HOLTEC INTERNATIONAL v. TOWNSHIP OF LACEY

CourtDistrict Court, D. New Jersey
DecidedOctober 22, 2020
Docket3:20-cv-12773
StatusUnknown

This text of HOLTEC INTERNATIONAL v. TOWNSHIP OF LACEY (HOLTEC INTERNATIONAL v. TOWNSHIP OF LACEY) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HOLTEC INTERNATIONAL v. TOWNSHIP OF LACEY, (D.N.J. 2020).

Opinion

NOT FOR PUBLICATION UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

HOLTEC INTERNATIONAL, et al. Civil Action No. 20-12773 (MAS) (DEA) MEMORANDUM OPINION TOWNSHIP OF LACEY, et al.

Defendants.

SHIPP, District Judge This matter comes before the Court upon Plaintiffs Holtec International (“Holtec”), Holtec Decommissioning International, LLC (“HDI”), and Oyster Creek Environmental Protection, LLC’s (“OCEP”) (collectively, “Plaintiffs”} Motion for a Temporary Restraining Order. (ECF No. 3.) Defendants Township of Lacey (the “Township”) and Lacey Township Planning Board (the “Planning Board”) (collectively, “Defendants”) opposed (ECF Nos. 13, 15) and Plaintiffs replied (ECF No. 18). The Court has carefully considered the parties’ submissions and decides the matter without oral argument pursuant to Local Civil Rule 78.1. For the reasons set forth herein, Plaintiffs’ Motion is denied. I. BACKGROUND Plaintiffs own Oyster Creek Nuclear Power Station (“Oyster Creek”), a shutdown nuclear power plant in Ocean County, New Jersey.' (Compl. J 1, ECF No. 1.) Oyster Creek is currently

1 OCEP and HDI are both wholly owned subsidiaries of Holtec, (Compl. 1 6.) OCEP is the licensed owner of Oyster Creek and HDI serves as the plant’s decommissioning operator. (/d. { 7.)

undergoing decommissioning, a “process by which [a] plant is retired from service.” (/d.) The decommissioning process is regulated by the Nuclear Regulatory Commission (“NRC”)? and includes the transfer of all spent nuclear fuel from a spent fuel pool to an on-site storage facility known as the Independent Spent Fuel Storage Installation (“ISFS!”). (/d. §f] 3-4.) In order to perform the spent fuel campaign, Plaintiffs must first complete a mandatory dry run (i.e., practice demonstrations). (/d. J 24.) On July 9, 2020, Plaintiffs submitted a minor site application (the “Application”) to the Planning Board, essentially seeking to expand the ISFSI area. (/d. {| 12.) The Planning Board, however, denied the Application on August 24, 2020. (/d. { 18.) Plaintiffs assert that this denial resulted in the suspension of a three-day dry run scheduled to begin on October 26, 2020.° (Dostal Aff. 7 11, ECF No. 3-2.) A. Oyster Creek Background In January 2018, Exelon Generating Company, LLC (“Exelon”), the previous owner of Oyster Creek, and the New Jersey Department of Environmental Protection entered into an Administrative Consent Order (“ACO”) governing the decommissioning of Oyster Creek. (Compl. 2-3; ACO Doc., Ex. D to Compl., ECF No. 1-1.) Among other things, the ACO directed Exelon to submit a Post-Shutdown Decommissioning Activities Report (“PSDAR”) to the NRC. (ACO Doc. 1-2.) The ACO also provided that “Exelon will transfer all fuel to the ISFSI as soon as technically and financially feasible and in accordance with the Facility’s PSDAR.” (/d. at 3.)

2 The NRC is an independent regulatory agency exercising all of the licensing and related regulatory functions formerly assigned to the Atomic Energy Commission. 42 U.S.C. §§ 5841(f), 5842. 3 Plaintiffs indicate that a dry run related activity at their Camden Facility was scheduled for September 28 through September 30, 2020. (Dostal Aff. { 11.)

