Holston Valley Hospital & Medical Center, Inc. v. Ashford Group Ltd.

661 F. Supp. 72, 1986 U.S. Dist. LEXIS 26693
CourtDistrict Court, E.D. Tennessee
DecidedApril 16, 1986
DocketNo. CIV-2-85-171
StatusPublished
Cited by1 cases

This text of 661 F. Supp. 72 (Holston Valley Hospital & Medical Center, Inc. v. Ashford Group Ltd.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holston Valley Hospital & Medical Center, Inc. v. Ashford Group Ltd., 661 F. Supp. 72, 1986 U.S. Dist. LEXIS 26693 (E.D. Tenn. 1986).

Opinion

MEMORANDUM AND ORDER

HULL, Chief Judge.

This is a breach of contract action which came before the Court for trial on April 9, 1986. Plaintiff, Holston Valley Hospital and Medical Center, Inc. (Holston Valley), alleges that on April 24, 1984 it contracted defendant to assist in transferring computer software programs from plaintiffs Honeywell computer system to its new IBM system. The contract, plaintiff claims, set a completion date of July 15, 1984 and fixed the maximum contract price at $30,555.00, with provisions for additional charges of up to $10,000.00 should certain contingencies arise.

Plaintiff argues that defendant breached its contract because defendant did not complete performance by July 15, 1984 and because defendant ultimately repudiated the contract, abandoned performance, and destroyed the work which had been previously completed. As a result of defendant’s breach, plaintiff asserts that it has received no benefit for the $27,700.00 it paid defendant before the breach and that it was forced to pay an additional $36,-086.63 to another contractor to complete the project.

Defendant, the Ashford Group Limited (Ashford), admits that it contracted with plaintiff to transfer computer programs from a Honeywell to an IBM computer system but asserts that contingencies provided for in the contract arose, causing delays and additional expenses. Furthermore, Ashford claims that plaintiff breached the contract when it refused to pay the invoices Ashford submitted in August, 1984 and failed to provide tapes that would be “readable” and “usable” on the IBM system. Ashford argues that these breaches on plaintiffs part justify its refusal to continue work on the project.

A central dispute in this case arises over which party had the responsibility of rendering the customized, Honeywell tapes “usable” on the IBM system. Plaintiff argues that it agreed to supply computer tapes which could be “read”, but not necessarily understood, by the IBM computer. Plaintiff says that it was Ashford’s task to adapt the tapes so that the IBM computer could understand and process the data contained on them. Defendant argues, on the other hand, that Holston Valley was to have made the old tapes “readable” and “usable” on the IBM equipment before defendant began the task of transferring the data from the Honeywell to the IBM. Ash-ford claims that Holston Valley’s failure to provide “usable” tapes was a contract breach which justifies the additional expenses and time required on the project.

Inexplicably, the contract, which was prepared by Ashford, does not directly address the issue of which party was to convert the Honeywell tapes so that the IBM could interpret and process the data contained on them. On page two the contract provides the following ambiguous language:

The Ashford Group Limited will provide technically qualified personnel to perform computer programming, analysis, documentation or other related duties to meet client’s requirements as indicated by this agreement. The data processing technical services will be furnished by the Holston Valley Hospital and Medical Center and performed at Ashford’s office on facilities furnished by IBM, and the Holston Valley Hospital and Medical Center. Holston Valley Hospital and Medical Center is responsible for furnishing MSA IBM system tapes to be used to accomplish this conversion.

Both parties admit that this contract language is ambiguous and does not clearly define the duties of either party.

[74]*74Under Tennessee Law, ambiguous and doubtful language in a contract will be construed against the party who submitted the language and prepared the contract. Dairymen, Inc. v. Hardin, 369 F.Supp. 1102, 1106-1107 (E.D.Tenn.1974); Hanover Insurance Co. v. Haney, 221 Tenn. 148, 425 S.W.2d 590 (1968). Furthermore, where, as here, the contract is ambiguous and arguably susceptible to two different interpretations, one reasonable and the other unreasonable, the reasonable interpretation should be adopted. Gibson v. International Harvester Co., 557 F.Supp. 1000 (W.D.Tenn.1983); Oman Construction Co., v. Tennessee Central Railway Co., 212 Tenn. 556, 370 S.W.2d 563 (1963).

The Court finds that the most reasonable interpretation of this contract is that Holston Valley was to provide computer tapes which would be “readable” and adaptable to use on the IBM computer equipment but that Ashford’s task was to convert the tapes so that the IBM could process and use the information. Nowhere does the contract state that Holston Valley must convert the Honeywell tapes so that the IBM computer could read, process, and interpret their information. In fact, as plaintiff’s expert, John Munsen testified, adapting the customized Honeywell MSA tapes so that the IBM could process the data they contained was the “heart of the technical task” in the conversion project.

Since plaintiff’s staff was admittedly inexperienced in using IBM equipment and since Ashford represented itself to be experts, the Court finds it unreasonable to believe that Holston Valley would hire experts to convert the computer programs but would reserve the most difficult conversion task for its own inexperienced staff. Had the parties intended otherwise, it would be reasonable to expect that Ash-ford, as the expert in computer conversion and the drafter of the contract, would have included explicit language to that effect in the contract.

Next, Ashford argues that the contingencies provided for in the contract all arose, necessitating additional time and expense. When Holston Valley refused to pay these expenses, Ashford claims it was justified in stopping work on the project. The contract provides the following at page seven:

In addition, Ashford has agreed that the amount of $30,555 will be the maximum to be charged for this project.
It is recognized that there are three areas of concern, not under the control of Ashford, and if a problem develops in any of the three, additional charges will be made if costs are incurred as follows:
1. If the release and installation of the MSA tapes at the Palo Alto Data Center requires corrective action, the maximum to be charged would be $2,000.
2. If the response time from the IBM system is very slow and requires additional equipment and time, the maximum to be charged would be $4,000.
3. If when the Ashford MSA specialist arrive in Kingsport to use the IBM 4381 and a determination is made that its development is unsatisfactory to complete the installation of the systems, a maximum charge of $4,000 may be made.

Defendant’s representative, Kermit Pickett, testified that each of the contingency problems foreseen in the contract did occur and that he billed Holston Valley accordingly. On cross-examination, however, Mr. Pickett admitted that he had only invoiced $1,600.00 in expenses directly attributable to the contingencies provided for in the contract. James Going, assistant executive director of Holston Valley, testified that Ashford had already billed and Holston Valley had already paid $27,700.00 on the project when Ashford submitted an invoice for $6,300.00. This demand, Going testified, exceeded the contract price and was not attributed to any of the contract contingencies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heller Financial, Inc. v. Gautam Pandhi
888 F.2d 1391 (Sixth Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
661 F. Supp. 72, 1986 U.S. Dist. LEXIS 26693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holston-valley-hospital-medical-center-inc-v-ashford-group-ltd-tned-1986.