Hollingsworth v. Leachville Special School District

249 S.W. 24, 157 Ark. 430, 1923 Ark. LEXIS 208
CourtSupreme Court of Arkansas
DecidedFebruary 26, 1923
StatusPublished
Cited by7 cases

This text of 249 S.W. 24 (Hollingsworth v. Leachville Special School District) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hollingsworth v. Leachville Special School District, 249 S.W. 24, 157 Ark. 430, 1923 Ark. LEXIS 208 (Ark. 1923).

Opinion

Smith, J.

On March 11, 1920, J. E. Hollingsworth, a building contractor doing business as J. E. Hollingsworth & Co., sued the Leachville Special School District, alleging that on or about May 20, 1919, he and the said district entered into a written contract, whereby he agreed to erect and complete a certain brick school building in the town of Leachville, according to the plans and specifications made a part of the complaint, for the sum of $34,000. That he began the construction of the building under his contract, and had expended thereon the sum of $20,178.80, and that he had been paid by the school district, on the certificate of the architect, the sum of $12,800, leaving a balance due him of $7,378.80. That on or about December 10, 1919, the school district forcibly took possession of said partly constructed building, and refused and declined to permit him to complete same, and that such action on the part of the school district was unlawful and wrongful, in that he was constructing the building in accordance with the plans and specifications.

On March 27, 1920, the school district filed its answer and cross-complaint. It admitted the execution of the contract sued on, but denied that the building was constructed according to the plans and specifications, and denied that it had, without right, forbidden plaintiff to continue the work, and averred that its reason for not permitting plaintiff to continue was that he had refused to construct and complete the building in accordance with the plans and specifications.

In its cross-complaint the school district set up the contract, and alleged the execution of a bond for its faithful performance by the Maryland Casualty Company as surety. The plaintiff, the surety and Mitchell Selligmail, tlie architect, were made parties to the suit. It was alleged that, the architect had conspired with the plaintiff to obtain the contract for the plaintiff, and that the architect had fraudulently permitted the plaintiff to make substitutions of defective material, and had fraudulently approved defective work by the contractor.

Answers were filed by the cross-defendants, denying all the allegations of the cross-complaint, and alleging that the work of the contractor was in accordance with the plans and specifications, and had been accepted and approved by the architect, whose decision, according to the terms of the building contract, was final with respect to the work, and averred failure to give notice of default.

The final decree dismissed the complaint, and also the cross-complaint in so far as the architect was concerned, but gave the district a judgment against Hollingsworth and his surety, and this appeal is from that decree.

The record is very voluminous, consisting of over a thousand pages, and the briefs, which are correspondingly large, discuss at length the conflicting testimony of the numerous witnesses. We shall not undertake to review all this testimony, although we have considered it, and have reached the conclusion that the findings of fact upon which the decree of the court below was based were not clearly against the preponderance of the testimony except as to two items, which we think were improperly charged against the contractor.

For the reversal of the judgment it is insisted:

1. That there was a substantial performance of the contract on the part'of the contractor up to the time of his discharge; and this is the principal question in the case.

2. That there was no certificate by the architect of a failure on Ihe part of the contractor to comply with the contract, it being’ insisted that Selligman was the architect authorized by the contract to make that certificate.

3. That, if the associate architect, who made the certificate upon which the directors acted in discharging the contractor, was authorized to so certify, he should have clone so in connection with Selligman, and not individually as he did do.

4. That proper notice, as prescribed by the contract, was not given by the district to the contractor of his discharge.

5. That the decision of the architect as to compliance with the contract was final, and could be impeached only by proof of fraud or mistake so gross as to imply bad faith and the exercise of dishonest judgment, and the evidence does not justify that finding.

6. That there was no notice of default, and the surety was, on that account, relieved of its obligation to pay liquidated damages for delay.

7. That the district waived strict compliance-with the terms of the contract requiring the completion of the building within five months.

8 and 9. That the district did not properly prove the damages allowed it.

The propositions stated are substantially questions of fact, as the principles of law which control their decision are well settled and are not in dispute between the parties, and we will not undertake a separate discussion of each of these propositions.

There are provisions in the building contract which make the architect the final arbiter between the contractor and the district, and it becomes important, therefore, to determine who the architect was, as Hollingsworth took the position, when the first disagreement arose, that Edelsvard was not the architect, and Hollingsworth demanded that Selligman approve the findings and directions of Edelsvard before he would as.sent thereto. On that question we quote from the contract as follows : ‘ ‘ This agreement, made this 20th day of March, 1919, by and between the Leachville Special School District, party of the first part, hereinafter called the owner, and Mitchell Selligman, party of the second part, hereinafter called the architect, with G. A. Edelsvarcl, associate, witnesseth:” The same instrument defines the terms, ‘ ‘ owner, ” “ architect, ’ ’ and ‘ ‘ contractor, ’ ’ the definition of “architect” being “the term ‘architect’ refers to Mitchell Selligman or associate.”

Selligman and Edelsvard were partners, as Selligman & Edelsvard, at the time the district contracted with them as architects, although the negotiations leading to their employment were conducted by Selligman, and that member of the firm acted for the firm in the award of the contract to Hollingsworth, the plaintiff in this suit. However, “the plans and specifications were prepared by Edelsvard.

The court below was of the opinion that Edelsvard, as well as Selligman, was the “architect,” as that term was used in tlie contract, and we concur in that finding.

The contract specified what supervision the architect should give the building and what his duties should be in that connection, and we think it was contemplated by the parties that either Selligman or Edelsvard might perform those duties. The contractor was therefore in error in disputing Edelsvard’s authority as architect.

Pour bids were received by the district for the construction of the building as originally advertised. The lowest bid was $34,737, and was made by TI. E. Monk; the next lowest bid was $34,887, and this bid was made by the plaintiff Hollingsworth. The district had only $34,000 to spend for the building, and did not accept any of these bids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowman v. McFarlin
615 S.W.2d 383 (Court of Appeals of Arkansas, 1981)
Carter v. Quick
563 S.W.2d 461 (Supreme Court of Arkansas, 1978)
A. F. Conner & Sons, Inc. v. Tri-County Water Supply Corp.
541 S.W.2d 856 (Court of Appeals of Texas, 1976)
County of Tarrant v. Butcher & Sweeney Construction Co.
443 S.W.2d 302 (Court of Appeals of Texas, 1969)
Tech-Neeks, Inc. v. Francis
407 S.W.2d 938 (Supreme Court of Arkansas, 1966)
Norvell v. James
234 S.W.2d 378 (Supreme Court of Arkansas, 1950)
Harris v. Holder
230 S.W.2d 645 (Supreme Court of Arkansas, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
249 S.W. 24, 157 Ark. 430, 1923 Ark. LEXIS 208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hollingsworth-v-leachville-special-school-district-ark-1923.