Hope Electric Enterprises, Inc. v. Schindler Elevator Corporation

CourtCourt of Appeals of Georgia
DecidedNovember 19, 2013
DocketA13A1586
StatusPublished

This text of Hope Electric Enterprises, Inc. v. Schindler Elevator Corporation (Hope Electric Enterprises, Inc. v. Schindler Elevator Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hope Electric Enterprises, Inc. v. Schindler Elevator Corporation, (Ga. Ct. App. 2013).

Opinion

THIRD DIVISION ANDREWS, P. J., DILLARD and MCMILLIAN, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

November 19, 2013

In the Court of Appeals of Georgia A13A1586. HOPE ELECTRIC ENTERPRISES, INC. v. SCHINDLER ELEVATOR CORP.

MCMILLIAN, Judge.

Plaintiff/appellant Hope Electric Enterprises, Inc. (“Hope Electric”) appeals

from the trial court’s order granting partial summary judgment to defendant/appellee

Schindler Elevator Corporation (“Schindler”) on Hope Electric’s claim for wrongful

termination of the parties’ contract. For the reasons set forth below, we now reverse.

The record shows that in October 2007, Schindler entered into a contract with

the Metropolitan Atlanta Rapid Transit Authority (“MARTA”) to act as the general

contractor on a project to rehabilitate escalators in MARTA stations throughout the

Atlanta area (the “Prime Contract”). In June 2008, Schindler subcontracted with Hope Electric to perform certain electrical work for a portion of the project (“Subcontract”),

and Hope Electric began working on the project later that year.

Hope Electric apparently worked on the project without any documented

incidents until April 2010. On April 16, 2010, MARTA issued a Construction Safety

Inspection Report citing Hope Electric for leaving an electrical closet door open on

a train platform (“Violation 1”). According to the report of Violation 1, there were

“no men [Hope personnel] at location” and the corrective action taken at that time

included providing the “Station Manager” safety cones to protect the wires on the

floor and barricades to protect the doorway. Further, the report indicated that verbal

instructions were given not to leave the door open. And, according to a letter sent to

Hope Electric on August 27, 2010, Schindler’s safety officer at the site conducted a

safety review following the violation.

A few weeks later, on April 28, 2010, MARTA cited Hope Electric for

removing a breaker from a live breaker panel without any MARTA personnel present

(“Violation 2”). According to the report of Violation 2, Hope Electric was

reprimanded at a progress meeting for this violation.

On August 9, 2010, a MARTA train operator whose train was stopped in the

Georgia State station observed Hope Electric principal, Willie Hope Jr., and another

2 Hope Electric employee, James Reid, crossing “live” MARTA train tracks during

normal operating hours (“Wayside Violation”). The report of the Wayside Violation

also indicates that Willie Hope did not have proper MARTA identification on his

person and that he became belligerent when questioned by MARTA police who came

to the site. Willie Hope admitted in a meeting later that day with MARTA personnel

and Mark Lester, Schindler’s project manager, that his access to this live track area

was unauthorized, but refused to acknowledge that he had committed a safety

violation.

During the meeting, MARTA revoked Hope Electric’s access to the project

sites and Schindler directed Hope Electric to cease all further work on the project

until MARTA concluded its investigation. On August 27, 2010, Schindler sent a letter

to Hope Electric stating that Schindler had discovered that electrical components at

the Georgia Dome Station were falling off the wall, apparently because they were not

properly anchored. The letter also stated that this violation had been discovered since

the Wayside Violation and referenced the other violations. The letter further notified

Hope Electric that “[t]hese repeated problems are unacceptable” and directed that it

repair the Georgia Dome Station problems. However, the letter also reiterated that

Hope Electric could not perform any work on the project, including repairing the

3 Georgia Dome Station components, until MARTA completed its investigation and

determined the “required corrective action” for the Wayside Violation.

On August 30, 2010, MARTA sent a letter to Lester directing Schindler to

immediately remove Hope Electric from the project based on the “severity of th[e]

recent [Wayside] infraction, coupled with the previous incidents[.]” On September

10, 2010, Schindler provided Hope Electric a copy of the August 30 MARTA letter.

On September 20, 2010, Schindler sent a letter notifying Hope Electric of the

immediate termination of the Subcontract. The letter also stated that Schindler had

“no choice” but to terminate the Subcontract based on MARTA’s August 30 letter.

Hope Electric subsequently filed a complaint against Schindler, alleging

Schindler breached the Subcontract by, among other things, wrongfully terminating

the Subcontract. Schindler moved for partial summary judgment on this claim, and

the trial court granted Schindler’s motion. Hope Electric timely filed the present

appeal challenging that order. We agree with Hope Electric that the trial court erred

by granting summary judgment to Schindler on the wrongful termination claim.

4 1. We turn first to the provisions of the Prime Contract and Subcontract which

are relevant to our analysis.1 The primary provision of the Subcontract at issue here

is Section 7.2.1, which provides as follows:

If the Subcontractor repeatedly fails or neglects to carry out the Work in accordance with the Subcontract Documents or otherwise to perform in accordance with this Subcontract and fails within a ten-day period after receipt of written notice to commence and continue correction of such default or neglect with diligence and promptness, the Contractor may, by written notice to the Subcontractor and without prejudice to any other remedy the Contractor may have, terminate the Subcontract and finish the Subcontractor’s Work by whatever method the Contractor may deem expedient. . . .”

And Hope Electric had a specific duty to perform its work safely under Section 4.3.1

of the Subcontract.2

Schindler argues that these provisions authorized the termination of the

Subcontract based on the “overwhelming evidence of four safety violations in five

1 The provisions of the Prime Contract were made part of the Subcontract in Article 1, § 1.1 of the Subcontract. 2 That section provided that Hope Electric “shall take reasonable safety precautions with respect to performance of this Subcontract, shall comply with safety measures initiated by the Contractor and with applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities for the safety of persons and property in accordance with the requirements of the Prime Contract.”

5 months time,” including the “very serious Wayside Violation.”3 On the other hand,

Hope Electric argues that a jury must decide whether it “repeatedly fail[ed] or

neglect[ed] to carry out the Work in accordance with the Subcontract[;]” whether it

“fail[ed] within a ten-day period after receipt of written notice to commence and

continue correction of such default or neglect with diligence and promptness[;]” and

whether its denial of access to the project site prevented it from taking any action to

address the alleged deficiencies in its work. We agree with Hope Electric that a jury

must decide these issues.

We start with the pivotal issue, which is whether Hope Electric “repeatedly”

failed or neglected to carry out the work or perform in accordance with the

Subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Kaminsky
610 S.E.2d 542 (Court of Appeals of Georgia, 2004)
McGuire Holdings, LLLP v. TSQ Partners, LLC
660 S.E.2d 397 (Court of Appeals of Georgia, 2008)
Archer Western Contractors, Ltd. v. Estate of Pitts
735 S.E.2d 772 (Supreme Court of Georgia, 2012)
Georgia-Pacific, LLC v. Fields
748 S.E.2d 407 (Supreme Court of Georgia, 2013)
Harkins v. CA 14th Investors, Ltd.
544 S.E.2d 744 (Court of Appeals of Georgia, 2001)
Freund v. Warren
740 S.E.2d 727 (Court of Appeals of Georgia, 2013)
Anderson v. Jones
745 S.E.2d 787 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Hope Electric Enterprises, Inc. v. Schindler Elevator Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hope-electric-enterprises-inc-v-schindler-elevator-corporation-gactapp-2013.