Holy Cross Wilderness Fund v. Madigan

960 F.2d 1515, 1992 WL 65032
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 3, 1992
DocketNo. 90-1252
StatusPublished
Cited by34 cases

This text of 960 F.2d 1515 (Holy Cross Wilderness Fund v. Madigan) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holy Cross Wilderness Fund v. Madigan, 960 F.2d 1515, 1992 WL 65032 (10th Cir. 1992).

Opinion

STEPHEN H. ANDERSON, Circuit Judge.

The central question in this case is whether the Army Corps of Engineers violated the National Environmental Policy Act (“NEPA”) and section 404 of the Clean Water Act (“CWA”) when it issued a permit to allow construction of the Homestake II water project in the Holy Cross Wilderness Area, located in the White River National Forest outside Denver, Colorado pri- or to the completion of studies designed to develop a plan to mitigate any adverse impact on wetlands in the Wilderness Area. The appellant contends as follows: (1) the Corps violated NEPA when it issued its section 404 permit on the basis of an inadequate Final Environmental Impact Statement (“FEIS”) which did not discuss mitigation measures and by failing to supplement the FEIS after obtaining additional information disputing certain of its conclusions; and (2) the Corps violated the CWA and various implementing regulations when it issued the permit before all environmental studies were completed and subjected to a full public interest review.

The Fund seeks an order invalidating the permit and enjoining the Corps from issuing a new permit until the Corps prepares a supplemental EIS and conducts a “proper” public interest review under the CWA. The district court held there was no NEPA or CWA violation and dismissed the complaint. We affirm. The crux of our holding is that, in the face of considerable conflicting expert views as to the probable impacts of the Project on Wilderness Area wetlands, the Corps’ decision to issue the permit with the specific condition that there would be no wetlands losses, and with the requirement that a long-term monitoring and mitigation plan be implemented, was not arbitrary or capricious or in violation of any applicable regulations.

BACKGROUND

The Homestake II project is the second phase of a long-term water development project designed to provide the Colorado cities of Colorado Springs and Aurora (the “Cities”) with additional water. It involves the diversion of water from the Cross Creek and Fall Creek drainages in the Wilderness Area to the Homestake Reservoir through a series of surface diversion structures and underground tunnels.1 Plaintiff Holy Cross Wilderness Defense Fund is a private non-profit organization formed for the express purpose of protecting the Wilderness Area.

The Wilderness Area is an area so designated by Congress under the Colorado Wilderness Act, Title I of Public Law 96-560, 94 Stat. 3266 and to be managed under the Wilderness Act, 16 U.S.C. §§ 1131-1136. The Homestake II project is, however, exempt from the Wilderness Act’s ban on water projects in wilderness areas. The Project nonetheless required authorization from the Forest Service under Title V of the Federal Land Policy and Management Act (“FLPMA”) so that a portion of the Project could be built on National Forest land.

To this end, the Cities sought in January 1982 a land use easement from the Forest Service. In accordance with regulations of the Council on Environmental Quality (“CEQ”), 40 C.F.R. 1500, et seq., implementing NEPA, 42 U.S.C. § 4332(2)(C), the Forest Service conducted an environmental analysis. In May 1982 the Forest Service issued its draft Environmental Impact Statement (“DEIS”). In the DEIS the Forest Service analyzed six project alternatives. It then conducted more than 20 public hearings to receive input on the proposed project.2 Among the main areas of [1519]*1519concern expressed to the Forest Service was the one which is the focus of this case — the impact of the project on wetlands areas in the Wilderness Area.

In 1983, the Forest Service completed its FEIS, concluding that the Homestake project would have no significant impact on wetlands areas or other environmental resources. The Forest Service subsequently issued its Record of Decision (“ROD”) and granted the land use easement to the Cities.3 The easement contained 29 specific mitigation restrictions with which the Cities must comply. In granting the easement, the Forest Service Supervisor concluded that the grant was consistent with Executive Order 11990, “Protection of Wetlands.” 4 The decision to grant the easement is not itself at issue in this case.5

The Cities then sought from the Army Corps of Engineers the dredge and fill permit which is at issue in this case.6 In order to discharge fill material into creek drain-ages in the Wilderness Area in the course of constructing the water diversion structures contemplated by the Project, the Cities were required under section 404 of the Clean Water Act, 33 U.S.C. § 1344, to obtain a permit from the Secretary of the Army, acting through the Corps. Before issuing a permit, the Corps must also comply with NEPA.

Apparently concerned that the Forest Service FEIS may not have adequately addressed the question of the impact of the Project on wetlands, the Corps asked its Environmental Laboratory to review the FEIS. In its July, 1983 report, the Laboratory concluded that the Forest Service had not adequately shown that wetland areas would be unaffected by the Project, and it recommended that the Corps acquire additional information. At approximately the same time, the U.S. Fish and Wildlife Service did its own review of the possible impact of the Project on wetlands, and concluded there would be no detrimental impact. Addendum Vol. II to Appellees’ Briefs at B357.

The Corps thereafter hired a consultant, Aqua Resources, Inc. (“ARI”), to study the matter. In its May, 1984 report, ARI concluded that “[t]here is a potential for significant adverse impacts to downstream wetlands in terms of sequentially (over time) lowering the water table associated with several Cross and Fall creek wetlands.” Addendum to Appellant’s Opening [1520]*1520Brief at A43. It recommended that specific additional studies be done, that pre- and post-construction monitoring be required, and that mitigation measures be developed if the additional studies showed an expected adverse impact on wetlands. Id. at A44. After reviewing the ARI Report, the Environmental Protection Agency (“EPA”) concluded that “the performance of additional studies ... should be considered before any construction is undertaken in the project area to identify probable wetland impacts.” Id. at A49.7

The Corps did not in fact conduct additional studies prior to issuance of the permit. It did not prepare a supplemental EIS or its own EIS or other environmental analysis. Instead, it adopted the Forest Service’s FEIS as its own and issued a permit subject to specific conditions. As the Record of Decision by the Army Corps District Engineer recognized:

[t]he Forest Service has made a reasoned decision and their judgment may ultimately prove correct. I believe, however, that due to specific mandates of my authority to protect the waters of the United States, I must take a more conservative approach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wyoming v. United States Department of Agriculture
661 F.3d 1209 (Tenth Circuit, 2011)
CITIZENS AGAINST RUINING OUR ENVT. v. Klein
747 F. Supp. 2d 1234 (D. Colorado, 2010)
Diné Citizens Against Ruining Our Environment v. Klein
747 F. Supp. 2d 1234 (D. Colorado, 2010)
Wyoming v. United States Department of Agriculture
570 F. Supp. 2d 1309 (D. Wyoming, 2008)
Sierra Club v. United States Army Corps of Engineers
464 F. Supp. 2d 1171 (M.D. Florida, 2006)
Methow Forest Watch v. United States Forest Service
383 F. Supp. 2d 1263 (D. Oregon, 2005)
Trout Unlimited v. United States Department of Agriculture
320 F. Supp. 2d 1090 (D. Colorado, 2004)
Southern Utah Wilderness Alliance v. Norton
301 F.3d 1217 (Tenth Circuit, 2002)
Southern Utah Wilderness Alliance v. Gale Norton
301 F.3d 1217 (Tenth Circuit, 2002)
Isle Royale Boaters Ass'n v. Norton
154 F. Supp. 2d 1098 (W.D. Michigan, 2001)
Sierra Club v. United States Department of Energy
150 F. Supp. 2d 1099 (D. Colorado, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
960 F.2d 1515, 1992 WL 65032, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holy-cross-wilderness-fund-v-madigan-ca10-1992.