Hoffman v. Philadelphia

95 A. 322, 250 Pa. 1
CourtSupreme Court of Pennsylvania
DecidedMay 26, 1915
DocketAppeal, No. 483
StatusPublished
Cited by19 cases

This text of 95 A. 322 (Hoffman v. Philadelphia) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoffman v. Philadelphia, 95 A. 322, 250 Pa. 1 (Pa. 1915).

Opinion

Opinion by

Mr. Justice Elkin,

This is an action for damages growing out of a condemnation whereby a portion of the land of appellant was taken by the city for park purposes. While there are twenty-one assignments of error, many of them [3]*3relate to unimportant and immaterial details which would not justify a reversal if standing alone, but several of them are based on the main contentions upon which appellant very confidently relies. The most important question in the case is whether the jury were properly instructed as to compensation for delay in payment. The ordinance directing the opening of the parkway and condemning the land for park purposes was approved 14 December, 1910, and the damages have not yet been paid. The jury of view to assess damages was appointed in January, 1911, but did not file their report until August, 1912. From the award of viewers both sides appealed and the litigation has been pending from that time to the present. There is no evidence to show that the parties, or either of them, made any effort to adjust the amount of damages which would be a fair compensation for the land taken. The case took the usual course before the viewers and in the courts, both parties standing upon the testimony of such witnesses as could be produced in support of their respective contentions relating to the difference in value before and after the taking. If the law contemplates, as this court has said it does, that in the first instance the parties will themselves attempt to agree upon the amount of damages to be paid by way of just compensation for the land taken or injured, then these litigants are equally at fault because neither party attempted to make an amicable settlement with the other at any stage of the proceedings. The city condemned the land and took possession. The owner has been deprived of his property and can only assert a claim for damages. This was the situation when the case was tried in the court below. In answer to points and in his general charge the learned trial judge instructed the jury in substance as follows:

“If you believe that there has been an unjust, arbitrary and improper delay without 'just cause, you may consider the question of compensation for delay under the principle of which I have spoken. On the [4]*4other hand, if you find from the evidence and all the facts in the case that there was an unreasonable, unwarrantable and stubborn claim by the plaintiff for excessive damages, and that the city was justified in resisting the claim upon the advice of experts in whose opinion its officials had the right to rely, then it was not only their right but their duty to contest this claim, and you should give no sum in allowance for this element of damages.”

To the same effect but differently phrased, this instruction was repeated several times in answer to points and in the general charge. There was no evidence that plaintiff had made any claim for damages, unreasonable, unwarrantable or otherwise, prior to the appointment of viewers, or indeed at any later time, except as he endeavored to sustain the amount claimed in his declaration by witnesses produced before the viewers and at the trial. Nor did the city produce any testimony to show that plaintiff had stubbornly resisted any offers to agree upon the amount of damages to which he was fairly entitled. Both sides acted npon the theory that they would take their chances on the result of a law suit rather than attempt to agree among themselves. These are the' facts, what is the law? The clearest and best exposition of what the law contemplates in the nature of damages for delay in payment in this class of cases will be found in the opinion written by our Brother Stewart in Wayne v. Penna. R. R. Co., 231 Pa. 512. It was there very well said that the right of the owner to any use of the land, inconsistent with the use for which it was condemned, ceases as soon as it is taken, and his right to damages immediately vests. The distinction between interest as an incident of debt and damages for delay in payment was clearly pointed out. As to the right of the owner to recover damages for delay in payment, this court speaking through Brother Stewart in that case said (p. 515) :

“Whether the owner is entitled to damages on this account, and if so, how much, are questions sometimes for [5]*5the jury. Prima facie, he is entitled to damages for delay in payment. The law contemplates that in the first instance parties will themselves agree upon the amount. If they do agree, it is presently payable and interest attaches as an incident. If they fail to agree and either appeals to the court, it becomes a question of damages and here, again prima facie, the owner is entitled to damages for the delay. But in fact he may not be so entitled. If he has disappointed the law and stubbornly refused to name an amount which he would be willing to accept as compensation, or in the same spirit has been extortionate in his demands, and has named a sum exorbitant and unreasonable, a jury might well find that he has himself unjustifiably provoked the delay and deny him all damages therefor. But the law will not presume any such conduct on his part. If the 'corporation would excuse itself for its delay on any such ground, the burden is on it to show the excusing facts; failing in this, the right of the owner to damages in such amount as the jury may assess is unquestionable. The right results as a matter of law; the quantum alone is for the jury to determine.”

