Homsi v. CH Babb Co., Inc.

409 N.E.2d 219, 10 Mass. App. Ct. 474
CourtMassachusetts Appeals Court
DecidedAugust 29, 1980
StatusPublished
Cited by36 cases

This text of 409 N.E.2d 219 (Homsi v. CH Babb Co., Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Homsi v. CH Babb Co., Inc., 409 N.E.2d 219, 10 Mass. App. Ct. 474 (Mass. Ct. App. 1980).

Opinion

Dreben, J.

The plaintiffs agreed to buy an oven for the baking of Arabic bread under a contract which, as amended, provided that an adequate supply of gas would be furnished by the defendant. At the time for delivery of the oven, natural gas was not available, and the plaintiffs asked for a return of the $10,600 they had paid as a down payment on the oven. The defendant refused to return the deposit, and the plaintiffs brought this action for damages, alleging breach of contract, fraud, and unfair and deceptive acts under G. L. c. 93A. The defendant counterclaimed. The plaintiffs’ common law claims were tried to a jury, which awarded the plaintiffs $15,000 and found for the plaintiffs on the defendant’s counterclaim. A judge sitting in the Superior Court by statutory authority found that the defendant had violated c. 93A, § 11, and awarded the plaintiffs counsel fees. The defendant appeals from the judgments entered on the jury verdict and on the findings of the judge, from the denial of its motion for a new trial, and from an order of the judge which amended his findings with respect to the date on which certain events had occurred. We affirm.

We shall first dispose of the defendant’s contentions which relate to the plaintiffs’ common law claims tried to the jury. The defendant alleges error in the judge’s refusal to suspend the trial in order to allow a rebuttal witness to testify. The witness, whose absence was due to a flight delay, presumably would have testified that the oven which was originally intended for the plaintiffs was sold at a loss as a pizza oven. The judge refused the request which was made for the first time on a Monday morning after the conclusion of all the evidence. There was no error. Whether the defendant had been sufficiently diligent or whether for any reason “justice required a postponement” are ordinarily questions for “the presiding judge alone” and will not be disturbed in the absence of a showing of an abuse of discretion or arbitrariness. *476 Noble v. Mead-Morrison Mfg. Co., 237 Mass. 5, 16 (1921). Morgan v. Steele, 242 Mass. 217, 218 (1922). There was no such showing here. Moreover, evidence of the defendant’s loss on the oven had been presented previously, and the judge could well have determined the evidence to be merely cumulative. Cf. Bendett v. Bendett, 315 Mass. 59, 65-66 (1943).

The defendant also argues that there was insufficient evidence for the jury to award the plaintiffs damages in excess of the amount of the deposit of $10,600. This claim, however, should have been made at the time of the charge to the jury. The defendant did not object to the judge’s instructions (which permitted damages in excess of the deposit) and made no suggestions after the charge was given although invited to do so by the judge. It is only by way of appeal from the denial of its motion for a new trial that the defendant argues the issue of excessive damages. The defendant was not entitled as of right to bring before the trial judge on his motion for a new trial this question which it neglected to raise at trial. Devore v. Good, 321 Mass. 84, 85 (1974). Chaplain v. Dugas, 323 Mass. 91, 95 (1948). “[A]n award of damages must stand unless ... to permit it to stand was an abuse of discretion on the part of the court below, amounting to an error of law.” Bartley v. Phillips, 317 Mass. 35, 43, 41-44 (1944). See also Torre v. Harris-Seybold Co., 9 Mass. App. Ct. 660, 663-665 (1980). There was no such abuse here. In any event, there was evidence before the jury that the plaintiffs spent about two months looking for business locations in reliance on the contract, that they went to Brockton by automobile, thus incurring travel expenses, and that they placed a $1,000 deposit on a location. 2 There was also evidence of the hourly earnings of at least one of the plaintiffs.

We turn next to the defendant’s contentions which relate to the plaintiffs’ statutory claim heard by the judge under *477 G. L. c. 93A, § 11. 3 The defendant claims that it committed no “unfair or deceptive acts or practices” in dealing with the plaintiffs under G. L. c. 93A, § 2(a), as appearing in St. 1967, c. 813, § 1. We relate the relevant facts as found by the judge and as supplemented by us from the record. Western Mass. Elec. Co. v. Sambo’s of Mass., Inc., 8 Mass. App. Ct. 815, 817 (1979), and cases cited.

