Hoida, Inc. v. M & I MIDSTATE BANK

2006 WI 69, 717 N.W.2d 17, 291 Wis. 2d 283, 2006 Wisc. LEXIS 361
CourtWisconsin Supreme Court
DecidedJune 13, 2006
Docket2003AP2108
StatusPublished
Cited by118 cases

This text of 2006 WI 69 (Hoida, Inc. v. M & I MIDSTATE BANK) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoida, Inc. v. M & I MIDSTATE BANK, 2006 WI 69, 717 N.W.2d 17, 291 Wis. 2d 283, 2006 Wisc. LEXIS 361 (Wis. 2006).

Opinions

PATIENCE DRAKE ROGGENSACK, J.

¶ 1. We review a court of appeals decision that affirmed the circuit court's grant of summary judgment dismissing the claims of Hoida, Inc. (Hoida) against defendants M&I Midstate Bank (M&I) and McDonald Title Company, Inc. (McDonald Title). Hoida is a subcontractor that incurred losses on a building project gone awry when the general contractor and the owner of the property fraudulently misappropriated approximately $650,000 of the project's construction loan proceeds. M&I and McDonald Title were the lending bank and the disbursing agent, respectively, on the project. Hoida claimed that it was a third-party beneficiary of the owner's loan agreement with M&I. Hoida also claimed that the defendants were negligent because they did not identify the subcontractors and materialmen who worked on the project, did not verify that the progress on the work was sufficient to justify the release of loan funds, and did not secure lien waivers from Hoida, which Hoida alleges would have prevented its losses. The defendants deny Hoida's claims. They also make a prima facie showing that they did not breach the duty of [291]*291ordinary care under the circumstances by not undertaking the tasks Hoida identified and that the lack of lien waivers was not a cause-in-fact of Hoida's damage. The defendants also contend that public policy precludes Hoida's claim.

¶ 2. We conclude that Hoida has not stated a third-party beneficiary claim, and that it has not provided facts to controvert M&I's prima facie showing that it did not breach the duty of ordinary care under the circumstances. We also conclude that the claim Hoida seeks to establish against M&I is barred by the legislative determination of priority as between a lender and a subcontractor set out in Wis. Stat. § 779.01(4) (2003-04)1 and Wis. Stat. § 706.11. And finally, while we do not conclude that Hoida has overcome McDonald Title's prima facie showing that it did not breach the duty of ordinary care under the circumstances, if we were to do so, Hoida's negligence claim would be precluded by judicial public policy. Accordingly, we affirm the court of appeals.

I. BACKGROUND

¶ 3. In October 1996, The Villager at Nashotah, L.L.C. (Villager) entered into a construction loan agreement with M&I to borrow money to build four eight-unit apartment buildings in Plover, Wisconsin. The agreement between M&I and Villager was written and called for M&I to lend a total of $1,320,000 to Villager. The loan agreement set out the limits of M&I's responsibilities and it was secured by four separate real estate mortgages. Villager presented four initial draw requests for loan funds at the closing, and M&I disbursed [292]*292those funds for project start-up. M&I made arrangements with McDonald Title to make the remaining disbursements of the loan. There was no written agreement between M&I and McDonald Title to establish the terms of the disbursement arrangement; their agreement was oral, arranged between the M&I loan officer for the project, Thomas Domaszek (Domaszek), and Robert McDonald (McDonald) of McDonald Title.