And thus the legal right, incidentally involving the method of procedure and the burden of proof, is so clearly stated that he who runs may read and understand. In the case at bar the city did not undertake to prove any excusing facts to justify the delay, nor does the evidence show that appellant had stubbornly, or for any other reason, refused to name an amount he would be willing to accept as compensation — indeed he was not asked to name an amount that would be satisfactory to him. Aside from the amount stated in his declaration, and which he produced witnesses to sustain at the trial, there is nothing to even indicate what he demanded. Under these circumstances it was error for the learned trial judge to instruct the jury that if they found from the evidence there was an unreasonable, unwarrantable and stubborn claim by the plaintiff for excessive dam[6]*6ages, they should not allow any sum as damages for delay in making payment. The facts did not warrant this instruction which entirely ignored the prima facie right of plaintiff to damages for delay and that the burden was on the city to establish the excusing circumstances.

No amount was demanded in this case except in the statement of claim filed in the court below and the plaintiff substantially sustained his claim by witnesses produced at the trial. It is true that the witnesses of appellee fixed the depreciation in market value much below the amount claimed, but depreciation in market value before and after the taking was the question in controversy between the parties, and we see nothing in the record to justify a departure from the rule as stated in Wayne v. Penna. R. R. Company, above cited.

To sustain the instruction of the learned trial judge relating to the question of compensation for delay appellee relies on Pierce v. Lehigh Valley Coal Co., 232 Pa. 170; Duffy v. York Haven Water & Power Co., 242 Pa. 146, and other cases of like import. These were cases sounding in tort and there was no actual taking of property under the power of eminent domain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. 21.1 Acres of Land
433 A.2d 915 (Commonwealth Court of Pennsylvania, 1981)
Hay v. Commonwealth
21 Pa. D. & C.3d 567 (Somerset County Court of Common Pleas, 1980)
Elizabeth Township Sanitary Authority Case
198 A.2d 304 (Supreme Court of Pennsylvania, 1964)
Wolf v. Commonwealth
170 A.2d 557 (Supreme Court of Pennsylvania, 1961)
Springer v. Allegheny County
165 A.2d 383 (Supreme Court of Pennsylvania, 1960)
Waugh v. Commonwealth
146 A.2d 297 (Supreme Court of Pennsylvania, 1958)
Gravity Fill Service Station, Inc. v. Turnpike Commission
85 Pa. D. & C. 190 (Alleghany County Court of Common Pleas, 1953)
Seltzer v. Commonwealth
55 Pa. D. & C. 59 (Schuylkill County Court of Common Pleas, 1946)
Fidelity-Philadelphia Trust Co. v. Commonwealth
42 A.2d 585 (Supreme Court of Pennsylvania, 1945)
Johnson's Petition
23 A.2d 880 (Supreme Court of Pennsylvania, 1941)
United States v. 20.08 Acres of Land
35 F. Supp. 265 (W.D. Pennsylvania, 1940)
Brewer v. Blue Mountain Consolidated Water Co.
191 A. 408 (Superior Court of Pennsylvania, 1937)
Pattison v. Buffalo, Rochester & Pittsburgh Ry. Co.
112 A. 101 (Supreme Court of Pennsylvania, 1920)
Whitcomb v. Philadelphia
107 A. 765 (Supreme Court of Pennsylvania, 1919)
Cox v. Pennsylvania Co.
106 A. 70 (Supreme Court of Pennsylvania, 1919)
Hoffman v. Philadelphia
104 A. 674 (Supreme Court of Pennsylvania, 1918)
Rider v. York Haven Water & Power Co.
99 A. 798 (Supreme Court of Pennsylvania, 1916)
Hirsch v. North Braddock Borough
97 A. 113 (Supreme Court of Pennsylvania, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
95 A. 322, 250 Pa. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoffman-v-philadelphia-pa-1915.