The defendant manufactured and sold “Arabic Tunnel Ovens”, which are ovens specially designed to bake Arabic or Syrian bread. These ovens require sufficient gas to produce 1,000,000 B.T.U.’s per hour and, in most locations, the installation of a larger gas line. In the summer of 1974, officers of the defendant took the plaintiffs to places in Massachusetts where the defendant’s ovens were in use. All those ovens used natural gas as a source of heat.

The plaintiffs decided to go into the Syrian bread baking business and, in August, 1974, signed a contract for the purchase of an oven from the defendant. They gave a $600 deposit, and some time in October, deposited an additional $10,000. At about the time of the additional deposit, the plaintiffs became concerned that they would be obliged to purchase an oven for which they would be unable to obtain gas. As a result of this concern, an amendment to the contract was executed under which “the seller agreed to procure the necessary gas to run the Arabic Bread oven purchased by Mr. Homsi and partners.”

At the time the amendment was signed, there was an acute oil and gas shortage. The judge found that the defendant at that time knew that natural gas was not available in an adequate amount in the Brockton area, where the plaintiffs wanted to locate. The defendant argues that there was no evidence to support this finding, but we disagree. The defendant knew the quantity of gas needed for the oven and that a larger gas line would probably be needed. It was in a business highly dependent on adequate fuel *478 supplies and could be expected to follow closely the available sources of supply. There was evidence that the Brockton Gas Company took on no new gas customers after May, 1974, and there was evidence from two fuel dealers that there were problems in obtaining natural gas. The defendant also knew that the plaintiffs were looking in Brockton, a city with large Lebanese and Greek populations which did not have a bakery making Arabic bread. Moreover, the gas shortage was not limited to Brockton, and there was evidence that another customer of the defendant was irate because, despite the defendant’s promise, the customer was unable to obtain gas. We conclude that the judge’s finding that the defendant knew natural gas was not available in an adequate amount was not clearly erroneous. Mass.R.Civ.P. 52(a), 365 Mass. 816 (1974).

The defendant introduced evidence that at the time it offered delivery of the oven, an event which occurred approximately one month after the contract amendment had been signed, propane gas was available for the operation of the oven.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reniere v. Alpha Management Corp.
32 Mass. L. Rptr. 410 (Massachusetts Superior Court, 2014)
Great America Leasing Corp. v. Law Office of Jackson
2008 Mass. App. Div. 165 (Mass. Dist. Ct., App. Div., 2008)
Brewster Wallcovering Co. v. Blue Mountain Wallcoverings, Inc.
864 N.E.2d 518 (Massachusetts Appeals Court, 2007)
Jensen v. Daniels
57 Mass. App. Ct. 811 (Massachusetts Appeals Court, 2003)
Moon v. Trust Insurance
2000 Mass. App. Div. 89 (Mass. Dist. Ct., App. Div., 2000)
Bollen v. Camp Kingsmont
2000 Mass. App. Div. 56 (Mass. Dist. Ct., App. Div., 2000)
Ramirez v. C.L.A.S., Inc.
2000 Mass. App. Div. 16 (Mass. Dist. Ct., App. Div., 2000)
Mayer v. Cohen-Miles Insurance Agency, Inc.
722 N.E.2d 27 (Massachusetts Appeals Court, 2000)
Locke v. Austin
1999 Mass. App. Div. 257 (Mass. Dist. Ct., App. Div., 1999)
American Shooting Sports Council, Inc. v. Attorney General
429 Mass. 871 (Massachusetts Supreme Judicial Court, 1999)
Community Builders, Inc. v. Indian Motocycle Associates, Inc.
692 N.E.2d 964 (Massachusetts Appeals Court, 1998)
Arthur D. Little International, Inc. v. Dooyang Corp.
995 F. Supp. 217 (D. Massachusetts, 1998)
Urman v. South Boston Savings Bank
424 Mass. 165 (Massachusetts Supreme Judicial Court, 1997)
Richard Lundgren, Inc. v. American Honda Motor Co.
4 Mass. L. Rptr. 477 (Massachusetts Superior Court, 1995)
Urman v. South Boston Savings Bank
3 Mass. L. Rptr. 123 (Massachusetts Superior Court, 1994)
Forest City Craftsmen, Inc. v. DeMagistris
1 Mass. L. Rptr. 453 (Massachusetts Superior Court, 1993)
Lumbermens Mutual Casualty Co. v. Office Unlimited, Inc.
1 Mass. L. Rptr. 49 (Massachusetts Superior Court, 1993)
Halper v. Demeter
610 N.E.2d 332 (Massachusetts Appeals Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
409 N.E.2d 219, 10 Mass. App. Ct. 474, Counsel Stack Legal Research, https://law.counselstack.com/opinion/homsi-v-ch-babb-co-inc-massappct-1980.