¶ 4. The loan agreement between M&I and Villager stated that M&I "shall not be responsible for any aspect of the Construction ... or the procurement of lien waivers," and that M&I would have "no obligation or liability to contractors, subcontractors, laborers [or] materialmen."2 It also gave M&I the right to inspect the property at any time during construction, but explicitly stated that M&I "is in no way obligated to do so."3 Another provision required Villager to forward notices [293]*293to M&I any time that an individual or business providing goods or services to the project gave notice or demand relating to payment.4

¶ 5. Another portion of the contract, "Owner's Deposit and Disbursement of Construction Funds," sets forth the respective responsibilities of M&I and Villager with regard to disbursement of construction funds. Among other provisions within that section, provision (d), was a requirement that construction funds be disbursed only upon the owner's order and satisfaction of the requirements within the lending contract.5 The contract also gave M&I the right, at its option, to complete construction if any breach of the contract occurred.6

[294]*294¶ 6. M&I and McDonald Title agreed that McDonald Title would act as M&I's agent for disbursing the loan proceeds. Upon receipt of requests for payment from the general contractor, Packard Construction, Inc. (Packard), McDonald Title would follow a payment process and disburse funds. This payment process required the completion of a written Application and Certification for Payment form that contained Packard's itemized application for payment, the project architect's signed certificate for payment and Villager's signed certificate, as owner/borrower, authorizing payment in the amount of the application.

¶ 7. In February 1997, Packard subcontracted with Hoida for prefabricated wooden wall sections and roof trusses. Hoida commenced construction, and by February 26, Hoida had invoiced Packard for $5,705 of its work. The invoices required payment within 15 days. On March 5, 1997, as a result of not being paid, Hoida wrote to Villager and explained that pursuant to Wis. Stat. § 779.02, it possessed lien rights on the project property. However, Hoida did nothing further after sending the letter, and it continued to produce and ship materials to the construction site until April 23, 1997. Hoida also continued to invoice Packard, sending 51 separate invoices through the end of April.7 Hoida was paid only $25,000 over the course of those two months.

¶ 8. In late May or early June, after Hoida had delivered all of the product it contracted with Packard to produce, Kenneth Larsen of Hoida contacted Domaszek to advise him that Hoida had not yet been [295]*295paid. McDonald Title and M&I became concerned at about the same time because the project did not appear to be progressing as planned. On June 5, 1997, almost three months after Hoida's letter to Villager giving notice that it claimed lien rights, Hoida served Villager with a Written Notice of Intent to File Construction Lien Claims pursuant to Wis. Stat. § 779.06.8 On June 6, 1997, McDonald informed Packard that no more funds would be provided until McDonald Title and M&I received lien waivers for the funds that had been released.

¶ 9. On July 7, 1997, McDonald sent a letter to Villager, to the attention of Mike Imperl (Imperl), stating that two subcontractors had filed separate notices of Intent to File Liens and that "obviously indicates that they haven't been paid." He requested a response and said that he would seek a replacement contractor if Villager did not take appropriate action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William B. Larimore v. Midland Plastics Inc.
Court of Appeals of Wisconsin, 2025
Jenny Lou Johnson v. Michael Mewis
Court of Appeals of Wisconsin, 2025
Jori Bielawski v. Andrew J. Barth
Court of Appeals of Wisconsin, 2025
Arnold R. Kaiser v. Townline CTH-N LLC
Court of Appeals of Wisconsin, 2024
Francis G. Graef v. Applied Underwriters, Inc.
Court of Appeals of Wisconsin, 2024
Juan Delgado v. Robert Dvorak, Jr.
Court of Appeals of Wisconsin, 2023
Richard Webber v. Armslist, LLC
70 F.4th 945 (Seventh Circuit, 2023)
Erin Bauer v. Armslist, LLC
Seventh Circuit, 2023
Edbart Gonzales v. Protective Insurance Company
Court of Appeals of Wisconsin, 2023
Colin Hoffman v. Frank Gribble
Court of Appeals of Wisconsin, 2023
Rachel Slabey v. Dunn County, Wisconsin
2023 WI 2 (Wisconsin Supreme Court, 2023)
Matthew W. Murphy v. Columbus McKinnon Corporation
2022 WI 109 (Wisconsin Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2006 WI 69, 717 N.W.2d 17, 291 Wis. 2d 283, 2006 Wisc. LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoida-inc-v-m-i-midstate-bank-wis-2006.