Hongkong & Whampoa Dock Co. v. United States

50 Ct. Cl. 213, 1915 U.S. Ct. Cl. LEXIS 89, 1915 WL 1085
CourtUnited States Court of Claims
DecidedApril 12, 1915
DocketNo. 31522
StatusPublished
Cited by6 cases

This text of 50 Ct. Cl. 213 (Hongkong & Whampoa Dock Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hongkong & Whampoa Dock Co. v. United States, 50 Ct. Cl. 213, 1915 U.S. Ct. Cl. LEXIS 89, 1915 WL 1085 (cc 1915).

Opinions

Campbell, Chief Justice,

reviewing the facts found to be established, delivered the opinion of the court:

The plaintiff had two contracts with the defendants, one dated June 24, 1909, and the other dated June 30, 1909, and [219]*219both of them providing for the construction and delivery of boats known as lorchas. The first contract was for six steel lorchas and the second contract was for four wooden lorchas. The deliveries were to be made to the chief quartermaster, Philippine Division, in Manila Bay, and the dates of the contemplated deliveries were mentioned in tbe contracts. One of the steel lorchas was delivered ahead of time and three of the wooden lorchas were delivered ahead of time. Two of the lorchas, one of steel due to be delivered December 4 and one of wood due to be delivered November 19, were started from Hongkong in time to have reached their destination within the period fixed for their delivery, but were lost at sea and were subsequently replaced by the claimant. All the others were delayed beyond the contract time. The delay in the delivery of three of them was excused in the auditing department upon the ground that the delay was occasioned by the act of God, which, under the provisions of the contract, was made an exception to the plaintiff’s obligation to deliver within the stipulated time.

For the delay in making delivery of two of the steel and one of the wooden lorchas there was deducted from the amount due the plaintiff the sum of $5,480 under the provisions of the second paragraph of the contracts, and to recover said sum this suit was brought. These three lorchas, numbered, respectively, 460, 461, and 468, were deliverable under paragraph 4 of the contracts as follows: No. 460 on or before December 18, 1909; 461 on or before January 1, 1910; and 468 on or before December 14, 1909. No. 460 was 72 days late in delivery, 481 was 77 days late, and 468 was 125 days late in delivery, making an aggregate of 274 days delay, for which plaintiff was charged $20 per day as liquidated damages.

The proof shows that all of these boats were completed in time to have been delivered sooner than the dates fixed for their delivery, two of them having been completed early in November, and the third, finished on December 3, 1909, was practically completed sooner.

The evidence shows that generally during the months of October and November small craft can be towed across the [220]*220China Sea safely, but that during said months in 1909 the conditions prevailing on that sea were abnormal and typhoons occurred with unusual frequency. As above stated, two of the lorchas were lost in the effort to cross in November. It was because of this abnormal and dangerous condition that plaintiff was excused for its failure to deliver the lorchas due in November.

According to the record in this case the northeast monsoon generally sets in over the China Sea about December 1 and lasts until April or May, when the southwest monsoon begins; the latter does not bring wind or produce stormy weather on said sea, but during the northeast monsoon light-erage or towages can only be done at great risk and danger to the craft being towed. Safe towage can usually be relied upon during typhoon weather — from April to December— because, as we are told, while there are occasional bursts of very stormy weather during that period they are succeeded by long intervals of fine weather, with calm sea, which makes towage safe.

The plaintiff insists that the contracts do not authorize the deduction of liquidated damages for delay in delivering the said lorchas, but confine the liquidated damages to delay in their completion, and refers to the several paragraphs of each of the contracts as sustaining this contention because, it is insisted, that while article 2 mentions a failure “ to complete in all respects the lorchas called for under this agreement on or before the dates stipulated for such completion ” and fixes the damages at $20 per day for each day that “ each lorcha remains uncompleted after such dates,” there is no mention in specific terms of delay in delivery.

Unquestionably the' whole contract, and not segregated portions of it, must be examined when construction of it is resorted to. “ The elementary canon of interpretation is not that particular words may be isolatedly considered, but that the whole contract must be brought into view' and interpreted with reference to the nature of the obligations between the parties and the intention which they may have manifested in forming them.” O'Brien v. Miller, 168 U. S., 287, 296; Boardman v. Lessees, 6 Pet., 318, 345. The under[221]*221taking of the plaintiff was to furnish the labor and material necessary to construct and to “ construct and deliver complete in every detail” certain lorchas to the chief quartermaster at Manila for a specified consideration. These things were to be done in accordance with the plans and specification and “ Instructions to bidders ” attached to and made a part of the contract. Among others, said instructions required the bidders to state when the work would begin and when it would be completed. The contracts (par. 4) refer to the dates on or before which the lorchas are severally to be delivered and the final delivery made, and do not mention “ the dates stipulated for such completion,” if completion is to be confined to something short of actual delivery. It is hence argued for defendants that the failure “ to complete in all respects the lorchas ” for which liquidated damages are agreed upon means a failure to deliver complete in all respects the said lorchas, and further that the defendants were not concerned with the times of completion of construction, but were interested in the completion of delivery. The latter phase of this contention can not be supported under the facts of the case. The instructions to bidders, made part of the contract, required them- to “ state the time in which they will complete each vessel from the date of commencement of work,” and we think it is a fair assumption that the purpose of this requirement was to inform defendants’ representatives of the times which the several bidders would take to complete the work so that some regard could be had to the .times of delivery; that is, whether the lorchas would be completed so as to be deliverable within the period of the year when the China Sea would admit of delivery without too great risk of loss. It may reasonably be presumed that the Government’s agents had notice of the conditions which usually prevailed during the monsoons and their general effect upon towages over the China Sea. It was, we think, because of these well-known conditions that the Government’s representatives in their instructions spoke of the times of completion, and provided in their draft of the contracts for delivery “on or before” the several dates fixed therefor. They probably considered that if the [222]*222lorchas were completed in construction the certainty of delivery during October or November would be enhanced and that if the lorchas were not completed until after November there would be uncertainty as to when, in the usual conditions prevailing over the China Sea, delivery could be had.

The other phase of the contention is more difficult of solution. There is much force in the defendants’ argument that the provisions of paragraph 2 are to be interpreted in the light of the remainder of the contract and the intention shown thereby of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Padilla v. United States
58 Fed. Cl. 585 (Federal Claims, 2003)
Global Van Lines, Inc. v. United States
177 Ct. Cl. 829 (Court of Claims, 1966)
K E C O Industries, Inc. v. The United States
364 F.2d 838 (Court of Claims, 1966)
Jefferson Construction Co. v. United States
151 Ct. Cl. 75 (Court of Claims, 1960)
Breese Burners, Inc. v. United States
121 F. Supp. 530 (Court of Claims, 1954)
Hotpoint Inc. v. United States
117 F. Supp. 572 (Court of Claims, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
50 Ct. Cl. 213, 1915 U.S. Ct. Cl. LEXIS 89, 1915 WL 1085, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hongkong-whampoa-dock-co-v-united-states-cc-1915.