On May 21, 2018, Exelon submitted the PSDAR, which included a “description of the planned decommissioning activities [and] a schedule for their accomplishment.” (Exelon’s PSDAR 3, Ex. E to Compl., ECF No. 1-1; Compl. 5.) The PSDAR indicates that Exelon selected the SAFSTOR decommissioning method.* (/d. at 4-5.) Under SAFSTOR, Exelon intended to commence the transfer of spent fuel to the ISFSI in March 2020 and expected to complete the transfer in March 2024. (See id. at 8, 12.) According to the PSDAR, Exelon estimated the overall decommissioning process would be completed by approximately 2078. (/d. at 8.) Exelon also indicated in the PSDAR that no abnormal environmental issues were expected to result from use of the SAFSTOR method. (See id. at 22-41.) Sometime thereafter, Plaintiffs and Exelon entered into an agreement for the sale of Oyster Creek that was subject to the NRC’s approval. (See Compl. 4 6.) In anticipation of the acquisition, Plaintiffs submitted a revised PSDAR to the NRC on September 28, 2018. (/d. J 9; Pls.” PSDAR 4, Ex. F to Compl., ECF No. 1-1.) Unlike Exelon, Plaintiffs selected the DECON decommissioning method.? (Pls.’ PSDAR 4.) Plaintiffs’ PSDAR appears to indicate that they intended to commence the spent fuel campaign around June 2019 and expected to complete the transfer around June 2023. (See id. at 17.) According to the PSDAR, Plaintiffs sought to complete the decommissioning process, except for activities related to the ISFSI, “within approximately eight years of license

4 SAFSTOR is “[a] method of decommissioning in which a nuclear facility is placed and maintained in a condition that allows the facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use.” (Exelon’s PSDAR 10.) 5 Plaintiffs PSDAR describes the DECON decommissioning method as follows: “The equipment, structures, and portions of the facility and site that contain radioactive contaminants are promptly removed or decontaminated to a level that permits termination of the license shortly after cessation of operations.” (Pls.” PSDAR 4.)

transfer.” (/d. at 10.) On June 20, 2019, the NRC approved the transfer and Plaintiffs acquired Oyster Creek shortly thereafter. (Compl. [J 11-12.) B. Plaintiffs’ Application to the Planning Board In December 2019, Plaintiffs submitted an initial application to the Planning Board seeking approval to, among other things, expand the ISFSI pad to accommodate additional storage casks. (Compl. 7 61; Dec. 2019 Appl., Ex. Q to Compl., ECF No. 1-3.) Plaintiffs assert that they ultimately withdrew this application after determining that the proposed project was no longer necessary. (Compl. {9 62-63.) Plaintiffs, however, allegedly performed unauthorized construction at the site. Consequently, in March 2020, the Township issued a stop construction order to Plaintiffs for failing to obtain construction permits. (Stop Construction Order Doc. (“SCO”), Ex. S to Compl., ECF No. 1-3; Compl. § 64.) The order also advised Plaintiffs that they may resume construction after obtaining the proper permits. (See generally SCO.) By correspondence dated May 14, 2020, the Township again advised Plaintiffs to obtain the proper permits before continuing construction at Oyster Creek. (May 14, 2020 Correspondence, Ex. D to Def. Twp.’s Opp’n Br., ECF No. 15-1.) After Plaintiffs allegedly continued unauthorized construction, the Township filed a lawsuit in the Superior Court of New Jersey, Ocean County, Chancery Division,*® seeking to enjoin Plaintiffs from continuing to undertake such work until they obtained the necessary approvals and permits. (May 27, 2020 Superior Ct. Compl., Ex. E to Def. Twp.’s Opp’n Br., ECF No. 15-1; Compl. J 66.) The Superior Court entered an order granting the Township’s requested relief. (Compl. J 67.) On July 17, 2020, following settlement discussions by the parties, the Superior

6 Twp. of Lacey v. Holtec Int'l, Docket No. OCN-C-76-20.

Court entered a consent order resolving the matter. (/d. | 69; Consent Order, Ex. V to Compl., ECF No. 1-3.) The consent order indicated that Plaintiffs would submit a site plan application for any prior and planned construction at Oyster Creek. (Consent Order { 1.) That same month, Plaintiffs submitted the Application to the Planning Board in which they described the project as “includ[ing] the filling of a hole where a concrete pad was originally supposed to be constructed for spent fuel storage installation expansion.” (July 2020 Appl., Ex. G to Compl., ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
Deakins v. Monaghan
484 U.S. 193 (Supreme Court, 1988)
Frank E. Acierno v. New Castle County
40 F.3d 645 (Third Circuit, 1994)
Tsai-Yi Yang v. Fu-Chiang Tsui
416 F.3d 199 (Third Circuit, 2005)
Kendall v. Russell
572 F.3d 126 (Third Circuit, 2009)
Laidlaw, Inc. v. Student Transportation of America, Inc.
20 F. Supp. 2d 727 (D. New Jersey, 1998)
Khadidja Issa v. Lancaster School District
847 F.3d 121 (Third Circuit, 2017)
Colleen Reilly v. City of Harrisburg
858 F.3d 173 (Third Circuit, 2017)
Sprint Commc'ns, Inc. v. Jacobs
134 S. Ct. 584 (Supreme Court, 2013)
Morton v. Beyer
822 F.2d 364 (Third Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
HOLTEC INTERNATIONAL v. TOWNSHIP OF LACEY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holtec-international-v-township-of-lacey-njd-2020.