on that date entered a decree confirming both awards, from which this appeal is taken.

Appellant’s principal contentions are that the original award was invalid because of its incompleteness and that the supplemental award was invalid because not made within time specified in the original articles of submission. We think that a determination of the first question will be decisive of all points raised. There is no contention against anything in connection with the original arbitration except that the finding of the board of arbitration is so incomplete as to render it invalid. On March 7, 1950, the architect issued his certificate of appellant’s default on his contract, this certificate being-in accordance with the original contract, and within a few days thereafter the appellee entered an order upon its minutes terminating the contract pursuant to the authority of the architect’s certificate. Appellee demand *527 ed arbitration. After laborious work extending over a period of approximately two weeks the board of arbitration made its award which is, in part, as follows: “We, the Board of Arbitration, find for the defendant and find that sufficient cause did exist for the issuance of the Architect’s certificate of March 7, 1950, above mentioned, and assess all costs of this proceeding against the plaintiff, Arthur Horne.”

Section 297, Code of 1942, provides that the provisions in the chapter on arbitration and award shall be construed liberally. To the same effect is Stout v. W. M. Garrard & Co., 128 Miss. 418, 91 So. 33.

Appellant contends that the general award above quoted is incomplete because he claimed the right to have a specific finding by the arbitrators on fifteen different questions which were eventually specifically found adversely to him in the supplemental award, but the trouble with appellant’s contention is that the general award necessarily constituted a denial of appellant’s claim under the so-called fifteen points.

The award necessarily adjudicated the following facts contained in the architect’s certificate of March 7, 1950, as being correct: (1) that the contractor, Horne, had failed to furnish a sufficient number of skilled workmen and proper materials; (2) that he had persistently disregarded the instructions of the architect; (3) that he cannot complete his work satisfactorily and in accordance with the specifications; (4) that sufficient cause exists to justify the building commission in terminating Horne’s contract; (5) that Horne’s day to day progress on the job is not satisfactory and is not in keeping with the commission’s order of February 20, 1950, which, in effect, had put Horne on a probationary period before termination of his contract; (6) and that the commission should exercise its right to terminate the contract and call on the surety on Horne’s performance bond to complete the work.

*528 Unless the statute or the articles of submission to arbitration require separate findings on each matter considered, it is not necessary for the award to enumerate each matter considered or to make special findings of fact or law. Idaho Dredging Corporation v. Boise, etc., 49 Idaho 303, 288 P. 641; Podolsky v. Raskin, 294 Ill. 443, 128 N. E. 534. The original award in this case was definitely in favor of appellee and although no special findings were made other than we have stated, the general tenor of the award was that appellant was not entitled to any relief on any of the points urged by him. As to the sufficiency of the original award we quote from Leavenworth & Son, Inc. v. Kimble, 157 Miss. 462, 128 So. 354, as follows:

“It is the settled general rule that ‘it is essential to the validity of an award that it shall be final and complete, responsive to all the matters of difference included in the submission.’ Rhodes v. Hardy, 53 Miss. 592.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BC Rogers Poultry, Inc. v. Wedgeworth
911 So. 2d 483 (Mississippi Supreme Court, 2005)
Margerum v. Bud's Mobile Homes, Inc.
823 So. 2d 1167 (Mississippi Supreme Court, 2002)
INGRASSIA CONST. CO. v. Vernon Tp. Bd. of Educ.
784 A.2d 73 (New Jersey Superior Court App Division, 2001)
Robert Margerum v. Bud's Mobile Homes, Inc.
Mississippi Supreme Court, 2001
Americrete, Inc. v. West Alabama Lime Co.
758 So. 2d 415 (Mississippi Supreme Court, 2000)
B. C. Rogers Poultry, Inc. v. Tommy Wedgeworth
Mississippi Supreme Court, 2000
IP TIMBERLANDS OPERATING CO. LTD. v. Denmiss
726 So. 2d 96 (Mississippi Supreme Court, 1998)
IP Timberlands Oper Co Ltd v. Denmiss Corp
Mississippi Supreme Court, 1996
James Reeves Contractor, Inc. v. United States
39 Cont. Cas. Fed. 76,694 (Federal Claims, 1994)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Craig v. Barber
524 So. 2d 974 (Mississippi Supreme Court, 1988)
Horne v. State Building Commission
103 So. 2d 373 (Mississippi Supreme Court, 1958)
Fidelity & Casualty Co. v. State Building Commission
87 So. 2d 449 (Mississippi Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
76 So. 2d 356, 222 Miss. 520, 1954 Miss. LEXIS 675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horne-v-state-building-commission-miss-1954.