Harris v. Holder

230 S.W.2d 645, 217 Ark. 434, 1950 Ark. LEXIS 437
CourtSupreme Court of Arkansas
DecidedJune 5, 1950
Docket4-9155
StatusPublished
Cited by6 cases

This text of 230 S.W.2d 645 (Harris v. Holder) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Holder, 230 S.W.2d 645, 217 Ark. 434, 1950 Ark. LEXIS 437 (Ark. 1950).

Opinion

MiNOR W. Millwee, Justice.

Appellee, W. M. Holder, is a building contractor and appellants, John W. Harris, W. Bradley Trimble, and W. B. Justiss, are partners doing business as Justiss Motor Company. On May 12, 1948, appellee contracted to construct a Quonset steel garage bnilding for appellants in El Dorado, Arkansas. El Dorado Lumber Co. sold appellants the steel to be used in construction of the bnilding. Appellee was to furnish the labor, certain materials and construct the building for $4,446.

The Justiss Motor Co. moved into the building the latter part of July, 1948. On September 17,1948, appellee filed this suit alleging due performance of the contract, the payment by appellants of only $1,500 of the contract price, and prayed judgment for the balance together with damages to his reputation and credit.

Appellants’ answer and cross-complaint denied that the building was completed according to the contract and particularly alleged breach of the contract in construction of the concrete floor which was alleged to be defective and unusable for the purposes intended. Appellants prayed damages on the cross-complaint against appel-lee and the surety on the performance and labor and material payment bonds executed by appellee.

A suit previously filed against appellee by certain materialmen was consolidated with the instant suit and judgments sustaining liens in favor of said materialmen were entered under a stipulation of all the parties.

After an extensive hearing the trial court found that the concrete floor was defective, but that such condition resulted from appellants’ interference with appellee in the manner and method of doing the work. A decree was entered in favor of appellee for the balance found due under the contract after discharge of the judgments entered in favor of the materialmen. Appellants’ cross-complaint was dismissed for want of equity and they have appealed.

In reference to the construction of the 6,000-foot floor the contract provides that appellee shall fqrnish: “All materials and labor for 6" floor of 2,000 lbs. concrete, reinforced with 6" x 6" x 10-gauge steel in slabs 20 ft. x 20 ft., reinforcing mesh to be broken at all expansion joints and joints cleaned and filled with either mastic or formed expansion strips; all slabs to be floated and finished in a workmanlike manner and all details to be strictly adhered to.” While a great deal of testimony was directed to the condition of the concrete floor, it is undisputed that it was defective and not finished in a workmanlike manner as required by the contract. Expert and lay witnesses on both sides testified that the floor was rough, uneven, or out of level in many places, and that the topping was soft, pitted, flaky and crumbly.

In his testimony appellee first denied but later admitted that the floor was defective and offered a variety of reasons therefor. He stated that the building site was moved back 50 feet from the original level location called for in the contract to a place where there was a three-foot fill which he was required to ‘ ‘ cat-pack. ’ ’ The written contract recites that the building was to be located at 1200 West Hillsboro Street, but does not otherwise designate the building site. Appellee apparently acquiesced in the change of building sites, if made, and the preponderance of the evidence fails to disclose that the defective condition of the floor resulted from such change.

The contract also provided for erection of the building “according to blueprints furnished by El Dorado Lumber Co. subject to changes as directed by engineer approved by El Dorado Lumber Company.” Edward Bader was sent to El Dorado by the manufacturer of the steel furnished by El Dorado Lumber Co. and was employed by the latter as the engineer designated in the contract. The evidence on behalf of appellants is that they knew nothing about concrete construction and made no attempt to supervise appellee or his employees in the construction of the concrete floor. Appellee stated that both Bader and Justiss supervised the laying of the floor and that Harris and Bader directed appellee to pour concrete on ground that was too soft and wet.

The preponderance of the evidence was to the effect that it is not an improper practice to pour concrete on wet ground in hot weather, but that the use of too much, water might cause the concrete slab to crack or sink. According to the greater weight of the evidence the slab base of the floor in controversy did not crack or sink and the defects in the floor resulted from the manner in which the topping or surface was laid and finished.

There was evidence that the soft and flaky condition of the topping was caused by allowing it to dry while unprotected and uncovered from the hot sun. Appellee stated that such condition might have been caused by leaving the floor uncovered, but asserted that appellants failed to furnish material for that purpose. Appellants were not required to furnish such covering either under the contract or local custom. Several contractors testified that dirt, which was available to appellee, furnished the best covering and was used generally by them for that purpose.

Another reason assigned by appellee for the defective condition of the floor was that appellants and Bader ordered delivery of the mixed concrete too rapidly and before appellee was ready for it to be poured. The mixed concrete was purchased by appellee from Gilliam Bros. Appellants’ denial that they ordered the concrete is corroborated by the representative who handled the orders for Gilliam Bros. He testified that appellee ordered the concrete sent out and all the delivery tickets were shown to have been signed by appellee. While appellee stated that he told the truck drivers to slow down the delivery, there is no showing that he made any complaint to the representative who handled the orders.

Appellee also claimed that appellant Justiss interfered by allowing water to run all night on the fresh concrete floor. His testimony on this point is somewhat contradictory. Although he testified that he directed Justiss to sprinkle the concrete at night, he stated that it constituted a bad practice when the floor was unprotected from the sun. He also testified that Justiss continued to run too much water on the floor after being warned not to do so, but this was stoutly denied by appellants’ witnesses.

Appellee and his employees stated generally that Bader supervised and directed the construction of the floor but they were unable to name specific orders which contributed to the defective conditions found. Bader directed the use of extra steel in the curb walls and larger expansion joints in the floor, but neither of these changes had anything to ■ do with the defects in the floor and appellee apparently concurred in the changes which were authorized under the contract.

The contract stipulated that the 20' x 20' slabs should be “floated and finished in a workmanlike manner.” According to the evidence there are two types of finish — ■ a “wood float” finish and a “steel trowel” finish. Either finish will produce a smooth surface, but a steel trowel finish produces a harder surface and requires more time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armstrong Remodeling & Construction, LLC v. Cardenas
417 S.W.3d 748 (Court of Appeals of Arkansas, 2012)
Butera v. Boucher
798 A.2d 340 (Supreme Court of Rhode Island, 2002)
Smith v. Unitemp Dry Kilns, Inc.
698 S.W.2d 313 (Court of Appeals of Arkansas, 1985)
Platner v. Herwald
486 N.E.2d 202 (Ohio Court of Appeals, 1984)
Carter v. Quick
563 S.W.2d 461 (Supreme Court of Arkansas, 1978)
Tech-Neeks, Inc. v. Francis
407 S.W.2d 938 (Supreme Court of Arkansas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
230 S.W.2d 645, 217 Ark. 434, 1950 Ark. LEXIS 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-holder-ark-1950.