Holloman v. City of Georgetown

526 S.W.2d 682, 1975 Tex. App. LEXIS 2978
CourtCourt of Appeals of Texas
DecidedJuly 30, 1975
DocketNo. 12238
StatusPublished
Cited by4 cases

This text of 526 S.W.2d 682 (Holloman v. City of Georgetown) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holloman v. City of Georgetown, 526 S.W.2d 682, 1975 Tex. App. LEXIS 2978 (Tex. Ct. App. 1975).

Opinion

SHANNON, Justice.

This is an appeal from the judgment entered by the district court of Williamson County in favor of appellee, the City of Georgetown, Texas, for $69,526.28. Appellants are F. E. Holloman, doing business as F. E. Holloman Excavating Company and Millers Mutual Fire Insurance Company of Texas. We will affirm the judgment of the district court.

In his trial petition Holloman alleged that the City advertised for sealed bids for certain sanitary sewer improvements to be constructed in Georgetown. He submitted a written bid to do the work and furnish the materials for $137,174.75. The City accepted the bid and Holloman entered upon the construction of the improvements. The contract was to be completed in April of 1972.

Holloman pleaded that after the job was underway he discovered that the City’s plans and specifications were incorrect with respect to the quantities of rock required to be excavated. Those plans and specifications stated that the amount of rock to be excavated was 1200 cubic yards whereas, according to Holloman, the amount to be excavated exceeded 8900 cubic yards.

In addition to the greater quantity of rock, Holloman stated that he encountered large amounts of underground water. By reason of the difficulty in excavating the rock and in removing the water, the excavation was “slow and exceedingly expensive.” Holloman requested and received permission of the City to extend the time for completion of the contract until November 26,1972. Holloman pleaded additionally that he notified the City that he would need even a longer period of time than November 26. He claimed that in October [684]*684or November of 1972, he notified the City that a renegotiation should be had upon the bid price for rock excavation over the amount of 1500 cubic yards upon the basis of $35.00 per cubic yard.

Holloman averred further that the City’s agent wrote the City recommending that on November 26, the City declare the project abandoned, that the City take over Hollo-man’s equipment, and that Holloman not be paid on his monthly estimate number six. Holloman pleaded that on November 17, he learned that the contract had been terminated at the city council meeting on the preceding evening. On November 20, 1972, Holloman handed to appellee’s city manager his proposal to renegotiate the excavation of the rock. According to Holloman, the city manager advised Mm that the city council had voted to terminate the contract and to pay Mm the balance due him.

Acting upon such information, Holloman claimed that he proceeded to remove the workmen from the project and most of his equipment.

Holloman alleged that the City breached the contract, and prayed for compensatory damages in the sum of $88,150.16, for exemplary damages in the sum of $50,000.00, and for attorney’s fees in the sum of $10,000.00.

The City answered and filed a cross-action. The City pleaded that the contract “was repudiated and breached” by Hollo-man on November 20, 1972, when he refused to prosecute the job further unless the City agreed to renegotiate the contract. The terms of the contract, the City claimed, were clear and unambiguous, and did not require it to agree to any renegotiation because of any inaccuracies in the estimate submitted in its proposal.

In its cross-action the City pleaded the contract, under the terms of which Hollo-man was required to complete the work in April of 1972. Despite several extensions of time granted by the City, by November 20, 1972, the City was notified by its engineer that judging by the rate of past progress that it would take about 814 more calendar days for Holloman to complete the job and advised the City that no more extensions of time should be granted. Also on November 20, 1972, the City was informed that Holloman would continue on the job only if the rates for the excavation of the rock were renegotiated.

The City pleaded that “faced with Hollo-man’s ultimatum,” it notified Holloman that the contract was declared breached. Thereafter the City entered into a contract with Roy Krienke for the completion of the job. Krienke immediately began work on the project which was finished in December, 1978.

The City pleaded finally that it had suffered damages in the amount of $69,524.61, which sum was the difference between the total construction cost less the cost of the project had Holloman performed under the contract, increased by the “reasonably foreseeable” consequential damages. The City also sought recovery of $10,000.00 as reasonable attorney’s fees.

The case was submitted to the jury by sixteen special issues. In answering those issues the jury failed to find (1) that the City terminated the contract as of November 26, 1972; (2) that the City had wrongfully withheld certain of Holloman’s equipment; and (8) that the City had willfully made a claim against Holloman’s bonding company. The jury answered affirmatively (1) that Holloman abandoned the contract with the City; (2) that he failed to provide sufficient workmen and equipment to complete the work called for under the contract by November 26, 1972; and, (8) that there were defects in the lines and the “lift station” which had been installed by Holloman.

With respect to the damages issues, the jury answered that the remaining balance due Holloman by the City for labor performed and materials furnished to November 20, 1972, was $3,718.54. The amount that Holloman would have earned under the contract, had he completed it was $161,-226.35, and the amount which the City was reasonably required to spend in completing [685]*685the contract, excluding those amounts expended for the reasonable and necessary inspection and repairs of the materials and equipment installed by Holloman was §136,-376.60. The jury answered further that the amount the City was reasonably required to spend in inspecting and repairing the defects in the lines and lift station was §15,-496.53. The jury answered, in addition, that the City had incurred the total sum of $22,918.21 for additional engineering costs, interest, and attorney’s fees "to make good” the failure of Holloman to perform the contract.

Based upon the jury’s verdict, judgment was entered for the City for §58,946.23. The judgment recited that sum represented the City’s cost of completing the contract over and above the cost to the City had Holloman performed, including additional interest and engineering expenses, less the amount of offsets to Holloman as determined by the jury.

Holloman complains of the judgment by fifteen points of error. No effort will be made to discuss those points of error in the order of their appearance in the briefs.

Holloman’s claimed right of renegotiation was grounded upon General Provision 5.02 of the Specifications. That provision reads as follows:

"Changes and Increased or Decreased Quantities of Work:
“The Owner shall have the right to make such changes and alterations in the Plans or in the quantities of work as he may consider necessary or desirable, and such changes and alterations shall not be considered as a waiver of any condition of the Contract, nor shall they invalidate any provision thereof. The Contractor shall perform the work as increased or decreased, and no allowance will be made for anticipated profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hilsher v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
717 S.W.2d 435 (Court of Appeals of Texas, 1986)
Chernoff v. Chernoff Bros., Inc.
597 S.W.2d 24 (Court of Appeals of Texas, 1980)
Irick v. Andrew
545 S.W.2d 557 (Court of Appeals of Texas, 1976)
Muller v. Light
538 S.W.2d 487 (Court of Appeals of Texas, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
526 S.W.2d 682, 1975 Tex. App. LEXIS 2978, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holloman-v-city-of-georgetown-texapp-1975.