Honess 52 Corp. v. Widholt

176 Misc. 2d 57, 672 N.Y.S.2d 237, 1998 N.Y. Misc. LEXIS 86
CourtNew York Supreme Court
DecidedMarch 11, 1998
StatusPublished
Cited by3 cases

This text of 176 Misc. 2d 57 (Honess 52 Corp. v. Widholt) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honess 52 Corp. v. Widholt, 176 Misc. 2d 57, 672 N.Y.S.2d 237, 1998 N.Y. Misc. LEXIS 86 (N.Y. Super. Ct. 1998).

Opinion

OPINION OF THE COURT

Judith A. Hillery, J.

Petitioner, Honess 52 Corp., commenced this CPLR article 78 proceeding to obtain an order directing respondent, Eloise Widholt, the Town Clerk of the Town of Fishkill, to issue petitioner a certificate for default approval of petitioner’s preliminary plat pursuant to Town Law § 276 (8) due to respondent Planning Board of the Town of Fishkill’s failure to act on petitioner’s application within 62 days following the closing of the public hearing on that application. Respondents now move to dismiss the complaint pursuant to CPLR 7804 (f) on the grounds that petitioner’s application for subdivision approval is subject to review under the State Environmental Quality Review Act (ECL art 8 [SEQRA]) and, because no SEQRA review has occurred at this time, petitioner’s application is incomplete and it may, therefore, not obtain approval by default under Town Law § 276 (8).

In response to the motion, petitioner primarily relies on Town Law § 276 (5) (d) and (4) and argues that respondents deemed its application for preliminary subdivision approval complete by scheduling a public hearing. Petitioner also relies upon the Court of Appeals decision in King v Chmielewski (76 NY2d 182) and Town Law § 276 (8), for the proposition that respondent Planning Board’s failure to render a decision within 62 days after the close of that public hearing entitles it to a default approval of its preliminary subdivision application. Petitioner takes issue with respondents’ claim that its application is subject to SEQRA requirements. According to petitioner, its application is exempt or excluded from SEQRA review pursuant to ECL 8-0111 (5) and 6 NYCRR 617.5 (c) (34) because it was approved prior to the effective date of SEQRA, and/or pursuant to 6 NYCRR 617.5 (c) (37) because development of the property at issue had been mandated by prior judicial order. Finally, petitioner argues that even if its project is not exempt [59]*59or excluded from the requirements of SEQRA, a final environmental impact statement (hereinafter EIS), which was previously prepared and adopted by respondent Planning Board in 1990, identified all potentially significant environmental impacts on the property of a much larger proposed development and that that EIS is sufficient to grant site plan approval of petitioner’s smaller development proposal without requiring a supplemental or new EIS for petitioner’s proposal.

In reply, respondents challenge petitioner’s argument that its application was exempt or excluded from SEQRA review based on a purported approval of that application prior to the enactment of SEQRA or the purported mandate to that effect contained in a prior judicial order. Respondents reiterate that petitioner’s application for subdivision approval required SE-QRA review and that, notwithstanding their possible premature convening of a public hearing on preliminary approval in order to solicit public comment, the complete lack of SEQRA review for petitioner’s application mandates a denial of its petition for default approval under Town Law § 276 (8) because SEQRA review is a condition precedent to default approval under that section. Respondents also argue that the EIS, which was prepared in 1990, addressed the environmental impacts of an entirely different project whose preliminary approval had long ago expired and is not sufficient to address the environmental impacts of petitioner’s application as required by SE-QRA.

The property which petitioner seeks to develop has been the subject of previous litigation. In 1966, the Town of Fishkill rezoned the property at issue, consisting of 62 acres on Honess Mountain in the Town of Fishkill, to cap its potential residential development to 31 dwelling units. In 1972, an entity known as Green Mountain Estates, Inc., purchased the property and sought to effect a zoning change for the property to accommodate a 500 dwelling unit development. The rezoning request was denied and litigation ensued in which Green Mountain sought to vitiate the 1966 rezoning and acquire judicial approval of its rezoning request.

Green Mountain and the Town of Fishkill ultimately negotiated a stipulation of settlement which established a fixed maximum dwelling count of 337 units on the parcel and defined how a specific project would be approved if and when it was proposed in the future. The stipulation was entered into by Green Mountain and the Town Board of the Town of Fishkill on May 6, 1977, more than four months prior to the effective date of SEQRA.

[60]*60In 1987, Green Mountain conveyed title to the property to an entity known as Ridgeview Associates which applied to respondent Planning Board for site plan approval of a 337-unit condominium project. Thereafter, Ridgeview Associates participated in an extensive review of environmental impacts as required by SEQRA. A positive declaration was issued by respondent Planning Board, thereby requiring the submission of a draft EIS by Ridgeview Associates, a public hearing on the draft EIS, and the preparation of a final EIS which responded to public concerns and comments. Throughout extensive modification, Ridgeview Associates declined to analyze project alternatives which included a reduction of the proposed 337 dwelling unit count in reliance upon the bifurcated scheme established in the 1977 stipulation of settlement.

On May 10, 1989, respondent Planning Board issued a finding statement on the Ridgeview Condominium project as required by SEQRA and final site plan approval was granted on June 28, 1990. This approval was subject to the Town Code requirement for commencement of construction within one year. However, the Town of Fishkill passed immediate legislation which authorized possible extensions of the one-year deadline for site plan approval to a maximum of three years. Thereunder, the maximum life for the Ridgeview Condominium site plan approval was June 28, 1993.

After approval of the final site plan, concerned citizens commenced an article 78 proceeding against the Planning Board to overturn its administrative determinations (see, Matter of Gallagher v Planning Bd., Dutchess County, Hillery, J., index No. 2820/89). Petitioners challenged the legality of this 1977 stipulation of settlement and attacked the adequacy of the Planning Board’s SEQRA review of the Ridgeview Condominium project for the agency’s failure to examine or impose a project alternative involving fewer dwelling units. The Town of Fishkill vigorously defended the agency’s actions in the article 78 proceeding arguing that Ridgeview Condominium was entitled to 337 clustered residential units under the stipulation of settlement and that that entitlement, and that entitlement alone, was exempt from SEQRA review because it resulted from the court mandate contained in the stipulation of settlement.

By decision dated April 17, 1990, this court issued its determination in Matter of Gallagher v Planning Bd. Addressing the Gallagher petitioners’ argument that the Planning Board had failed to comply with SEQRA by considering the reduction in the number of allowable dwelling units, this court stated: [61]*61“Since the town respondents’ approval for Ridgeview Associates to construct 337 dwelling units on the Honess Mountain parcel was exclusively a ministerial act based on the stipulation and did not involve the exercise of discretion as to the number of allowable units, the project is exempt under ECL 8-0105 (subd. 5, par ii); (6 NYCRR 617.2 (q) (1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matter of Lucente v. Terwilliger
144 A.D.3d 1223 (Appellate Division of the Supreme Court of New York, 2016)
New York SMSA Ltd. Partnership v. Town of Clarkstown
99 F. Supp. 2d 381 (S.D. New York, 2000)
Honess 52 Corp. v. Town of Fishkill
266 A.D.2d 510 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
176 Misc. 2d 57, 672 N.Y.S.2d 237, 1998 N.Y. Misc. LEXIS 86, Counsel Stack Legal Research, https://law.counselstack.com/opinion/honess-52-corp-v-widholt-nysupct-1998.