First National Bank v. Wernhart

555 N.W.2d 819, 204 Wis. 2d 361, 1996 Wisc. App. LEXIS 1089
CourtCourt of Appeals of Wisconsin
DecidedSeptember 4, 1996
Docket96-0176
StatusPublished
Cited by3 cases

This text of 555 N.W.2d 819 (First National Bank v. Wernhart) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank v. Wernhart, 555 N.W.2d 819, 204 Wis. 2d 361, 1996 Wisc. App. LEXIS 1089 (Wis. Ct. App. 1996).

Opinion

LaROCQUE, J.

First National Bank, the mortgagee, appeals a judgment on a counterclaim in favor of Manfred and Beth Wernhart, mortgagors, for negligent distribution of construction loan funds to a residential contractor. The trial court first granted the bank a money judgment against the Wemharts based upon a foreclosure action but granted the Wemharts a partial offset based upon their counterclaim. The court concluded the bank breached its duty for payments made to the building contractor when it failed to inspect the project to determine the work was actually done and by failing to obtain lien waivers from subcontractors. The court found the bank 70% causally negligent and the Wemharts 30% causally negligent, *364 and reduced the Wernharts’ damages accordingly. The bank claims the court erred by imposing a duty of care relating to the disbursement of the Wernharts' loan proceeds and their other funds in the bank's possession, and by failing to precisely state the standard of care applied. We conclude that a mortgage lender who consents to disburse the loan proceeds and personal funds of the borrower, without further participation by the borrower, is an agent of the borrower and therefore owes a duty of due care to assure the funds are paid for work actually done and to assure that the contractor has obtained lien waivers from subcontractors. Because there was no attempt to perform, these duties, we reject the bank's arguments and affirm. 1

The Wernharts selected Richard Ingram as their general contractor to build their single family dwelling in Vilas County. They negotiated a construction contract for a price of $110,000, specifying payments "as construction moves along, balance on completion." The Wernharts contacted the bank and arranged a mortgage loan. The Wernharts also deposited an additional $15,000 with the bank to supplement the loan proceeds used to pay for construction. In response to the Wernharts’ statement that a different bank made payouts through a title company, the bank informed them that it made those payments directly to the builder. The discussions and the parties' loan agreement were silent as to inspection to determine progress of construction. Payouts, however, were to be made in accord with the contract between the Wernharts and the builder.

*365 At trial, the bank offered testimony that it was the bank's standard procedure to contact its construction loan borrowers when draws were made, but that Beth Wemhart had expressly told the bank that it would not be necessary to contact them prior to paying the builder. Beth testified that she recalled no such discussion.

As construction progressed, the bank disbursed the Wernharts' loan funds whenever Ingram presented invoices. The bank made a first payment of $15,000 in July of 1992 and a second payment of the same amount in August of 1992. In September, Ingram submitted an invoice for $25,000, which the bank paid. Thus, as of this last payment, the bank had paid out a total of $55,000, of which $40,000 consisted of mortgage funds and $15,000 consisted of the Wernharts' funds deposited with the bank.

Shortly after receiving notice of this last payment to Ingram, the Wernharts contacted the bank and instructed it not to make any additional payments without their permission. The Wernharts were concerned that Ingram had not performed sufficient work on the project to justify the amount of money he had been paid. The bank to this point did not undertake any inspections of the work site. The bank's first inspection occurred in October of 1992 in response to the Wernharts' concerns. One of the suppliers filed a lien when it was not paid, and the Wernharts paid the claim from their own funds.

Concerns about the quality of Ingram's work caused the Wernharts to dismiss him as general contractor and to hire a third party to complete the construction. The Wernharts eventually filed a lawsuit against Ingram to attempt to recover monies paid to him for uncompleted work and for poor quality *366 construction. However, Ingram filed for bankruptcy, and the Wernharts recovered only $3,500 from the bankruptcy court.

In May of 1993 the bank initiated this foreclosure action against the Wernharts. The Wernharts counterclaimed for negligent distribution of loan proceeds. At a bench trial, the bank presented testimony from its expert that there was no standard construction loan disbursement procedure recognized by Wisconsin lending institutions. He was of the opinion that lending institutions were not required to ensure the work claimed by contractors had in fact been performed. The Wernharts' two experts indicated their own standard practice was to inspect the work site before making disbursements.

The trial court granted the bank a money judgment on its foreclosure action but found for the Wernharts on their counterclaim. The trial court ordered the amount recovered by the Wernharts offset against the amount owed the bank as the result of the foreclosure. The court concluded that the bank owed a duty to the Wernharts to inspect prior to payout and that it breached that duty. The bank now appeals the judgment on the counterclaim, arguing that it owed no duty to the Wernharts and that it did not breach its duty in any event.

The bank concedes that the Wernharts' counterclaim is grounded in negligence. To sustain a cause of action for negligence, the complaining party must prove a duty of care on the part of the other, a breach of that duty, a causal connection between the conduct and the injury and actual loss or damage as a result of the injury. Nieuwendorp v. American Family Ins. Co., 191 Wis. 2d 463, 475, 529 N.W.2d 594, 599 *367 (1995). The bank challenges the trial court's conclusion that it owed the Wemharts a duty and its conclusion that it breached that duty. We begin our discussion with the question whether the bank owed thé Wemharts a duty.

Whether a duty exists in a particular case is a question of law the appellate court decides de novo. State Bank v. Arndt, 129 Wis. 2d 411, 416, 385 N.W.2d 219, 222 (Ct. App. 1986). A defendant's duty is established

when it can be said that it was foreseeable that his act or omission to act may cause harm to someone. A party is negligent when he commits an act when some harm to someone is foreseeable. Once negligence is established, the defendant is liable for unforeseeable consequences as well as foreseeable ones.

Westphal v. E.I. du Pont de Nemours & Co., 192 Wis. 2d 347, 364-65, 531 N.W.2d 386, 391-92 (Ct. App. 1995) (quoting A.E. Inv. Corp. v. Link Bldrs., Inc., 62 Wis. 2d 479, 483-84, 214 N.W.2d 764, 766 (1974)). In order to prove negligence, a party complainant must first prove that the defendant owes him a duty. Swatek v. County of Dane, 192 Wis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoida, Inc. v. M & I MIDSTATE BANK
2006 WI 69 (Wisconsin Supreme Court, 2006)
Glaeske v. Shaw
2003 WI App 71 (Court of Appeals of Wisconsin, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
555 N.W.2d 819, 204 Wis. 2d 361, 1996 Wisc. App. LEXIS 1089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-v-wernhart-wisctapp-1996.